April 29, 2004 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
BRAIDWOOD STATION RE-SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS
Dear Mr. Crane:
In a letter dated March 15, 2004 (BW040028), your staff requested that the NRC re-schedule an initial license examination from August/September 2005 to May 2006 at the Braidwood Station. The examination scheduled for 2005 has been removed from our examination schedule. We are not currently scheduling examinations during calendar year 2006. However, your requested examination has been noted and will be given first consideration for the requested dates (May 15 and 22, 2006) when we begin calendar year 2006 scheduling. Yours is currently the only request for an examination during May 2006.
On-site validation of the examinations will occur at Braidwood Station approximately three weeks before the examination administration date which is different than the April 3, 2006 date proposed in your letter. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examination at a mutually acceptable date.
We anticipate that your staff will develop the examination. Please inform us if the number of candidates decreases below 10 as this will impact the examination schedule.
A letter will be sent to the Braidwood Station Training Department after we have completed scheduling efforts for calendar year 2006 to inform them of the schedule. An additional letter will be sent approximately 120 days prior to the initial examination informing them of the chief examiners name and examination security expectations. The letter will list the materials required by the NRC to conduct the examination, reconfirm the examination dates, and reconfirm the number of candidates you have in the training program. If you have any questions concerning this information, please contact Mr. M. Bielby of my staff at 630-829-9762.
C. Crane In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Roger D. Lanksbury, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77 cc w/encl:
Site Vice President - Braidwood Station Plant Manager - Braidwood Station Regulatory Assurance Manager - Braidwood Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer Chairman, Illinois Commerce Commission
C. Crane In accordance with 10 CFR 2.390 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Roger D. Lanksbury, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-456; 50-457 License Nos. NPF-72; NPF-77 cc w/encl:
Site Vice President - Braidwood Station Plant Manager - Braidwood Station Regulatory Assurance Manager - Braidwood Station Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer Chairman, Illinois Commerce Commission DOCUMENT NAME: G:\\DRS\\ML041200575.wpd To receive a copy of this document, indicate in the box "C" = Copy w/o attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII:DRS RIII:DRS NAME DMcNeil for MBielby:sd RDLanksbury DATE 04/29/04 04/29/04 OFFICIAL RECORD COPY
C. Crane ADAMS Distribution:
AJM DFT MLC RidsNrrDipmIipb GEG HBC SPR DRPIII DRSIII PLB1 JRK1 M. A. Bies, DRS D. C. Trimble, NRR:DIPM:IOLB