ML042180294
ML042180294 | |
Person / Time | |
---|---|
Issue date: | 08/05/2004 |
From: | Marshall M NRC/NRR/DLPM/LPD2 |
To: | Nuclear Energy Institute |
Marshall M NRR/DLPM 415-2734 | |
References | |
+KBR1SISP20050504, TAC MA6454 | |
Download: ML042180294 (4) | |
Text
August 5, 2004 STAKEHOLDERS: Nuclear Energy Institute, Westinghouse Owners Group, and Members of the Public ISSUE: Generic Safety Issue 191, PWR [Pressurized-Water Reactor] Sump Performance
SUBJECT:
SUMMARY
OF MAY 19, 2004, MEETING WITH NUCLEAR ENERGY INSTITUTE REGARDING INTERIM SAFETY ASSESSMENTS CONCERNING LICENSEES PLANT-SPECIFIC SUMP EVALUATIONS (TAC NO. MA6454)
On May 19, 2004, a Category 2 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Nuclear Energy Institute (NEI) at NRC Headquarters, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland. The purpose of the meeting was for NEI to inform the NRC staff of its proposal for interim safety assessments for licensees that complete a plant-specific evaluation of sump performance. A list of attendees is provided as an Attachment. Neither NEI representatives nor the NRC staff used handouts or other presentation aids during the meeting.
The original purpose of the meeting was for NEI to inform the NRC staff of its planned development of a proposal for interim safety assessments for licensees that complete a plant-specific evaluation of sump performance and discover a nonconformance. However, NEI did not present any such proposal. Instead, NEI asked the NRC staff several questions about the implementation of the proposed Generic Letter (GL) 2004-xx, "Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accidents at Pressurized Water Reactors," which was issued for public comment. Many of the questions concerned: (1) time needed to implement the actions necessary to respond to the GL, (2) NRC review and inspection of boiling-water reactors resolution of strainer blockage issue, (3) regulatory basis for the GL, (4) whether the GL constituted a backfit, and (5) applicability of PWRs licensing bases. Since the meeting, many of the questions raised by the NEI representatives have been submitted to the NRC by industry representatives as comments on the proposed GL, prior to the end of the public comment period of June 1, 2004, for the GL.
Members of the public were in attendance. Three Public Meeting Feedback forms were received. Comments received included the following: (1) the noticed meeting purpose was not addressed, (2) meeting was similar to a meeting held earlier in the day on the proposed GL, and (3) the availability of a telephone conference line was not publicized. These have been forwarded to the NRR Senior Communications Analyst who will forward them to the Office of the Executive Director for Operations.
2 Please direct any inquiries to me, at 301-425-2734, or mxm2@nrc.gov.
/RA/
Michael L. Marshall, Jr., Acting Chief, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
List of Attendees cc w/atts: Anthony R. Pietrangelo, Senior Director Risk Regulation Nuclear Generation Nuclear Energy Institute 1776 I Street, NW Suite 400 Washington, DC 20006-3708 Elliot Rosenfeld State of New Jersey Bureau of Nuclear Engineering 33 Arctic Parkway Post Office Box 415 Trenton, New Jersey 08625-0415
2 Please direct any inquiries to Michael L. Marshall, Jr., at 301-425-2734, or mxm2@nrc.gov.
/RA/
Michael L. Marshall, Jr., Acting Chief, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation
Attachment:
List of Attendees cc w/atts: Anthony R. Pietrangelo, Senior Director Risk Regulation Nuclear Generation Nuclear Energy Institute 1776 I Street, NW Suite 400 Washington, DC 20006-3708 Elliot Rosenfeld State of New Jersey Bureau of Nuclear Engineering 33 Arctic Parkway Post Office Box 415 Trenton, New Jersey 08625-0415 DISTRIBUTION:
PUBLIC RArchitzel EMerschoff PDII-2 R/F BPJain JArroyo RidsNrrPM RidsNrrDlpm MMayfield RCaruso RidsOgcRp JBoska JJolicoeur RidsAcrsAcnwMailCenter JHannon JZimmerman RidsNrrOd (JDyer/RBorchardt) MKowal CJackson RidsNrrDlpm (LMarsh) WKemper RJasinki RidsNrrDlpmLpdii (EHackett) AHsia RidsRgn1MailCenter RidsNrrDlpmLpdii-2 (MMarshall) JBeall RidsRgn2MailCenter RidsNrrLABClayton RidsOpaMail (SBurnell) RidsRgn3MailCenter TMensah (Comm. Analyst) DSolorio RidsRgn4MailCenter RHogan (EDO) TYChang ALarretta RidsEdoMailCenter (LReyes) RidsNrrDssa (SBlack/MJohnson) DCullison RElliott ADAMS Accession No.: ML042180294 NRC-001 OFFICE PDII-2/SC PDII-2/LA PDII-2/BC NAME MMarshall BClayton EHackett DATE 8/3/04 8/3/04 8/5/04
3 OFFICIAL RECORD COPY
NEI/NRC GSI-191 Meeting May 19, 2004 List of Attendees Name Organization Name Organization Marcus Dinglor WCHDC Mike Schoppman NEI Chuck Feist TXU Energy Johy Meyer TXU Power Gretachew Tesfaye CEG Mark Kostelnik CEG Addison Ricker Proto-Power Andre Drake Constellation Energy A. K. Singh Sargent & Lundy John Boska NRC John Walker Framatome ANP Paul Willoughby Dominion Resources Aaron Smith Enercon Services Rob Choromokos Alion Science John Lamb NRC Bill Reckley NRC Dave Cullison NRC Ralph Caruso NRC Jose Arroyo NRC Wes McGoun Progress Energy Rob Elliott NRC Don Eggett AES Corp.
Angie Larretta NRC David Solorio NRC Michael Johnson NRC Tony Pietrangelo NEI Pedro Salas TVA John Butler NEI Tim Andreychek Westinghouse Steven Winter NMC Kazvhiki Kishisku JAPC William Rinkals Westinghouse Gordon Hurt PCI Greg Quitoriano PG&E Ralph Architzel NRC Mark Kowal NRC Bill Kemper NRC Dave Lochbaum UCS Steven Doltey McGraw Hill George Graney MPR Altheia Wyche SERCH Russ Oakley Duke Energy Licensing/Bechtel Michael Marshall NRC ATTACHMENT