Letter Sequence Other |
---|
|
|
MONTHYEARML0414604492004-05-17017 May 2004 Response to Nuclear Regulatory Commission (NRC) Requests for Additional Information (Rais) Regarding Severe Accident Mitigation Alternatives Project stage: Other ML0418903762004-07-0606 July 2004 Summary of Telephone Conferences Between the U.S. Nuclear Regulatory Commission Staff and Indiana Michigan Power Company Representatives Regarding the Severe Accident Mitigation Alternatives Analysis Related to the Cook Nuclear Plant, Units Project stage: Other ML0513201652005-05-12012 May 2005 5-12-05 - Results of the Severe Accident Mitigation Alternative (SAMA) Review for Donald C. Cook Nuclear Plant, Units 1 and 2 Project stage: Other 2004-07-06
[Table View] |
Similar Documents at Cook |
---|
Category:Meeting Summary
MONTHYEARML23215A1662023-08-17017 August 2023 Summary of July 31, 2023, Meeting with Indiana Michigan Power Company Regarding Operating Power Sources for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML23199A2402023-07-19019 July 2023 Summary of the July 13, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 ML22355A6022023-01-0303 January 2023 Summary of December 14, 2022, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22318A1992022-11-21021 November 2022 Summary of November 7, 2022, Meeting with Indiana Michigan Power Company Regarding Neutron Flux Instrumentation for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML22154A5342022-06-0909 June 2022 Summary of the June 1, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML22011A2732022-01-13013 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Planned Final Response to Generic Letter 2004-02 for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21349B3092022-01-0303 January 2022 Summary of Meeting with Indiana Michigan Power Company to Discuss Potential Changes to the Quality Assurance Program for Donald C. Cook Nuclear Plant, Units 1 and 2 ML21202A1072021-07-23023 July 2021 Summary of July 20, 2021, with Indiana Michigan Power Company to Discuss Potential Changes to the Emergency Plan for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML21196A5182021-07-15015 July 2021 July 8, 2021, Summary of Public Webinar to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant ML21082A0052021-03-24024 March 2021 Summary of March 19, 2021, with Indiana Michigan Power Company Regarding Containment Water Level Channels for Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20349A0152020-12-17017 December 2020 Summary of November 30, 2020, Teleconference with Indiana Michigan Power Company Regarding a Planned License Amendment Request to Extend the Containment Integrated Leak Rate Testing Interval for Donald C. Cook Nuclear Plant, Unit No. 2 ML20282A2712020-10-14014 October 2020 Summary of October 2, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML20248H4752020-09-10010 September 2020 Summary of August 6, 2020, Teleconference with Indian Michigan Power Company Related to Steam Generator Eddy Current Testing License Amendment Request ML20209A6032020-07-27027 July 2020 Summary of the July 21, 2020, Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of the Donald C. Cook Nuclear Plant, Units 1 and 2 ML20133K1282020-05-21021 May 2020 Summary of May 4, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20121A0692020-05-0404 May 2020 Summary of Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML20041C9492020-02-13013 February 2020 Summary of February 6, 2020, Teleconference with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19350A0552019-12-30030 December 2019 Summary of 12/12/2019 Meeting with Indiana Michigan Power Company, License Amendment Request for D.C. Cook Nuclear Plant, Units 1 and 2 to Delete Surveillance Requirement Related to Diesel Generator Load Test Resistor Banks ML19212A5652019-07-30030 July 2019 Summary of Public Open House to Discuss NRC Activities and the 2018 End-Of-Cycle Performance Assessment of Donald C. Cook Nuclear Generating Plant, Units 1 and 2 ML19141A0622019-06-0606 June 2019 Summary of November 19, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19099A3262019-04-16016 April 2019 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML19067A0482019-03-12012 March 2019 Summary of Public Teleconference with Indiana Michigan Power Co. (I&M) Review of LAR for Approval of Leak-Before-Break Methodology for Reactor Coolant System Small Diameter Piping (EPID-2019-LLA-0054) ML18334A0402018-12-13013 December 2018 Summary of Meeting with Indian Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML18109A0692018-04-26026 April 2018 Summary of April 10, 2018, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML18052B0542018-02-26026 February 2018 Summary of February 15, 2018, Meeting with Indian Michigan Power Company Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 (EPID L-2018-LRM-0008 ML18018B1382018-01-22022 January 2018 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit No. 1 ML17265A4922017-10-0404 October 2017 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 2 ML17235B1232017-08-23023 August 2017 Summary of the July 27, 2017, Open House to Discuss the 2016 End-of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant ML17082A0762017-03-27027 March 2017 Summary of March 20, 2017, Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Unit Nos. 1 and 2 ML16308A1132016-11-16016 November 2016 Summary of October 27, 2016, Public Meeting with Indiana Michigan Power Company Regarding the Donald C. Cook Nuclear Plant, Units 1 and 2 ML16244A7062016-08-30030 August 2016 Summary of the August 22, 2016, Donald C. Cook Public Meeting ML16193A5912016-07-15015 July 2016 Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15271A0462015-10-0505 October 2015 Summary of Public Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML15237A3362015-09-0202 September 2015 Summary of August 24, 2015, Telephone Call to Provide Verbal Authorization of Relief Request ISIR-4-06, Alternate Repair of Socket Weld ML15107A0982015-04-24024 April 2015 April 14, 2015, Summary of Meeting with Indiana Michigan Power Company Regarding Donald C. Cook Nuclear Plant, Units 1 and 2 ML14311A3182014-11-14014 November 2014 Summary of Conference Call with Donald C. Cook Nuclear Plant, Unit 1 Regarding the Fall 2014 Steam Generator Inspections ML14231A0752014-08-27027 August 2014 Summary of the August 8, 2014, Pre-Application Meeting with American Electric Power Company to Discuss a Future License Amendment Request for Alternative Source Term and TSTF-490 ML14209A9422014-07-30030 July 2014 July 9, 2014, Summary of Category 1, Public Meeting with Indiana Michigan Power Company to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2.1 ML14199A0802014-07-18018 July 2014 Summary of July 8, 2014 Donald C. Cook Public Annual Assessment Meeting ML14023A3872014-01-30030 January 2014 Summary of Joint Steering Committee Meeting to Discuss Activities Related to Lessons-Learned from the Fukushima Dai-Ichi Nuclear Power Plant Event ML13210A2272013-08-0202 August 2013 6/26/13, Summary of Pre-Application Meeting to Discuss Pending License Amendment Request to Modify the CNP Unit 1 Normal Operating Pressure and Temperature ML13189A2322013-07-15015 July 2013 Summary of Conference Telephone Call Regarding the 2013 Steam Generator Tube Inspections ML13154A4062013-06-0303 June 2013 5/30/2013 - Summary of the D.C. Cook Public Meeting ML12159A4022012-06-0707 June 2012 May 31, 2012 Summary of Public Meeting to Discuss the 2011 Annual Assessment Results for D.C. Cook ML1133307782011-11-29029 November 2011 Record of Discussion by Phone on 10/5/11 Regarding Steam Generator Inspection ML11129A2422011-06-0808 June 2011 Summary of Meeting with Indiana Michigan Power Company to Discuss Issues Related to a Future Submittal Using NFPA 805 ML0931305572009-11-0909 November 2009 Summary of Public Meeting with Staff from the D.C. Cook Nuclear Power Plant Regarding the September 2008 Unit 1 Turbine Vibration Event ML0915905922009-06-0808 June 2009 Summary of Open House to Discuss NRC Activities, Nuclear Power Issues, and the Donald C. Cook Nuclear Power Plant 2008 End-Of-Cycle Plant Performance Assessment ML0809200582008-04-18018 April 2008 Summary of Phone Call with Licensees Concerning Sump Strainer Head Loss Testing ML0811203302008-04-18018 April 2008 EOC Public Meeting Summary 2023-08-17
[Table view] Category:Note
MONTHYEARML0720505282006-03-13013 March 2006 Handwritten Notes from Meeting on D.C. Cook ML0428104752004-10-0707 October 2004 SAMA Presentation Examples ML0427301162004-09-28028 September 2004 Backfit Determination for the Staff Response to Task Interface Agreement (TIA) 2004-02 (Degraded Voltage Protection) ML0418903762004-07-0606 July 2004 Summary of Telephone Conferences Between the U.S. Nuclear Regulatory Commission Staff and Indiana Michigan Power Company Representatives Regarding the Severe Accident Mitigation Alternatives Analysis Related to the Cook Nuclear Plant, Units ML0412801022004-05-0606 May 2004 Note 05/06/2004 to All Region III Facility Training Managers Re Reprint of NRC Form 396 2006-03-13
[Table view] |
Text
July 6, 2004 LICENSEE: Indian Michigan Power Company FACILITY: Donald C. Cook Nuclear Plant, Units 1 and 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCES BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION STAFF AND INDIANA MICHIGAN POWER COMPANY REPRESENTATIVES REGARDING THE SEVERE ACCIDENT MITIGATION ALTERNATIVES ANALYSIS RELATED TO THE COOK NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MC1221 AND MC1222)
On June 7 and June 17, 2004, the U.S. Nuclear Regulatory Commission (NRC) staff and its contractor, Pacific Northwest National Laboratory (PNNL), conducted conference calls with representatives from Indiana Michigan Power Company (I&M). These calls were held to discuss I&Ms severe accident mitigation alternatives (SAMA) analysis related to the Donald C.
Cook Nuclear Plant, Units 1 and 2 (CNP), license renewal application. Enclosure 1 is the list of participants.
On the June 7, 2004, conference call, the staff requested that I&M provide summary information regarding the assumptions used in performing the cost-benefit analyses for the 72 SAMAs not eliminated from further consideration in I&Ms initial, qualitative screening evaluation. The list of assumptions were provided by I&M by electronic mail on June 16, 2004, and are provided in Enclosure 2.
On the June 17, 2004, conference call, the staff requested the basis for the factors used to adjust human error dependent sequences in the list of assumptions. I&M staff indicated that the factors were derived from the human performance shaping factors for procedural and execution errors provided in NUREG/CR-1278, "Handbook of Human Reliability Analysis with Emphasis on Nuclear Power Plant Applications, October 1983.
The staff also requested clarification regarding the cost estimate for SAMA 26. The cost estimate for SAMA 26 (hardware and procedural modifications for a permanently installed alternate ventilation system for electrical switchgear) was identical to the cost estimate for SAMA 25 (hardware and procedural modifications for a temporary alternate ventilation system for electrical switchgear). I&M stated that the cost estimate for SAMA 26 should have indicated
that the cost to implement this SAMA would be greater than $40,000 (the cost estimate to implement SAMA 25) rather than equal to $40,000. I&M staff stated that a detailed cost estimate was not completed for SAMA 26. Rather, the applicant assumed that the cost would be at least equivalent to the cost to implement SAMA 25.
/RA/
Robert G. Schaaf, Project Manager Environmental Section License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-315 and 50-316
Enclosures:
As stated cc w/enclosures: See next page
that the cost to implement this SAMA would be greater than $40,000 (the cost estimate to implement SAMA 25) rather than equal to $40,000. I&M staff stated that a detailed cost estimate was not completed for SAMA 26. Rather, the applicant assumed that the cost would be at least equivalent to the cost to implement SAMA 25.
/RA/
Robert G. Schaaf, Project Manager Environmental Section License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-315 and 50-316
Enclosures:
As stated cc w/enclosures: See next page DISTRIBUTION:
D. Matthews/F. Gillespie P. T. Kuo J. Tappert R. Schaaf W. Dam T. Terry J. Rowley J. Eads J. Lamb R. Palla OGC Kirk LaGory (ANL)
RLEP R/F ADAMS ACCESSION NOS.:
- 1. Note to Licensee: Indiana Michigan Pwr Co. w/Attendees List, Svc. List: ML041890376
- 2. D.C.Cook SAMA Report: ML041890409
- 3. Pkg: ML041890401 DOCUMENT NAME: C:\ORPCheckout\FileNET\ML041890376.wpd OFFICE PM:RLEP:DRIP LA:RLEP:DRIP SC:RLEP:DRIP NAME RSchaaf MJenkins J. Tappert DATE 7/6/04 7/6/04 7/6/04 OFFICIAL RECORD COPY
LIST OF ATTENDEES TELEPHONE CONFERENCES WITH INDIANA MICHIGAN POWER COMPANY JUNE 7 AND JUNE 17, 2004 TELECON PARTICIPANTS Attendees Affiliation Neil Haggerty Indiana Michigan Power Company (I&M)
Jim Hawley* I&M Robert Schaaf U.S. Nuclear Regulatory Commission (NRC)
Robert Palla NRC Fred Leverenz Pacific Northwest National Laboratory (PNNL)
- Did not participate on June 17 call ENCLOSURE 1
Donald C. Cook Nuclear Plant, Units 1 and 2 cc:
Regional Administrator, Region III Mr. John A. Zwolinski U.S. Nuclear Regulatory Commission Director, Design Engineering and 801 Warrenville Road Regulatory Affairs Lisle, IL 60532-4351 Indiana Michigan Power Company Nuclear Generation Group Attorney General 500 Circle Drive Department of Attorney General Buchanan, MI 49107 525 West Ottawa Street Lansing, MI 48913 Michigan Department of Environmental Quality Township Supervisor Waste and Hazardous Materials Div.
Lake Township Hall Hazardous Waste & Radiological P.O. Box 818 Protection Section Bridgman, MI 49106 Nuclear Facilities Unit Constitution Hall, Lower-Level North U.S. Nuclear Regulatory Commission 525 West Allegan Street Resident Inspectors Office P. O. Box 30241 7700 Red Arrow Highway Lansing, MI 48909-7741 Stevensville, MI 49127 David A. Lochbaum David W. Jenkins, Esquire Nuclear Safety Engineer Indiana Michigan Power Company Union of Concerned Scientists One Cook Place 1707 H Street NW, Suite 600 Bridgman, MI 49106 Washington, DC 20036 Mayor, City of Bridgman Mr. Fred Emerson P.O. Box 366 Nuclear Energy Institute Bridgman, MI 49106 1776 I Street, N.W., Suite 400 Washington, DC 20006-3708 Special Assistant to the Governor Room 1 - State Capitol Richard J. Grumbir Lansing, MI 48909 Project Manager, License Renewal Indiana Michigan Power Company Michael J. Finissi Nuclear Generation Group Plant Manager 500 Circle Drive Indiana Michigan Power Company Buchanan, MI 49107 Nuclear Generation Group One Cook Place Mr. Mano K. Nazar Bridgman, MI 49106 American Electric Power Senior Vice President and Chief Nuclear Joseph N. Jensen Officer Site Vice President Indiana Michigan Power Company Indiana Michigan Power Company Nuclear Generation Group Nuclear Generation Group 500 Circle Drive One Cook Place Buchanan, MI 49107 Bridgman, MI 49106
Ms. Carol Richardson, Director Bridgman Public Library 4460 Lake Street Bridgman, MI 49106 Ms. Mary Kynast, Director Maud Preston Palenske Memorial Library 500 Market Street St. Joseph, MI 49085