Request for Additional Information Security Plan Sections 1-9 (TAC Nos. MC2979 & MC2980)
ML041800048
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 06/22/2004
From: Chernoff M
NRC/NRR/DLPM/LPD2
To: Ferentz R
Pennsylvania Power & Light Co
References
TAC MC2979, TAC MC2980
Download: ML041800048 (5)


Text

SAFEGUARDS INFORMATION June 22, 2004 Mr. Roland Ferentz Manager, Nuclear Security Pennsylvania Power and Light Company, LLC 769 Salem Blvd.

Berwick, PA 18603

SUBJECT:

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: SECURITY PLAN SECTIONS 1 - 9 (TAC NOS. MC2979 AND MC2980)

Dear Mr. Ferentz:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and guard training and qualification plan, including an implementation schedule, for Susquehanna Steam Electric Station, Units 1and 2. The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of Sections 1 through 9 of your physical security plan. Please respond to the enclosed RAI within 10 days from receipt of this letter.0 WARNING: Violation of Section 147 of the Atomic Energy Act, NOTICE: The enclosed information contains Safeguards Safeguards Information is subject to Information. Upon separation from the Enclosure, this Civil and Criminal Penalties letter is DECONTROLLED.

SAFEGUARDS INFORMATION

SAFEGUARDS INFORMATION R. Ferentz If circumstances result in the need to revise the target response date, please contact me at (301) 415-1952.

Sincerely,

/RA/

Margaret H. Chernoff, Project Manager Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosure:

As stated cc w/o encl: See next page SAFEGUARDS INFORMATION

SAFEGUARDS INFORMATION R. Ferentz If circumstances result in the need to revise the response target date, please contact me at (301) 415-1952.

Sincerely,

/RA/

Margaret H. Chernoff, Project Manager Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosure:

As stated cc w/o encl: See next page DISTRIBUTION:

PUBLIC SPRT R/F J. Nakoski J. Peralta C. Hawes M. Chernoff OGC ACRS R. Guzman R. Laufer C. Holden C. Bixler, RI ADAMS Accession Number: ML041800048 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR SPRT/NRR/SC NAME MChernoff CHawes JPeralta JNakoski DATE 6/22/04 6/22/04 6/22/04 6/22/04 OFFICIAL RECORD COPY SAFEGUARDS INFORMATION

Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:

Richard L. Anderson Dale F. Roth Vice President - Nuclear Operations Manager - Quality Assurance PPL Susquehanna, LLC PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Berwick, PA 18603-0467 Aloysius J. Wrape, III Herbert D. Woodeshick General Manager - Nuclear Assurance Special Office of the President PPL Susquehanna, LLC PPL Susquehanna, LLC Two North Ninth Street, GENPL4 634 Salem Blvd., SSO Allentown, PA 18101-1179 Berwick, PA 18603-0467 Terry L. Harpster Bryan A. Snapp, Esq General Manager - Plant Support Assoc. General Counsel PPL Susquehanna, LLC PPL Services Corporation 769 Salem Blvd., NUCSA4 Two North Ninth Street, GENTW3 Berwick, PA 18603-0467 Allentown, PA 18101-1179 Robert A. Saccone Supervisor - Document Control Services General Manager - Nuclear Engineering PPL Susquehanna, LLC PPL Susquehanna, LLC Two North Ninth Street, GENPL4 769 Salem Blvd., NUCSB3 Allentown, PA 18101-1179 Berwick, PA 18603-0467 Richard W. Osborne Rocco R. Sgarro Allegheny Electric Cooperative, Inc.

Manager - Nuclear Regulatory Affairs 212 Locust Street PPL Susquehanna, LLC P.O. Box 1266 Two North Ninth Street, GENPL4 Harrisburg, PA 17108-1266 Allentown, PA 18101-1179 Director - Bureau of Radiation Protection Walter E. Morrissey Pennsylvania Department of Supervising Engineer Environmental Protection Nuclear Regulatory Affairs P.O. Box 8469 PPL Susquehanna, LLC Harrisburg, PA 17105-8469 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Senior Resident Inspector U.S. Nuclear Regulatory Commission Michael H. Crowthers P.O. Box 35, NUCSA4 Supervising Engineer Berwick, PA 18603-0035 Nuclear Regulatory Affairs PPL Susquehanna, LLC Regional Administrator, Region 1 Two North Ninth Street, GENPL4 U.S. Nuclear Regulatory Commission Allentown, PA 18101-1179 475 Allendale Road King of Prussia, PA 19406

SAFEGUARDS INFORMATION Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:

Board of Supervisors Salem Township P.O. Box 405 Berwick, PA 18603-0035 Dr. Judith Johnsrud National Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803 Mr. Bryce L. Shriver Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Boulevard Berwick, PA 18603-0467 SAFEGUARDS INFORMATION