Supplemental Response to the April 29, 2003, Orders Modifying Licenses for Revised Design Basis Threat
ML041410192
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/20/2004
From: John Nakoski
NRC/NRR/DLPM/LPD2
To: Vanmiddlesworth G
Nuclear Management Co
Chernoff, M H, NRR/DLPM, 301-415-4041
References
EA-03-086, TAC MC2957, TAC MC2958
Download: ML041410192 (4)


Text

May 20, 2004 Mr. Gary D. VanMiddlesworth Site Vice President - Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS MODIFYING LICENSES FOR REVISED DESIGN BASIS THREAT (TAC NOS. MC2957 AND MC2958)

Dear Mr. VanMiddlesworth:

On April 29, 2003, the Nuclear Regulatory Commission (NRC) issued Orders modifying the operating licenses for Point Beach, Units 1 and 2 to: (1) require compliance with a revised design basis threat (DBT); (2) implement new security force personnel training and physical fitness requirements; and (3) prescribe compensatory measures related to fitness-for-duty enhancements applicable to security force personnel.

Section III.A.1 of the EA-03-086 (DBT Order) required that all licensees submit revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, based on the revised DBT, to the NRC for review and approval no later than April 29, 2004. The Order further requires licensees to implement the revised physical security plans, revised safeguards contingency plans, and revised security force personnel training and qualification plans no later than October 29, 2004.

By letter dated April 29, 2004, you submitted a supplemental response to the Orders for Point Beach, Units 1 and 2.

You provided information on your security plan as it relates to your Independent Spent Fuel Storage Installation (ISFSI). You will be notified by separate correspondence of the NRC staffs plan for review of your ISFSI security plan.

The NRC staff will be reviewing your physical security plan in the months of May and June, your training and qualification plan during July, and your contingency plan during August. Should further information regarding your submittal be necessary to support our review, you will be notified promptly.

G. D. VanMiddlesworth The NRC staff is currently reviewing your supplemental response and intends to complete the review of your revised plans by October 29, 2004.

Sincerely,

/RA/

John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-260 and 50-301 cc: See next page

G. D. VanMiddlesworth The NRC staff is currently reviewing your supplemental response and intends to complete the review of your revised plans by October 29, 2004.

Sincerely,

/RA/

John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-260 and 50-301 cc: See next page DISTRIBUTION:

PUBLIC SPRT R/F J. Nakoski J. Peralta C. Hawes M. Chernoff P. Peduzzi OGC ACRS NRR/DLPM - PMs NRR/DLPM - SCs A. Howell, RIII ADAMS Accession Number: ML041410192 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR/SSC SPRT/NSIR/SC SPRT/NRR/SC NAME MChernoff CHawes PPeduzzi JPeralta JNakoski DATE 5/20/04 5/20/04 5/20/04 5/20/04 5/20/04 OFFICIAL RECORD COPY

Point Beach Nuclear Plant, Units 1 and 2 cc:

Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Mr. Richard R. Grigg President and Chief Operating Officer Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 Regulatory Affairs Manager Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspectors Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Mr. Jeffery Kitsembel Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Douglas E. Cooper Senior Vice President - Group Operations Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043 Site Director of Operations Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 January 2003