General Electric Nuclear Test Reactor - Technical Specification Typographical Error Correction, Amendment No. 21
ML042100347
Person / Time
Site: Vallecitos Nuclear Center
Issue date: 08/19/2004
From: Mendonca M
NRC/NRR/DRIP/RNRP
To: Doreen Turner
General Electric Co
Witt K, NRC/NRR/DRIP/RNRP, 415-4075
References
TAC MC3775
Download: ML042100347 (3)


Text

August 19, 2004 Mr. David Turner, Manager Vallecitos and Morris Operations Vallecitos Nuclear Center General Electric Company 6705 Vallecitos Road Sunol, CA 94586

SUBJECT:

GENERAL ELECTRIC NUCLEAR TEST REACTOR - CORRECTION OF TECHNICAL SPECIFICATION TYPOGRAPHICAL ERROR (TAC NO. MC3775)

Dear Mr. Turner:

As discussed in your letter dated June 22, 2004, TS page 4-6 is incorrect in that paragraph 4.4.3.2 specifies "3.4.3.5" rather than "3.4.3.4." The typographical error was introduced in License Amendment No. 21 dated April 20, 2001. This typographical error was not specifically requested by you, the licensee but was inadvertently introduced in the Technical Specifications for Amendment No. 21. The error was neither addressed in a notice to the public, nor approved by the NRC. The NRC staff is issuing the attached correction to the typographical error on TS page 4-6, as requested in your letter. Please replace TS Page 4-6 with the enclosed page.

The revised page is identified by issuance date and contains a vertical line indicating the area of typographical correction. This letter is in accordance with the NRC policy as specified in "The Non-Power Reactor Project Managers Handbook," dated September 30, 1998, and "Proposed Guidance for Correction of Technical Specification Typographical Errors," SECY 238 dated November 19, 1996.

If you have any questions regarding this letter, please contact Kevin Witt at 301-415-4075, or by Internet e-mail at kmw@nrc.gov.

Sincerely,

/RA/

Marvin M. Mendonca, Senior Project Manager Research and Test Reactors Section New, Research and Test Reactors Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-73

Enclosure:

TS Page 4-6 cc w/enclosure: Please see next page

General Electric Company (NTR) Docket No. 50-73 cc:

Mr. Steve Hsu Radiologic Health Branch State Department of Health Service P.O. Box 942732 Sacramento, CA 94234-7320 California Department of Health ATTN: Chief, Environmental Radiation Control Unit Radiological Health Section 714 P Street, Room 498 Sacramento, CA 95814 Mr. Chuck Bassett, Manager Regulatory Compliance Vallecitos and Morris Operations Vallecitos Nuclear Center General Electric Company 6705 Vallecitos Road Sunol, CA 94586 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611 Mr. Chris Hamilton Senior Licensing Engineer Certified Six Sigma Green Belt Vallecitos Nuclear Center Sunol, CA 94586 Mr. Harold Neems General Electric Company Nuclear Energy Business Operations 175 Cutner Avenue Mail Code 123 San Jose, CA 95125

August 19, 2004 Mr. David Turner, Manager Vallecitos and Morris Operations Vallecitos Nuclear Center General Electric Company 6705 Vallecitos Road Sunol, CA 94586

SUBJECT:

GENERAL ELECTRIC NUCLEAR TEST REACTOR - TECHNICAL SPECIFICATION TYPOGRAPHICAL ERROR, AMENDMENT NO. 21 (TAC NO. MC3775)

Dear Mr. Turner:

As discussed in your letter dated June 22, 2004, TS page 4-6 is incorrect in that paragraph 4.4.3.2 specifies "3.4.3.5" rather than "3.4.3.4." The typographical error was introduced in License Amendment No. 21 dated April 20, 2001. This typographical error was not specifically requested by you, the licensee but was inadvertently introduced in the Technical Specifications for Amendment No. 21. The error was neither addressed in a notice to the public, nor approved by the NRC. The NRC staff is issuing the attached correction to the typographical error on TS page 4-6, as requested in your letter. Please replace TS Page 4-6 with the enclosed page.

The revised page is identified by issuance date and contains a vertical line indicating the area of typographical correction. This letter is in accordance with the NRC policy as specified in "The Non-Power Reactor Project Managers Handbook," dated September 30, 1998, and "Proposed Guidance for Correction of Technical Specification Typographical Errors," SECY 238 dated November 19, 1996.

If you have any questions regarding this letter, please contact Kevin Witt at 301-415-4075, or by Internet e-mail at kmw@nrc.gov.

Sincerely,

/RA/

Marvin M. Mendonca, Senior Project Manager Research and Test Reactors Section New, Research and Test Reactors Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-73

Enclosure:

TS Page 4-6 cc w/enclosure: Please see next page DISTRIBUTION:

PUBLIC RNRP/R&TR r/f TDragoun AAdams JLyons OGC EHylton RidsNrrDrip SHolmes CBassett PYoung MMendonca WEresian PIsaac GHill (2) PDoyle PMadden DHughes KWitt ACCESSION #: ML042100347 TEMPLATE #: NRR-106 OFFICE RTRS RTRS:PM RTRS:LA OGC RTRS:C NAME KWitt:vmj* MMendonca EHylton* MBupp* PMadden DATE 7/ 28 /2004 8/ 5 /2004 8/ 11 /2004 8/ 16 /2004 8/ 18 /2004 C = COVER E = COVER & ENCLOSURE N = NO COPY OFFICIAL RECORD COPY

  • See previous concurrence

NEDO-32765 4.3 REACTOR COOLANT SYSTEM Specifications regarding surveillance requirements of the reactor coolant system are included in the reactor safety system, Specification 4.2, Tables 4-1 and 4-2.

4.4 REACTOR CELL AND VENTILATION SYSTEM 4.4.1 Applicability This specification applies to the surveillance requirements for the reactor cell and ventilation system.

4.4.2 Objective The objective of this specification is to ensure that the reactor ventilation system is in satisfactory condition to provide adequate confinement and to control the release of radioactivity to the environment.

4.4.3 Specification 4.4.3.1 The reactor cell negative pressure, with respect to the control room, shall be verified prior to the first reactor startup of each day.

4.4.3.2 Surveillance requirements of the instrumentation and equipment required to comply with Specifications 3.4.3.2, 3.4.3.3 and 3.4.3.4 shall be as listed in Specification 4.2, Table 4-2. l 4.4.4 Bases Operation in accordance with Specification 4.4.3.l ensures that contaminated reactor cell air is exhausted through the ventilation system. This minimizes the possibility of airborne contamination release to surrounding areas.

4-6 Rev. August XX, 2004 l