MONTHYEARPMNS20231157, Pre-planning Meeting with PSEG Nuclear LLC to Discuss Future Amendments Regarding Integrated Technical Specification Conversion, 24-Month Fuel Cycle and Revise Safety Release Valve Setpoint to 1130 Psig2023-10-10010 October 2023 Pre-planning Meeting with PSEG Nuclear LLC to Discuss Future Amendments Regarding Integrated Technical Specification Conversion, 24-Month Fuel Cycle and Revise Safety Release Valve Setpoint to 1130 Psig PMNS20230612, Pre-submittal Meeting with PSEG to Discuss the Amendment to Reduce Sites Exclusion Area Boundary2023-05-10010 May 2023 Pre-submittal Meeting with PSEG to Discuss the Amendment to Reduce Sites Exclusion Area Boundary ML23124A1072023-05-0404 May 2023 Notice of Public Meeting (Webinar) - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants (Bv, CC, FP, Gn, Hc, Lm, NMP, Pb, SAL, & Sus) PMNS20221135, Public Meeting to Discuss Transfer of Ownership of Portions of the PSEG Nuclear Site2022-11-0303 November 2022 Public Meeting to Discuss Transfer of Ownership of Portions of the PSEG Nuclear Site ML22131A2212022-05-11011 May 2022 Notice of Public Meeting (Webinar) - Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants (Bv, CC, FP, Gn, Hc, Lm, NMP, Pb, SAL, & Sus) ML21140A3142021-05-20020 May 2021 Notice of Public Meeting - Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Power Plants (Bv, CC, FP, Gn, Hc, Lm, NMP, Pb, SAL, & Sq) PMNS20210302, Pre-Submittal Meeting with PSEG Nuclear LLC to Discuss Plans and Details of Upcoming License Amendment Request Regarding Changes to the Ultimate Heat Sink Technical Specifications for Hope Creek2021-03-17017 March 2021 Pre-Submittal Meeting with PSEG Nuclear LLC to Discuss Plans and Details of Upcoming License Amendment Request Regarding Changes to the Ultimate Heat Sink Technical Specifications for Hope Creek PMNS20210173, Pre-Submittal Meeting with PSEG Nuclear, LLC to Discuss Relief Requests to Adopt Code Cases N-878, N-879, and N-880 for Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 22021-02-18018 February 2021 Pre-Submittal Meeting with PSEG Nuclear, LLC to Discuss Relief Requests to Adopt Code Cases N-878, N-879, and N-880 for Hope Creek Generating Station and Salem Nuclear Generating Station, Units 1 and 2 ML20287A2472020-10-13013 October 2020 Pre-submittal Teleconference Regarding Proposed Licensing Approach to Install the General Electric Numac Wide Range Neutron Monitoring System for Hope Creek Generating Station ML20140A2762020-05-19019 May 2020 June 10, 2020: Notice of Public Meeting for Salem Generating Station Units No. 1 and 2 and Hope Creek Generating Station ML19084A1102019-03-25025 March 2019 April 10, 2019 Public Meeting Notice for Salem Nuclear Generating Station, Units 1 and 2; Hope Creek Generating Station ML18134A1982018-05-14014 May 2018 5/30/18: Notice of Public Meeting for Salem Nuclear Generating Station, Units 1 and 2; Hope Creek Generating Station ML17076A0562017-03-17017 March 2017 3/28/2017 - Notice of Category 3 Public Annual Assessment Meeting - Salem Nuclear Generating Station Units 1 and 2; Hope Creek Generating Station for 2016 ML16068A3692016-03-0808 March 2016 Notice of Annual Assessment Meeting - Salem Nuclear Generating Station & Hope Creek Generating Station, on March 30, 2016 ML15069A4882015-03-10010 March 2015 March 25, 2015, Notice of Open House Meeting with Salem and Hope Creek Generating Stations LR-N15-0016, Pre-Application Meeting: Installation of Digital Power Range Neutron Monitor (Prnm) in Accordance with Interim Staff Guidance, Digital I&C-ISG-062015-01-21021 January 2015 Pre-Application Meeting: Installation of Digital Power Range Neutron Monitor (Prnm) in Accordance with Interim Staff Guidance, Digital I&C-ISG-06 ML15015A6772015-01-16016 January 2015 Forthcoming Closed Meeting with PSEG Nuclear, LLC, Regarding a Planned Digital Instrumentation and Controls License Amendment Request Associated with Hope Creek Generating Station, Unit 1 ML14338A3732014-12-0404 December 2014 Plan for Site Visits DLR 2015 ML14070A4702014-03-11011 March 2014 2014 Salem & Hope Creek Annual Assessment Meeting Notice & Open House, March 27, 2014 ML13233A1132013-08-22022 August 2013 Notice of Forthcoming Meeting with PSEG Nuclear, LLC Regarding a Planned Digital Instrumentation and Controls License Amendment Request Associated with Hope Creek Generating Station, Unit 1 ML13073A2012013-03-14014 March 2013 Notice of Public Meeting to Discuss Nrc'S Assessment of Safety Performance at Salem Nuclear Generating Station and Hope Creek Generating Station for 2012 ML12229A2402012-08-15015 August 2012 Closed Notice of Meeting for Salem and Hope Creek Nuclear Generating Station Scheduled for August 31, 2012 ML12124A0492012-05-0303 May 2012 Update - 2012 Salem & Hope Creek Open House and Public Meeting Notice No. 12-012, for May 15, 2012 ML12103A0382012-04-12012 April 2012 5/15/2012 - Salem and Hope Creek Generating Stations - Notice of Public Meeting with PSEG Nuclear LLC ML12013A1002012-01-13013 January 2012 Notice of Closed Meeting with PSEG Nuclear, LLC, Salem and Hope Creek, to Discuss a Potentially Greater than Green Security Related Finding ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML11126A0962011-05-12012 May 2011 Notice of Meeting with Petitioner Requesting Action Under 10CFR2.206 Regarding Immediate Suspension of Operating Licenses of General Electric Mark 1 Boiling Water Reactors ML1111703172011-04-27027 April 2011 Notice of Public Meeting - Salem Nuclear Generating Station and Hope Creek Generating Station ML1112200122011-04-20020 April 2011 05/12-14/2011 - Meeting (583rd) of the Advisory Committee on Reactor Safeguards - Federal Register Notice ML1029500062010-10-28028 October 2010 11/17/10 Forthcoming Meeting to Discuss the Draft Supplemental Environmental Impact Statement for the License Renewal of Hope Creek Generating Station and Salem Nuclear Generating Station Units 1 and 2 ML1012412182010-05-0606 May 2010 Public Meeting with Salem-Hope Creek to Discuss PSEG Nuclear, Llc'S Plans for Movement of Spent Fuel from Salem Nuclear Generating Station to the Independent Spent Fuel Storage Installation That It Shares with Hope Creek Generating Station ML1008103452010-03-22022 March 2010 Notice of Public Meeting: Annual Assessment Meeting with PSEG ML0934405582009-12-10010 December 2009 Notice of Closed Meeting with PSEG Nuclear LLC (PSEG) to Discuss Exemption from Schedular Requirements of 10 CFR 73.55 for Hope Creek Generating Station and Salem Nuclear Generating Station, Unit Nos. 1 and 2 ML0928706352009-10-23023 October 2009 11/05/2009 Notice of Meeting to Discuss License Renewal Process and Environmental Scoping for Salem Nuclear Generating Station, Units 1 and 2, and Hope Creek Generating Station, License Renewal Application Review ML0910703162009-04-16016 April 2009 NRC Meeting with PSEG Nuclear (Salem & Hope Creek) on May 5, 2009 ML0903708282009-02-10010 February 2009 03/16/2009 Forthcoming Meeting to Discuss the Scheduled Submittal of License Renewal Application for Salem and Hope Creek, PSEG Nuclear, LLC ML0810210522008-04-11011 April 2008 Notice of Meeting with PSEG Nuclear Llc., to Discuss Safety Performance at Salem and Hope Creek for Calendar Year 2007 ML0726402342007-10-0101 October 2007 Notice of Closed Meeting with PSEG Nuclear LLC (Licensee) Regarding an Application for Extended Power Uprate for Hope Creek Generating Station ML0721803862007-08-0606 August 2007 Notice of Forthcoming Meeting with PSEG Nuclear LLC (Licensee) Regarding an Application for Extended Power Uprate for Hope Creek Generating Station ML0717804562007-06-27027 June 2007 Notice of Meeting with PSEG Nuclear LLC (Licensee) Regarding an Application for Extended Power Uprate for Hope Creek Generating Station, to Discuss Acceptance Criteria for Boiling-Water Reactor Steam Dryer Predictive Load Under Power Uprate ML0712402122007-05-0404 May 2007 EPU Air Quality Notice of Public Hearing and Opportunity to Comment ML0710105422007-04-13013 April 2007 Notice of Forthcoming Meeting with PSEG Nuclear LLC to Discuss Technical Aspects of the Licensee'S Application for an Extended Power Uprate (EPU) at Hope Creek ML0709505272007-04-0505 April 2007 Notice of Annual Assessment Meeting with PSEG Nuclear LLC Management to Discuss the Nrc'S Assessment of the Safety Performance at the Salem and Hope Creek Generating Stations for Calendar Year 2006 ML0704602562007-02-15015 February 2007 3/02/07, Notice of Meeting with PSEG Nuclear, LLC, to Discuss Technical Aspects of the Licensee'S Application for an Extended Power Uprate (EPU) at the Hope Creek ML0631001592006-11-0808 November 2006 11/13-14/2006 Revised Notice of Forthcoming Meeting with PSEG Nuclear LLC (Licensee) Regarding an Application for Extended Power Uprate for Hope Creek ML0630301362006-10-30030 October 2006 11/13-14/2006 Notice of Meeting with PSEG Nuclear LLC Regarding Application for Extended Power Uprate for Hope Creek Generating Station ML0624400542006-09-0101 September 2006 Meeting Notice for Public Outreach (Salem/Hope Creek) ML0617900252006-07-0505 July 2006 Forthcoming Meeting with PSEG Nuclear LLC Regarding Planned Application for Extended Power Uprate for Hope Creek Generating Station ML0610902742006-04-26026 April 2006 Notice of Meeting with PSEG Nuclear LLC to Discuss Nrc'S Assessment of the Safety Performance at the Salem and Hope Creek Generating Stations for Calendar Year 2005 and to Review PSEG Actions to Improve the Safety Conscious Work Environment ML0607507462006-03-16016 March 2006 Forthcoming Meeting with PSEG Nuclear LLC Regarding Planned Application for Extended Power Uprate for Hope Creek Generating Station 2023-05-04
[Table view] |
Text
May 20, 2004 MEMORANDUM TO: James W. Clifford, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Daniel S. Collins, Senior Project Manager, Section 2 /RA by TTate for/
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
FORTHCOMING MEETING WITH PSEG NUCLEAR, HOPE CREEK NUCLEAR GENERATING STATION DATE & TIME: Wednesday, June 2, 2004 9:00 a.m. - 12:00 p.m.
LOCATION: U.S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike, Room O-13B4 Rockville, Maryland PURPOSE: Discuss GE14 fuel changes at Hope Creek Nuclear Generating Station and supporting analyses. PSEG will be supported at this meeting by its contractors Global Nuclear Fuels - Americas (GNF) and GE Nuclear Energy (GNE).
CATEGORY 1:
- This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
Proprietary information will be discussed at certain times during this meeting. These portions of the meeting will be closed to members of the public who have not been granted access to the information by the owner of the information.
PARTICIPANTS: Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR) Division of Licensing Project Management (DLPM), and Division of Systems Safety and Analysis, Reactor Systems Branch (SRXB).
NRC UTILITY D. Collins, DLPM D. Notigan, PSEG J. Hardy, DLPM F. Safin, PSEG F. Akstulewicsz, SRXB S. Bier, PSEG A. Attard, SRXB P. Duke, PSEG E. Kendrick, SRXB D. McHugh, PSEG Q. Nguyen, SRXB M. Colby, GNF R. Kingston, GNF G. Stramback, GNE E. Schrull, GNE Docket No. 50-354
Attachment:
Agenda (package containing notice, agenda, and supporting documentation can be obtained through ADAMS Accession Number ML041410506).
cc w/att: See next page MEETING CONTACTS: Daniel Collins, NRR Jeff Hardy, NRR 301-415-1427 301-415-4029 DXC1@nrc.gov JXH12@nrc.gov
- Commission's Policy Statement on Enhancing Public Participation in NRC Meetings,"
(67 FR 36920), May 28, 2002
Hope Creek Generating Station cc:
Mr. A. Christopher Bakken, III Ms. R. A. Kankus Senior Vice President - Site Operations Joint Owner Affairs PSEG Nuclear - X15 Exelon Generation Company, LLC P.O. Box 236 Nuclear Group Headquarters KSA1-E Hancocks Bridge, NJ 08038 200 Exelon Way Kennett Square, PA 19348 Mr. John T. Carlin Vice President - Nuclear Assessment Lower Alloways Creek Township PSEG Nuclear - N10 c/o Mary O. Henderson, Clerk P.O. Box 236 Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038 Mr. David F. Garchow Dr. Jill Lipoti, Asst. Director Vice President - Eng/Tech Support Radiation Protection Programs PSEG Nuclear - N28 NJ Department of Environmental P.O. Box 236 Protection and Energy Hancocks Bridge, NJ 08038 CN 415 Trenton, NJ 08625-0415 Mr. James A. Hutton Plant Manager Brian Beam PSEG Nuclear - X15 Board of Public Utilities P.O. Box 236 2 Gateway Center, Tenth Floor Hancocks Bridge, NJ 08038 Newark, NJ 07102 Mr. Steven Mannon Regional Administrator, Region I Acting Manager - Nuclear Safety and U.S. Nuclear Regulatory Commission Licensing 475 Allendale Road PSEG Nuclear - N21 King of Prussia, PA 19406 P.O. Box 236 Hancocks Bridge, NJ 08038 Senior Resident Inspector Hope Creek Generating Station Jeffrie J. Keenan, Esquire U.S. Nuclear Regulatory Commission PSEG Nuclear - N21 Drawer 0509 P.O. Box 236 Hancocks Bridge, NJ 08038 Hancocks Bridge, NJ 08038
AGENDA HOPE CREEK NUCLEAR GENERATING STATION GE14 FUEL CHANGES MEETING JUNE 2, 2004
- 1. Hope Creek fuel transition project overview
- 2. New fuel introduction process in Hope Creek reactor using GESTAR
- 3. GE14 fuel transition project status
- 4. Discussion of fuel vendor change submittal license change request (LCR) # H03-08 request for additional information questions (TAC No. MC1682 )
- 5. Discussion of Cycle 13 safety limit minimum critical power ratio (SLMCPR) submittal LCR # H04-03
- a. Power distribution uncertainties
- b. Cycle 12 and Cycle 13 SLMCPR comparisons
- c. Westinghouse SVEA fuel performance using GNF methods
- 6. Discussion of fuel supplemental reports
- a. Fuel transition report and9 stability
- b. Mixed core analysis report
- c. Loss-of-coolant accident report
- 7. Integration of GE14 fuel with extended power uprate - maximum extended load line limit analysis program implementation in Hope Creek reactor
- 8. Future meetings forum
- 9. Questions and answers / open discussion
- 10. Concluding remarks
- 11. Questions from the public Attachment
ML041410506 OFFICE PDI-2/PM PDI-2/LA PDI-2/SC NAME TTate for DCollins CRaynor JClifford DATE 5/20/04 5/20/04 5/20/04 Distribution E-mail PUBLIC PDI Reading B. Sheron RidsNrrAdpt T. Marsh/E. Leeds RidsNrrDlpm C. Holden J. Clifford D. Collins K. Johnson RidsNrrAdpt J. Hardy F. Akstulewicsz A. Attard E. Kendrick Q. Nguyen C. Raynor OPA RidsOpaMail D. Holody, DRP J. Jolicoeur D. Screnci, Region I PMNS PMNS J. Albright ACRS/ACNW RidsAcrsAcnwMailCenter Receptionist (OWFN and TWFN)