Supplemental Response to the April 29, 2003, Orders Modifying Licenses for Revised Design Basis Threat
ML041340711
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 05/20/2004
From: John Nakoski
NRC/NRR/DLPM/LPD2
To: Ted Sullivan
Entergy Nuclear Operations
Chernoff, M H, NRR/DLPM, 301-415-4041
References
EA-03-086, TAC MC2921
Download: ML041340711 (5)


Text

May 20, 2004 Mr. T. A. Sullivan Site Vice President Entergy Nuclear Operations, Inc.

P. O. Box 110 Lycoming, NY 13093

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT - SUPPLEMENTAL RESPONSE TO THE APRIL 29, 2003, ORDERS MODIFYING LICENSES FOR REVISED DESIGN BASIS THREAT (TAC NO. MC2921)

Dear Mr. Sullivan:

On April 29, 2003, the Nuclear Regulatory Commission (NRC) issued an Order modifying the operating license for James A. FitzPatrick Nuclear Power Plant to: (1) require compliance with a revised Design Basis Threat (DBT); (2) implement new security force personnel training and physical fitness requirements; and (3) prescribe compensatory measures related to fitness-for-duty enhancements applicable to security force personnel.

Section III.A.1 of EA-03-086 (DBT Order) required that all licensees submit revised physical security plans, safeguards contingency plans, and guard training and qualification plans, including an implementation schedule, based on the revised DBT, to the NRC for review and approval no later than April 29, 2004. The DBT Order further requires licensees to implement the revised physical security plans, revised safeguards contingency plans, and revised security force personnel training and qualification plans no later than October 29, 2004.

By letter dated April 29, 2004, you submitted a supplemental response to the DBT Order for James A. FitzPatrick Nuclear Power Plant.

You provided information on your security plan as it relates to your Independent Spent Fuel Storage Installation (ISFSI). You will be notified by separate correspondence of the NRC staffs plan for review of your ISFSI security plan.

T. A. Sullivan The NRC staff will review your physical security plan in the months of May and June, your training and qualification plan during July, and your contingency plan during August. Should further information regarding your submittal be necessary to support our review, you will be notified promptly.

The NRC staff plans to complete the review of your supplemental response by October 29, 2004.

Sincerely,

/RA/

John A. Nakoski, Chief Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-333 cc: See next page

ML041340711 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR/SSC SPRT/NSIR SPRT/NRR/SC NAME MChernoff CHawes PPeduzzi JPeralta JNakoski DATE 5/20/04 5/20/04 5/20/04 5/20/04 5/20/04

FitzPatrick Nuclear Power Plant cc:

Mr. Gary J. Taylor Chief Executive Officer Entergy Operations, Inc.

1340 Echelon Parkway Jackson, MS 39213 Mr. John T. Herron Sr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Theodore A. Sullivan Site Vice President Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Mr. Kevin J. Mulligan General Manager, Plant Operations Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Mr. Danny L. Pace Vice President, Engineering Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Brian OGrady Vice President, Operations Support Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. John F. McCann Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Resident Inspector's Office James A. FitzPatrick Nuclear Power Plant U. S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 Ms. Charlene D. Faison Manager, Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Michael J. Colomb Director of Oversight Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. William Maquire Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Mr. Andrew Halliday Manager, Regulatory Compliance Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Supervisor Town of Scriba Route 8, Box 382 Oswego, NY 13126 Mr. Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271

FitzPatrick Nuclear Power Plant cc:

Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Oswego County Administrator Mr. Steven Lyman 46 East Bridge Street Oswego, NY 13126 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Paul Eddy New York State Dept. of Public Service 3 Empire State Plaza Albany, NY 12223-1350 Mr. John M. Fulton Assistant General Counsel Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Ken L. Graesser BWR SRC Consultant 38832 N. Ashley Drive Lake Villa, IL 60046 Mr. Jim Sniezek Nuclear Management Consultant 5486 Nithsdale Drive Salisbury, MD 21801 Mr. Ron Toole BWR SRC Consultant 1282 Valley of Lakes Box R-10 Hazelton, PA 18202 Ms. Stacey Lousteau Treasury Department Entergy Services, Inc.

639 Loyola Avenue Mail Stop L-ENT-15E New Orleans, LA 70113 Mr. Michael Kansler, President Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10611