July 12, 2004 Mr. James A. Gresham, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company P.O. Box 355 Pittsburgh, PA 15230-0355

SUBJECT:

REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (TAC NO. MC3337)

Dear Mr. Gresham:

By letter dated June 1, 2004, Nuclear Management Company, LLC, submitted an affidavit dated February 24, 2004, executed by you, requesting that information in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390.

Enclosure 2, Applicability of WCAP-14333 and WCAP-15376 to Kewaunee, to License Amendment Request 204 to the Kewaunee Nuclear Power Plant Technical Specifications: Extend Reactor Trip System and Engineered Safety Features Actuation System Surveillance Test Intervals as Evaluated in WCAP-15376-P-A A nonproprietary copy of this document has been placed in the Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.

The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

(i) The information sought to be withheld from public disclosure is owned and has been held in confidence by Westinghouse.

(ii) The information is of a type customarily held in confidence by Westinghouse and not customarily disclosed to the public.

(a) The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouse's competitors without license from Westinghouse constitutes a competitive economic advantage over other companies.

(c) Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.

J. Gresham We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the information in the document entitled, "Enclosure 2, Applicability of WCAP-14333 and WCAP-15376 to Kewaunee, to License Amendment Request 204 to the Kewaunee Nuclear Power Plant Technical Specifications: Extend Reactor Trip System and Engineered Safety Features Actuation System Surveillance Test Intervals as Evaluated in WCAP-15376-P-A," marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at (301) 415-2296.

Sincerely,

/RA/

Carl F. Lyon, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-305 cc: See next page

J. Gresham We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the information in the document entitled, "Enclosure 2, Applicability of WCAP-14333 and WCAP-15376 to Kewaunee, to License Amendment Request 204 to the Kewaunee Nuclear Power Plant Technical Specifications: Extend Reactor Trip System and Engineered Safety Features Actuation System Surveillance Test Intervals as Evaluated in WCAP-15376-P-A," marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at (301) 415-2296.

Sincerely,

/RA/

Carl F. Lyon, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-305 cc: See next page DISTRIBUTION:

PUBLIC LRaghavan THarris SRhow PDIII-1 Reading FLyon EMarinos WRuland OGC GGrant, RIII ADAMS ACCESSION NO.: ML041690400 OFFICE PDIII-1/PM PDIII-1/LA EEIB/SC PDIII-1/SC NAME FLyon THarris EMarinos LRaghavan DATE 06/24/04 06/24/04 07/07/04 07/12/04 OFFICIAL RECORD COPY

Kewaunee Nuclear Power Plant cc:

John Paul Cowan David Zellner Executive Vice President & Chairman - Town of Carlton Chief Nuclear Officer N2164 County B Nuclear Management Company, LLC Kewaunee, WI 54216 700 First Street Hudson, MI 54016 Mr. Jeffery Kitsembel Electric Division Plant Manager Public Service Commission of Wisconsin Kewaunee Nuclear Power Plant PO Box 7854 N490 Highway 42 Madison, WI 53707-7854 Kewaunee, WI 54216-9511 Manager, Regulatory Affairs Kewaunee Nuclear Power Plant N490 Highway 42 Kewaunee, WI 54216-9511 David Molzahn Nuclear Asset Manager Wisconsin Public Service Corporation 600 N. Adams Street Green Bay, WI 54307-9002 Resident Inspectors Office U. S. Nuclear Regulatory Commission N490 Hwy 42 Kewaunee, WI 54216-9511 Regional Administrator, Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 Jonathan Rogoff Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Larry L. Weyers Chairman, President and CEO Wisconsin Public Service Corporation 600 North Adams Street Green Bay, WI 54307-9002