May 19, 2004 Mr. Bryce L. Shriver Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Boulevard, NUCSB3 Berwick, PA 18603-0467
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION (RAI) - SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (SSES 1 AND 2) - REVISED RESPONSE TO GENERIC LETTER 94-02: LONG-TERM STABILITY SOLUTION (TAC NOS. MC1659 AND MC1660)
Dear Mr. Shriver:
In reviewing your submittal of December 22, 2003, concerning a request to add SSES 1and 2 Technical Specification (TS) 3.3.1.3, Oscillation Power Range Monitor Instrumentation, and revise TS 3.4.1, Recirculation Loops Operating, and TS 5.6.5, Core Operating Limits Report, the Nuclear Regulatory Commission staff has determined that additional information contained in the enclosure to this letter is needed to complete its review. These questions were discussed with your staff during a teleconference on May 5, 2004. As agreed to by your staff, we request you respond within 30 days of the date of this letter.
If you have any questions, please contact me at 301-415-1030.
Sincerely,
/RA/
Richard V. Guzman, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388
Enclosure:
RAI cc w/encl: See next page
May 19, 2004 Mr. Bryce L. Shriver Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Boulevard, NUCSB3 Berwick, PA 18603-0467
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION (RAI) - SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (SSES 1 AND 2) - REVISED RESPONSE TO GENERIC LETTER 94-02: LONG-TERM STABILITY SOLUTION (TAC NOS. MC1659 AND MC1660)
Dear Mr. Shriver:
In reviewing your submittal of December 22, 2003, concerning a request to add SSES 1and 2 Technical Specification (TS) 3.3.1.3, Oscillation Power Range Monitor Instrumentation, and revise TS 3.4.1, Recirculation Loops Operating, and TS 5.6.5, Core Operating Limits Report, the Nuclear Regulatory Commission staff has determined that additional information contained in the enclosure to this letter is needed to complete its review. These questions were discussed with your staff during a teleconference on May 5, 2004. As agreed to by your staff, we request you respond within 30 days of the date of this letter.
If you have any questions, please contact me at 301-415-1030.
Sincerely,
/RA/
Richard V. Guzman, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388
Enclosure:
RAI cc w/encl: See next page DISTRIBUTION:
Public OGC CBixler, Rgn-1 RGuzman DLPM DPR PDI-1 R/F RLaufer MO'Brien THuang ACRS FAkstulewicz Accession Number: ML041400526 OFFICE PDI-1/PM PDI-2/LA SRXB/SC PDI-1/SC NAME RGuzman MO'Brien FAkstulewicz TColburn for RLaufer DATE 5/12/04 5/12/04 5/17/04 5/17/04 OFFICIAL RECORD COPY
Enclosure REQUEST FOR ADDITIONAL INFORMATION RELATING TO REVISED RESPONSE TO GENERIC LETTER 94-02 LONG-TERM STABILITY SOLUTION FOR SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 (SSES 1 AND 2)
DOCKET NOS. 50-387 AND 50-388 The Nuclear Regulatory Commission (NRC) staff is reviewing the proposed license amendment to Facility Operating License Nos. NPF-14 and NPF-22 requesting to add SSES 1and 2 Technical Specification (TS) 3.3.1.3, Oscillation Power Range Monitor [OPRM]
Instrumentation, and revise TS 3.4.1, Recirculation Loops Operating and TS 5.6.5, Core Operating Limits Report [COLR], dated December 22, 2003. The NRC staff has determined that the information requested below will be needed to complete its review.
1.
Confirm the current validity of the plant-specific actions stated in CENPD-400-P-A, Rev. 1, Generic Topical Report for the ABB Option III Oscillation Power Range Monitor.
2.
Describe the current implementation and monitoring status (i.e., system tests and operability basis) of the OPRM system, and the analytical approach stated in NEDO-32465-A, Reactor Stability Detect and Suppress Solutions Licensing Basis Methodology for Reload Applications.
3.
Provide a description of the actions taken by PPL according to the Boiling Water Reactor Owners Group (BWROG) letter, BWROG-03049 dated September 30, 2003, Utility Commitment to NRC for OPRM Operability at Option III Plants. Please identify any plant-specific differences from the generic values specified in NEDO-32465-A such as Period Based Detection Algorithm (PBDA) period confirmation setpoints in Table 3-1, PBDA trip setpoints in Table 3-2, and generic DIVOM (Delta critical power ratio (CPR) to Initial CPR vs. Oscillation Magnitude) curve slope.
4.
Provide the rationale for locating the OPRM Period Based Algorithm Allowable Value and Confirmation Counts in the COLR.
5.
Identify the methodologies and key inputs used to determine the OPRM setpoints for TS 3.3.1.3 and indicate whether they are NRC-approved methods.
6.
Describe how the alternate method will be employed to detect and suppress thermal hydraulic instability oscillations stated in TS 3.3.1.3 Actions A.3 and B.1.
Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:
Richard L. Anderson Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467 Aloysius J. Wrape, III General Manager - Nuclear Assurance PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Terry L. Harpster General Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Robert A. Saccone General Manager - Nuclear Engineering PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467 Rocco R. Sgarro Manager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Walter E. Morrissey Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Michael H. Crowthers Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Dale F. Roth Manager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Herbert D. Woodeshick Special Office of the President PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467 Bryan A. Snapp, Esq Assoc. General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179 Supervisor - Document Control Services PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Richard W. Osborne Allegheny Electric Cooperative, Inc.
212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266 Director - Bureau of Radiation Protection Pennsylvania Department of Environmental Protection P.O. Box 8469 Harrisburg, PA 17105-8469 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4 Berwick, PA 18603-0035 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406
Susquehanna Steam Electric Station, Unit Nos. 1 and 2 cc:
Board of Supervisors Salem Township P.O. Box 405 Berwick, PA 18603-0035 Dr. Judith Johnsrud National Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803