ML041390239
| ML041390239 | |
| Person / Time | |
|---|---|
| Site: | Prairie Island |
| Issue date: | 05/20/2004 |
| From: | John Nakoski NRC/NRR/DLPM/LPD2 |
| To: | Solymossy J Nuclear Management Co |
| Chernoff, M H, NRR/DLPM, 301-415-4041 | |
| References | |
| TAC MC2959, TAC MC2960 | |
| Download: ML041390239 (5) | |
Text
May 20, 2004 Mr. Joseph M. Solymossy Site Vice President Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, Minnesota 55089-9642
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 -
SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS MODIFYING LICENSES FOR REVISED DESIGN BASIS THREAT (TAC NO. MC2959 AND MC2960)
Dear Mr. Solymossy:
On April 29, 2003, the Nuclear Regulatory Commission (NRC) issued an Order modifying the operating licenses for Prairie Island Nuclear Generating Plant, Units 1 and 2 to: (1) require compliance with a revised Design Basis Threat (DBT); (2) implement new security force personnel training and physical fitness requirements; and (3) prescribe compensatory measures related to fitness-for-duty enhancements applicable to security force personnel.
Section III.A.1 of EA-03-086 (DBT Order) required that all licensees submit revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, based on the revised DBT, to the NRC for review and approval no later than April 29, 2004. The DBT Order further requires licensees to implement the revised physical security plans, revised safeguards contingency plans, and revised security force personnel training and qualification plans no later than October 29, 2004.
By letter dated April 29, 2004, you submitted a supplemental response to the DBT Order for Prairie Island Nuclear Generating Plant, Units 1 and 2.
You provided information on your security plan as it relates to your Independent Spent Fuel Storage Installation (ISFSI). You will be notified by separate correspondence of the NRC staffs plan for review of your ISFSI security plan.
J. M. Solymossy The NRC staff will review your physical security plan in the months of May and June, your training and qualification plan during July, and your contingency plan during August. Should further information regarding your submittal be necessary to support our review, you will be notified promptly.
The NRC staff plans to complete the review of your supplemental response by October 29, 2004.
Sincerely,
/RA/
John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos.05-282 and 05-306 cc: See next page
ML041390239 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR/SSC SPRT/NSIR SPRT/NRR/SC NAME MChernoff CHawes PPeduzzi JPeralta JNakoski DATE 5/20/04 5/20/04 5/20/04 5/20/04 5/20/04
Prairie Island Nuclear Generating Plant, Units 1 and 2 cc:
Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Manager, Regulatory Affairs Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089 Manager - Environmental Protection Division Minnesota Attorney Generals Office 445 Minnesota St., Suite 900 St. Paul, MN 55101-2127 U.S. Nuclear Regulatory Commission Resident Inspector's Office 1719 Wakonade Drive East Welch, MN 55089-9642 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Administrator Goodhue County Courthouse Box 408 Red Wing, MN 55066-0408 Commissioner Minnesota Department of Commerce 121 Seventh Place East Suite 200 St. Paul, MN 55101-2145 Tribal Council Prairie Island Indian Community ATTN: Environmental Department 5636 Sturgeon Lake Road Welch, MN 55089 Nuclear Asset Manager Xcel Energy, Inc.
414 Nicollet Mall, R.S. 8 Minneapolis, MN 55401 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Craig G. Anderson Senior Vice President, Group Operations Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 November 2003