Summary of Public Information Session for the U.S. Nuclear Regulatory Commission (NRC) Staff to Describe Its License Renewal Process (Letter, Enclosure 1 and Enclosure 2)
ML042240048
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 08/11/2004
From: Tuan Le
NRC/NRR/DRIP/RLEP
To:
Le N. B., NRR/DRIP/RLEP, 415-1458
References
Download: ML042240048 (8)


Text

August 11, 2004 LICENSEE:

Constellation Energy FACILITY:

Nine Mile Point Nuclear Station, Units 1 and 2

SUBJECT:

SUMMARY

OF PUBLIC INFORMATION SESSION FOR THE U.S. NUCLEAR REGULATORY COMMISSION (NRC) STAFF TO DESCRIBE ITS LICENSE RENEWAL PROCESS On July 8, 2004, the U.S. Nuclear Regulatory Commission (NRC) staff conducted a Public Information Session to describe the license renewal process to the public living near Nine Mile Point Nuclear Station, Units 1 and 2. The purpose of the meeting was to provide information describing the license renewal process and how the public can participate. The meeting was held at the Joint News Center at 10 Airport Road in Fulton, New York. A list of meeting attendees is provided in Enclosure 1, and the meeting agenda is provided in Enclosure 2. A copy of the presentation slides used by the NRC staff are provided in Enclosure 3.

After welcoming the public participants, the NRC staff presented slides describing the NRCs license renewal process and how the public can participate in the process. The staff then answered questions from members of the public.

/RA/

Tommy Le, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-220 and 50-410

Enclosures:

As stated cc w/enclosures: See next page

Package: ML042240038; Letter, Enclosure 1 & 2: ML042240048; : ML042240058 DOCUMENT NAME:C:\\ORPCheckout\\FileNET\\ML042240048.wpd OFFICE:

PM:RLEP SE:RLEP LA:RLEP SC:RLEP NAME:

TLe SSL for OYee YEdmonds SLee DATE:

08/11/04 08/11/04 07/22/04 08/11/04

DISTRIBUTION: Dated: August 11, 2004 Package Accession No: ML042240038; Letter, Enclosure 1 & 2: ML042240048 : ML042240058 HARD COPY RLEP RF T. Le (PM)

O. Yee E-MAIL:

RidsNrrDrip RidsNrrDe G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair RidsNrrDssa RidsNrrDipm D. Thatcher R. Pettis G. Galletti C. Li M. Itzkowitz (RidsOgcMailCenter)

R. Weisman M. Mayfield A. Murphy S. Smith (srs3)

S. Duraiswamy Y. L. (Renee) Li RLEP Staff C. Holden R. Laufer P. Tam B. Fuller, RI E. Knutson, RI J. Trapp, RI T. Mensah OPA ATTENDANCE LIST NRCS LICENSE RENEWAL PUBLIC INFORMATION SESSION JOINT NEWS CENTER FULTON, NEW YORK JULY 8, 2004 Participants Affiliations Kate Cooper Citizens Awareness Network Thomas Dellwo Citizens Awareness Network Tim Juddon Citizens Awareness Network Peter Bullock Constellation & Resident Oswego County Rich Breyne Constellation & Resident Oswego County John Dosa Constellation Energy Robert Godlen Constellation Energy Anil Juliana Constellation Energy Jill Lyon Constellation Energy Peter Mazzaferro Constellation Energy Gary A. Polinsky Constellation Energy Dop Randau Constellation Energy Dennis Vandeputte Constellation Energy Russ Wells Constellation Energy J. Evans LIPA Jean Chambers Resident, Oswego area, NY Janelle Reichert News 10 Now Gordon Hunegs U.S. Nuclear Regulatory Commission (NRC)

P.T. Kuo NRC Tommy Le NRC Sam Lee NRC Michael Morgan NRC Saiwah Ng NRC Neil Sheehan NRC Tyson Smith NRC Chris Sydnor NRC Jim Trapp NRC Tom Gurdziel Jason Luna Ed Stronski Renee Vogelsang AGENDA FOR PUBLIC INFORMATION SESSION FOR THE NRC STAFF TO DESCRIBE THE LICENSE RENEWAL PROCESS FULTON, NEW YORK JOINT NEWS CENTER AGENDA (Times are approximate)

JULY 8, 2004 I.

Introduction/Opening remarks 7:00 p.m. - 7:15 p.m.

II.

Presentation of the NRCs license renewal process 7:15 p.m. - 7:45 p.m.

III.

Public Questions 7:45 p.m. - 8:00 p.m.

V.

Adjourn 8:00 p.m.

Nine Mile Point Nuclear Station, Unit Nos. 1 & 2 cc:

Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 126 Lycoming, NY 13093 Supervisor Town of Scriba Route 8, Box 382 Oswego, NY 13126 Mr. James R. Evans LIPA P.O. Box 129 Lycoming, NY 10393 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Mr. Paul D. Eddy Electric Division NYS Department of Public Service Agency Building 3 Empire State Plaza Albany, NY 12223 C. Adrienne Rhodes Chairman and Executive Director State Consumer Protection Board 5 Empire State Plaza, Suite 2101 Albany, NY 12223-1556 Mark J. Wetterhahn, Esquire Winston & Strawn 1400 L Street, NW Washington, DC 20005-3502 Mr. Michael J. Wallace President Nine Mile Point Nuclear Station, LLC c/o Constellation Energy Group, Inc.

750 East Pratt Street Baltimore, MD 21202 Mr. James M. Petro, Jr., Esquire Counsel Constellation Energy Group 750 East Pratt Street, 5th Floor Baltimore, MD 21202 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Fred Emerson Nuclear Energy Institute 1776 I St., NW, Suite 400 Washington, DC 20006-3708 Mr. Mark Flaherty Manager - Fleet Licensing R.E. Ginna Nuclear Power Plant 1503 Lake Rd.

Ontario, NY 14519 Mr. M. Steven Leonard General Supervisor - Nuclear Regulatory Matters Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093 Mr. Peter Mazzaferro Site Project Manager - License Renewal Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093

Nine Mile Point Nuclear Station, Unit Nos. 1 & 2 cc:

Mr. Mike Heffley Senior Vice President and Chief Nuclear Officer Constellation Generation Group 1997 Annapolis Exchange Parkway Suite 500 Annapolis, MD 21401 Mr. James A. Spina Vice President Nine Mile Point Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093