SAFEGUARDS INFORMATION SAFEGUARDS INFORMATION WARNING: Violation of Section 147 of the Atomic Energy Act, Safeguards Information is subject to Civil and Criminal Penalties July 9, 2004 Mr. Thomas Coutu Site Vice President Nuclear Management Company, Inc.
N 490 Highway 42 Kewaunee, WI 54216-9511
SUBJECT:
KEWAUNEE NUCLEAR POWER PLANT - REQUEST FOR ADDITIONAL INFORMATION RE: TRAINING AND QUALIFICATION PLAN (TAC NO.
Dear Mr. Coutu:
In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for Kewaunee Nuclear Power Plant.
The Nuclear Regulatory Commission staff is reviewing your submission and has determined based on its review of your Training and Qualification Plan that a request for additional information (RAI) is necessary in order to complete its evaluation. Please respond to the enclosed RAI within 10 working days from the date of receipt. If circumstances result in the need to revise the target response date, please contact me at (301)415-3498.
Sincerely,
/RA/
Bhalchandra Vaidya, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-305
Enclosure:
As stated cc w/o encl: See next page NOTICE: The Enclosure contains Safeguards Information. Upon separation from the Enclosure, this letter is DECONTROLLED.
July 9, 2004 Mr. Thomas Coutu Site Vice President Nuclear Management Company, Inc.
N 490 Highway 42 Kewaunee, WI 54216-9511
SUBJECT:
KEWAUNEE NUCLEAR POWER PLANT - REQUEST FOR ADDITIONAL INFORMATION RE: TRAINING AND QUALIFICATION PLAN (TAC NO.
Dear Mr. Coutu:
In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for Kewaunee Nuclear Power Plant.
The Nuclear Regulatory Commission staff is reviewing your submission and has determined based on its review of your Training and Qualification Plan that a request for additional information (RAI) is necessary in order to complete its evaluation. Please respond to the enclosed RAI within 10 working days from the date of receipt. If circumstances result in the need to revise the target response date, please contact me at (301)415-3498.
Sincerely,
/RA/
Bhalchandra Vaidya, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-305
Enclosure:
As stated cc w/o encl: See next page DISTRIBUTION:
SPRT R/F RidsNsirDns RidsNrrDlpm OGC ACRS C. Lyon L. Raghavan B. Ruland S. Reynolds, RIII ADAMS Accession Number: ML042100118 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR SPRT/NRR/SC NAME BVaidya CHawes JPeralta JNakoski DATE 07/09/04 07/09/04 07/09/04 07/09/04 OFFICIAL RECORD COPY
Kewaunee Nuclear Power Plant cc:
John Paul Cowan Executive Vice President &
Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, MI 54016 Plant Manager Kewaunee Nuclear Power Plant N490 Highway 42 Kewaunee, WI 54216-9511 Manager, Regulatory Affairs Kewaunee Nuclear Power Plant N490 Highway 42 Kewaunee, WI 54216-9511 David Molzahn Nuclear Asset Manager Wisconsin Public Service Corporation 600 N. Adams Street Green Bay, WI 54307-9002 Resident Inspectors Office U. S. Nuclear Regulatory Commission N490 Hwy 42 Kewaunee, WI 54216-9511 Regional Administrator, Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 Jonathan Rogoff Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Larry L. Weyers Chairman, President and CEO Wisconsin Public Service Corporation 600 North Adams Street Green Bay, WI 54307-9002 David Zellner Chairman - Town of Carlton N2164 County B Kewaunee, WI 54216 Mr. Jeffery Kitsembel Electric Division Public Service Commission of Wisconsin PO Box 7854 Madison, WI 53707-7854 Mr. Thomas Coutu Site Vice President Kewaunee Nuclear Power Plant Nuclear Management Company, LLC N490 Highway 42 Kewaunee, WI 54216-9511