Public Meeting Slides, Palisades 2003 End-of-Cycle AssessmentML041310056 |
Person / Time |
---|
Site: |
Palisades |
---|
Issue date: |
05/06/2004 |
---|
From: |
NRC/RGN-III |
---|
To: |
|
---|
References |
---|
Download: ML041310056 (19) |
|
|
---|
Category:Slides and Viewgraphs
MONTHYEARML24296B1652024-10-22022 October 2024 Pre-Submittal Meeting Slides Oct 24 GSI191 ML24212A3452024-07-30030 July 2024 August 1, 2024 Holtec Public Meeting Presentation on Potential Palisades Nuclear Plant Restart ML24193A0252024-07-11011 July 2024 NRC Presentation on Palisades Nuclear Plant Potential Reauthorization Scoping Meeting PNP 2024-023, Pre-Submittal Meeting Presentation - License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis2024-05-0909 May 2024 Pre-Submittal Meeting Presentation - License Amendment Request to Approve the Biasi Critical Heat Flux (CHF) Correlation for Use with the Palisades Main Steam Line Break (MSLB) Analysis ML24116A2932024-04-29029 April 2024 Pre-Submittal Meeting on April 29, 2024 - Palisades Nuclear Plant Power Operations Quality Assurance Program Manual ML24086A5822024-04-0303 April 2024 Construction Permit Application: Initial Environmental & Site Characterization ML24074A3302024-03-18018 March 2024 March 18, 2024 Pre-submittal Meeting for Proposed Emergency Plan at the Palisades Nuclear Plant (Presentation) ML24036A1082024-02-0606 February 2024 Pre-submittal Meeting for Palisades Nuclear Plant Power Operations Technical Specifications Administrative Controls and Quality Assurance Program (Presentation) ML23334A1322023-12-0505 December 2023 Pre-submittal Meeting with Holtec for Palisades Nuclear Plant Power Operations Technical Specifications (Presentation) PNP 2023-026, Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations2023-09-28028 September 2023 Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations ML23235A1802023-08-29029 August 2023 Public Meeting 08/29/23 - Palisades Nuclear Plant - Return to Power Operations - Exemption to CFR 50.82(a)(2) ML23139A1922023-05-24024 May 2023 Slides for Public Meeting on 5/24/23 ML23075A3312023-03-16016 March 2023 KM Session OL Process February 9, 2023 ML23075A3322023-03-16016 March 2023 Containment 2008 ML23075A3332023-03-16016 March 2023 Ts/Rg 1.33 V. Appendix B, Criterion V ML23075A3352023-03-16016 March 2023 KM-KT Session Presentation Disputed Violations PNP 2023-012, Presentation on Regulatory Path to Reauthorize Power Operations2023-03-16016 March 2023 Presentation on Regulatory Path to Reauthorize Power Operations ML22262A3032022-09-22022 September 2022 Post-Shutdown Decommissioning Activities Report Public Meeting Slides - September 22, 2022 ML22153A1702022-06-16016 June 2022 Public Presentation Slides for Palisades Webinar June 16, 2022 ML21196A0872021-07-15015 July 2021 Slideshow for the July 1, 2021 Public End of Cycle Meeting for Palisades Nuclear Plant ML21124A0062021-05-12012 May 2021 Pre-Application PDTS Meeting Slides (L-2021-LRM-xxxx) ML20342A0022020-12-0808 December 2020 NRC License Transfer Application Pre-Submittal Meeting ML20269A3452020-09-28028 September 2020 Pre-submittal Meeting for Request for One-Time Exemption from 10 CFR Part 50, Appendix E, Biennial EP Exercise (Offsite) Due to COVID-19- Entergy Presentation Slides ML20231A2312020-08-17017 August 2020 2019 Palisades - EOC Presentation ML19231A2852019-08-19019 August 2019 NEIMA Meeting Slides - August 21 Palisades Meeting ML18107A3342018-04-10010 April 2018 Tech Spec 3.3.5.2a Change Pre-Submittal Meeting Presentation Slides ML18075A1232018-03-20020 March 2018 Entergy Nuclear Operations - March 20, 2018, Presentation Slides for Surveillance Frequency Control Program, UFSAR Change Considerations ML17335A0332017-11-28028 November 2017 Meeting Slides for November 27, 2017 Public Meeting with Entergy Nuclear Operations, Inc. Regarding Request to Extend Enforcement Discretion for Tornado Missle Non-Conformances ML17160A1952017-06-12012 June 2017 Meeting Slides for Pre-Submittal Meeting with Entergy Regarding the Plan for Decommissioning Licensing Actions PNP 2017-017, Notification in Response to Confirmatory Order, EA-15-0392017-05-0404 May 2017 Notification in Response to Confirmatory Order, EA-15-039 ML17080A1782017-03-20020 March 2017 3/20/2017, Meeting Slide Re. Palisades Nuclear Plant License Amendment Request; Application Meeting Cyber Security Plan Milestone 8 Implementation Schedule Change ML16344A0882016-12-0707 December 2016 December 7, 2016, Summary of Public Meeting with Entergy Nuclear Operations, Inc.- Meeting Slides ML16277A6212016-09-28028 September 2016 GSI-191 Closure Plan: September 28, 2016 - Meeting Slides ML16167A3722016-06-23023 June 2016 Nrc'S Annual Performance Assessment of Palisades for 2015 ML15107A3062015-04-14014 April 2015 April 14, 2015, Public Meeting Slides for Primary Coolant System Branch Connection Weld Volumetric Examination Status - Palisades Nuclear Plant ML15107A3072015-04-14014 April 2015 April 14, 2015, Corrected Public Meeting Slides for Primary Coolant System Branch Connection Weld Volumetric Examination Status - Palisades Nuclear Plant ML15093A2902015-04-0303 April 2015 Licensee End-of-Cycle Meeting Slides ML15093A2942015-04-0303 April 2015 NRC Meeting Slides ML15012A3682015-01-12012 January 2015 EA-14-168; Palisades Nuclear Plant Conference Slides ML14175A2842014-06-24024 June 2014 NRC Presentation for Palisades 2013 Annual Assessment Public Meeting ML14175A2992014-06-24024 June 2014 Licensee Presentation for Palisades 2013 Annual Assessment Public Meeting ML13316C4722013-11-14014 November 2013 Palisades Independent Spent Fuel Storage Installation (ISFSI) at Nuclear Power Plants ML13262A4492013-09-23023 September 2013 October 9, 2013, EMA Presentation Slides for Conference Call with Entergy Nuclear Operations ML13193A3302013-07-16016 July 2013 NRC Internet Event Briefing - Palisades Safety Injection Refueling Water Tank (SIRWT) Leak Repair and Inspections ML13190A2552013-07-16016 July 2013 NRC Internet Event Briefing - Palisades Safety Injection Refueling Water Tank (SIRWT) Leak Repair and Inspections ML13140A3582013-05-20020 May 2013 May 23, 2013 NRC Presentation ML13093A1912013-04-0303 April 2013 EOC Public NRC Meeting Slides Final ML13091A1172013-04-0101 April 2013 EOC Licensee Slides for April 2, 2013 Meeting ML13091A2202013-03-29029 March 2013 Public Meeting Slides ML13080A3852013-03-21021 March 2013 NRC Slides for EOC Meeting 4/2/13 2024-07-30
[Table view] |
Text
Palisades Annual Assessment Meeting Reactor Oversight Program - CY 2003 Nuclear Regulatory Commission - Region 3 Lisle, Illinois May 6, 2004
NRC Representatives l Steven Reynolds, Acting Division Director, DRP K (630) 829-9600 l Jay Lennartz, Senior Resident Inspector K (269) 764-8971 l Michelle Garza, Resident Inspector K (269) 764-8971 l Eric Duncan, Branch Chief K (630) 829-9628
Agenda l Review of Reactor Oversight Process l National Summary of Plant Performance l Discussion of Plant Performance Results l Licensee Response and Remarks l NRC Closing Remarks l NRC Available to Address Public Questions
Region III Organization James Caldwell Regional Administrator Geoffrey Grant Deputy Regional Administrator Steven Reynolds Cynthia Pederson Acting Director, DRP Director, DRS Patrick Hiland Roy Caniano Acting Deputy Director, DRP Deputy Director, DRS Eric Duncan Regional Specialists Branch Chief Palisades Staff Reactor Engineer Jay Lennartz -SRI Raymond Ng Michelle Garza - RI Robert Ruiz Rosemary Jones - Secretary
NRC Performance Goals l Maintain safety and protect the environment l Enhance public confidence l Improve effectiveness, efficiency, and realism of processes and decision making l Reduce unnecessary regulatory burden
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response
Examples of Baseline Inspections l Equipment Alignment ~92 hrs/yr l Triennial Fire Protection ~200 hrs every 3 yrs l Operator Response ~125 hrs/yr l Emergency Preparedness ~80 hrs/yr l Rad Release Controls ~100 hrs every 2 yrs l Worker Radiation Protection ~100 hrs/yr l Corrective Action Program ~250 hrs every 2 yrs l Corrective Action Case Reviews ~60 hrs/yr
Significance Threshold Performance Indicators Green: Only baseline inspections required White: May increase NRC oversight Yellow: Requires more NRC oversight Red: Requires more NRC oversight Inspection Findings Green: Very low safety significance White: Low to moderate safety significance Yellow: Substantial safety significance Red: High safety significance
Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions
Purpose of Todays Meeting l A public forum for discussion of the licensees performance l NRC will discuss the licensee performance issues identified in the annual assessment letter l Licensee will respond to the information in the letter and inform the NRC of new or existing programs to maintain or improve their performance
National Summary of Plant Performance Status at End of CY 2003 Licensee Response 75 Regulatory Response 22 Degraded Cornerstone 2 Multiple/Repetitive Degraded Cornerstone 3 Unacceptable 0 Total 102*
National Summary l Performance Indicator Results (at end of CY 2003) u Green 1825 u White 15 u Yellow 0 u Red 0 l Total Inspection Findings (CY 2003) u Green 748 u White 9 u Yellow 2 u Red 1
Palisades Annual Assessment Summary January 1 - December 31, 2003 l NMC operated Palisades in a manner that preserved public health and safety.
l All cornerstone objectives were met with one White inspection finding.
l A substantive cross-cutting issue in the Problem Identification and Resolution area was closed.
l NRC planned baseline inspections at Palisades for the assessment period and a supplemental inspection to review corrective actions to address the White finding.
Safety Significant Findings or PIs l One White Inspection Finding in the Initiating Events Cornerstone. A loss of offsite power and loss of shutdown cooling occurred when workers installing a signpost in the parking lot damaged a cable which contained offsite power protective relaying circuitry.
l All other Inspection Findings and Performance Indicators for the assessment period were Green.
Palisades Inspection Activities (Jan 1 - Dec 31, 2003) l A Special Inspection was conducted to review the circumstances surrounding a March 18 breaker fire in the cable spreading room and a March 25 loss of offsite power and loss of shutdown cooling event. Both events resulted in Alert declarations.
Palisades Inspection Activities (Jan 1 - Dec 31, 2004) l Biennial Problem Identification and Resolution Inspection (completed) l White Finding - Supplemental Inspection (completed) l Biennial Safety System Design Inspection (completed) l Emergency Preparedness Exercise Inspection
Licensee Response and Remarks Daniel J. Malone Site Vice President Palisades Nuclear Plant
Contacting the NRC l Report an emergency u (301) 816-5100 (call collect) l Report a safety concern:
u (800) 695-7403 u Allegation@nrc.gov l General information or questions u www.nrc.gov u Select What We Do for Public Affairs
Reference Sources l Reactor Oversight Process K http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html l Public Electronic Reading Room K http://www.nrc.gov/reading-rm.html l Public Document Room K 1-800-397-4209 (Toll Free)