Other: 2CAN010401, Arkansas, Unit 2 - License Renewal Application Clarifications, 2CAN020502, License Renewal Clarification, Arkansas Nuclear One - Unit 2, 2CAN030401, License Renewal Application Clarifications, Arkansas Nuclear One - Unit 2, 2CAN070409, Unit 2, License Renewal Application Clarifications, 2CAN080401, Unit 2, License Renewal Application Clarifications, 2CAN090402, Unit 2, License Renewal Application Clarifications, 2CAN100302, License Renewal Application, Attachment a - E, ML040900270
|
MONTHYEAR2CAN100302, License Renewal Application, Attachment a - E2003-10-14014 October 2003 License Renewal Application, Attachment a - E Project stage: Other ML0407706112003-12-22022 December 2003 E-Mail MSIV Leakage Pathway RAI & License Amendment Request - Attachment 3 Project stage: Request ML0407706062003-12-22022 December 2003 E-mail Draft Proposed Emergency Changes to Technical Specifications 3.8.1.1 to Support Steam Diesel Generator Inspections - Attachment 4 Project stage: Request ML0407705992003-12-22022 December 2003 Draft Information Input Configuration Risk Management Program - Attachment 5 Project stage: Request ML0407705932003-12-23023 December 2003 Draft Information Request PRA Analysis Assessment PRA-03-024, Rev. 0 - Attachment 6 Project stage: Request ML0407705842003-12-28028 December 2003 Draft Information Input Material Discussion - Attachment 8 Project stage: Request 2CAN010401, Arkansas, Unit 2 - License Renewal Application Clarifications2004-01-22022 January 2004 Arkansas, Unit 2 - License Renewal Application Clarifications Project stage: Other ML0406105422004-02-26026 February 2004 & 12/16/2003 Summary of Telephone Calls with Entergy Operations Incorporated Regarding Draft Responses to Questions Pertaining to the Arkansas Nuclear One, Unit 2 License Renewal Application Project stage: Draft Other ML0407104662004-03-0808 March 2004 Request for Additional Information for the Review of the Arkansas Nuclear One, Unit 2, License Renewal Application Project stage: RAI 2CAN030401, License Renewal Application Clarifications, Arkansas Nuclear One - Unit 22004-03-24024 March 2004 License Renewal Application Clarifications, Arkansas Nuclear One - Unit 2 Project stage: Other ML0409002702004-03-29029 March 2004 Summary of Telephone Call Between U.S. Nuclear Regulatory Commission (NRC) and Entergy Operations Incorporated Concerning Questions Pertaining to Aging Management Review for Arkansas Nuclear One, Unit 2 LRA Project stage: Other 2CAN040401, Unit 2, Request for Additional Information Responses for License Renewal Application TAC No. MB84022004-04-0606 April 2004 Unit 2, Request for Additional Information Responses for License Renewal Application TAC No. MB8402 Project stage: Request ML0409902302004-04-0808 April 2004 Request for Additional Information for the Review of the Arkansas Nuclear One, Unit 2, License Renewal Application Project stage: RAI ML0410508202004-04-13013 April 2004 Request for Additional Information for the Review of the Arkansas Nuclear One, Unit 2, License Renewal Application Project stage: RAI ML0408206822004-04-13013 April 2004 Draft Information Input, Memo from 12/2/03 to 12/28/03 Project stage: Request ML0410508582004-04-14014 April 2004 Request for Additional Information, Review of the Arkansas Nuclear One, Unit 2, License Renewal Application Project stage: RAI ML0412003842004-04-23023 April 2004 Request for Additional Information for the Review of the Arkansas Nuclear One, Unit 2, License Renewal Application Project stage: RAI ML0412805542004-05-0505 May 2004 RAI, License Renewal Application, Section 3.3 Auxiliary Systems Project stage: RAI ML0413304862004-05-11011 May 2004 Request for Additional Information for Arkansas Nuclear One-Unit 2 License Renewal Application from Plant Systems Branch Division of Systems Safety and Analysis Docket No. 50-368 Project stage: RAI 05000368/LER-2004-001, Unit 2 Operation Prohibited by Technical Specifications Due to an Inoperable Channel of Wide-Range Containment Water Level Instrumentation2004-05-17017 May 2004 Unit 2 Operation Prohibited by Technical Specifications Due to an Inoperable Channel of Wide-Range Containment Water Level Instrumentation Project stage: Request ML0413802842004-05-17017 May 2004 Request for Additional Information for the Review of the Arkansas Nuclear One, Unit 2, License Renewal Application (Tac No. MB8402) Project stage: RAI 2CAN050404, Arkansas, Unit 2, Request for Additional Information Responses for License Renewal Application2004-05-19019 May 2004 Arkansas, Unit 2, Request for Additional Information Responses for License Renewal Application Project stage: Request 2CAN050401, Arkansas, Unit 2 - Request for Additional Information Responses for License Renewal Application2004-05-19019 May 2004 Arkansas, Unit 2 - Request for Additional Information Responses for License Renewal Application Project stage: Request 2CAN050403, Arkansas, Unit 2 - Request for Additional Information Responses for License Renewal Application2004-05-19019 May 2004 Arkansas, Unit 2 - Request for Additional Information Responses for License Renewal Application Project stage: Request 2CAN050402, Arkansas, Unit 2, Request for Additional Information Response for License Renewal Application2004-05-19019 May 2004 Arkansas, Unit 2, Request for Additional Information Response for License Renewal Application Project stage: Request 2CAN050407, Unit 2, Request for Additional Information Responses for License Renewal Application TAC No. MB84022004-05-24024 May 2004 Unit 2, Request for Additional Information Responses for License Renewal Application TAC No. MB8402 Project stage: Request ML0414700212004-05-25025 May 2004 Request for Additional Information for Review of Arkansas Nuclear One, Unit 2, License Renewal Application - DE Eeib Mcconnell Knox Project stage: RAI ML0414801342004-05-26026 May 2004 Request for Additional Information for the Review of the Arkansas Nuclear One, Unit 2, License Renewal Application (Tac No. MB8402) Project stage: RAI 2CAN060401, Arkansas, Unit 2, Request for Additional Information Responses for License Renewal Application2004-06-10010 June 2004 Arkansas, Unit 2, Request for Additional Information Responses for License Renewal Application Project stage: Request ML0416202472004-06-11011 June 2004 Request for Additional Information, Arkansas Nuclear One, Unit 2, License Renewal Application Project stage: RAI 2CAN060403, Unit 2 - Request for Additional Information Responses for License Renewal Application TAC No. MB84022004-06-16016 June 2004 Unit 2 - Request for Additional Information Responses for License Renewal Application TAC No. MB8402 Project stage: Request ML0417305712004-06-21021 June 2004 Summary of Telephone Call with Entergy Operations, Inc., Representatives Regarding Draft Request for Additional Information Pertaining to the Arkansas Nuclear One, Unit 2 License Renewal Application Project stage: Draft RAI ML0417305262004-06-21021 June 2004 & 04/16/2004 Summary of Telephone Calls Between the U.S. NRC Staff and Entergy Operations, Inc., Representatives Concerning Draft Request for Additional Information Pertaining to the Arkansas Nuclear One Project stage: Draft RAI ML0417700372004-06-23023 June 2004 & 05/27/2004, Summary of Telephone Calls Held Between the U.S. Nuclear Regulatory Commission (NRC) Staff and Entergy Operations, Inc., Representatives Concerning Drai Pertaining to the Arkansas One, Unit 2, License Renewal Application Project stage: RAI ML0417705572004-06-24024 June 2004 Request for Additional Information, Review of the Arkansas Nuclear One, Unit 2, License Renewal Application Project stage: RAI 2CAN070404, Unit 2, Request for Additional Information Responses for License Renewal Application2004-07-0101 July 2004 Unit 2, Request for Additional Information Responses for License Renewal Application Project stage: Request ML0419602602004-07-14014 July 2004 Summary of Telephone Conference Call Held on June 30, 2004, Between NRC and Entergy Representatives Concerning Request for Additional Information Pertaining to the Arkansas Nuclear One, Unit 2, LRA Project stage: RAI ML0421603562004-07-22022 July 2004 Unit 2, Request for Additional Information Responses for License Renewal Application Project stage: Request 2CAN070409, Unit 2, License Renewal Application Clarifications2004-07-22022 July 2004 Unit 2, License Renewal Application Clarifications Project stage: Other 2CAN070406, Unit 2, Request for Additional Information Responses for License Renewal Application2004-07-22022 July 2004 Unit 2, Request for Additional Information Responses for License Renewal Application Project stage: Request 2CAN080401, Unit 2, License Renewal Application Clarifications2004-08-18018 August 2004 Unit 2, License Renewal Application Clarifications Project stage: Other ML0423703952004-08-23023 August 2004 Summary of Telephone Conference Held on July 28, 2004, Between the USNRC and Entergy Operations, Inc., Concerning a Request for Additional Information Pertaining to the Arkansas Nuclear Station, Unit 2, License Renewal Application Project stage: RAI ML0423806322004-08-25025 August 2004 Summary of Telephone Call Held on July 7 and 8, 2004, Between the U.S. Nuclear Regulatory Commission (NRC) Staff and Entergy Operations Inc., Representatives Concerning Request for Additional Information Pertaining to the Arkansas Nuclear O Project stage: RAI 2CAN090402, Unit 2, License Renewal Application Clarifications2004-09-10010 September 2004 Unit 2, License Renewal Application Clarifications Project stage: Other ML0427406512004-09-30030 September 2004 Summary of Telephone Calls Held on August 26 and September 1, 2004, Between the U.S. NRC Staff and Entergy Operations Inc., Representatives Concerning RAI Pertaining to the Arkansas Nuclear One, Unit 2 LRA Project stage: RAI ML0427406292004-09-30030 September 2004 Summary of Telephone Call Held on August 24, 2004, Between the U.S. Nuclear Regulatory Commission (NRC) Staff and Entergy Operations Inc., Representatives Concerning Request for Additional Information Pertaining to the Arkansas Nuclear One, Project stage: RAI 2CAN120403, License Renewal Application Draft Safety Evaluation Report Comments2004-12-0909 December 2004 License Renewal Application Draft Safety Evaluation Report Comments Project stage: Draft Other 2CAN020502, License Renewal Clarification, Arkansas Nuclear One - Unit 22005-02-28028 February 2005 License Renewal Clarification, Arkansas Nuclear One - Unit 2 Project stage: Other 2004-05-24
[Table View] |
Text
April 8, 2004 Mr. Jeff Forbes Vice President, Operations ANO Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE ARKANSAS NUCLEAR ONE, UNIT 2, LICENSE RENEWAL APPLICATION (TAC NO. MB8402)
Dear Mr. Forbes:
The U.S. Nuclear Regulatory Commission (NRC) is reviewing a license renewal application (LRA) submitted by Entergy Operators Inc. (Entergy or the applicant) dated October 14, 2003 for the renewal of the operating licenses for Arkansas Nuclear One, Unit 2, pursuant to Title 10 Code of Federal Regulations Part 54 (10 CFR Part 54). The NRC staff has identified, in the enclosure, areas where additional information is needed to complete the review. Specifically, the enclosed requests for additional information (RAIs) are from Section 2.1 Scoping and Screening Methodology and Section 2.3 System Scoping and Screening Results: Mechanical.
These RAIs have been discussed with your staff.
Your responses to these RAIs are requested within 30 days from the receipt of this letter. If you have any questions, please contact me at (301) 415-1124 or e-mail gxs@nrc.gov.
Sincerely,
/RA/
Gregory F. Suber, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No.: 50-368
Enclosure:
As stated cc w/encl: See next page
April 8, 2004 Mr. Jeff Forbes Vice President, Operations ANO Entergy Operations, Inc.
1448 S. R. 333 Russellville, AR 72801
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE ARKANSAS NUCLEAR ONE, UNIT 2, LICENSE RENEWAL APPLICATION (TAC NO. MB8402)
Dear Mr. Forbes:
The U.S. Nuclear Regulatory Commission (NRC) is reviewing a license renewal application (LRA) submitted by Entergy Operators Inc. (Entergy or the applicant) dated October 14, 2003 for the renewal of the operating licenses for Arkansas Nuclear One, Unit 2, pursuant to Title 10 Code of Federal Regulations Part 54 (10 CFR Part 54). The NRC staff has identified, in the enclosure, areas where additional information is needed to complete the review. Specifically, the enclosed requests for additional information (RAIs) are from Section 2.1 Scoping and Screening Methodology and Section 2.3 System Scoping and Screening Results: Mechanical.
These RAIs have been discussed with your staff.
Your responses to these RAIs are requested within 30 days from the receipt of this letter. If you have any questions, please contact me at (301) 415-1124 or e-mail gxs@nrc.gov.
Sincerely,
/RA/
Gregory F. Suber, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No.: 50-368
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION: See next page Accession No: ML040990230 Document Name: C:\\ORPCheckout\\FileNET\\ML040990230.wpd OFFICE:
LA:RLEP PM:RLEP SC:RLEP NAME:
MJenkins GSuber SLee DATE:
4/6/04 4/5/04 4/8/04 OFFICIAL RECORD COPY
Attachment REQUEST FOR ADDITIONAL INFORMATION PERTAINING TO THE SCOPING AND SCREENING REVIEW OF THE ARKANSAS NUCLEAR ONE - UNIT 2 LICENSE RENEWAL APPLICATION (TAC NO. MB8402)
Division of Systems Safety and Analysis (DSSA)
RAI 2.3-1 Section 2.1.1 states the following with respect to the scoping methodology for the Heating, Ventilation, and Air Conditioning (HVAC) Systems: "Consistent with NEI 95-10, the scoping process used for the ANO-2 license renewal project began with a list of plant systems and structures, determined the functions they perform, and then determined which functions met any of the three criteria of 10 CFR 54.4(a). Functions that meet any of the criteria are intended functions for license renewal, and the systems and structures that perform these functions are included within the scope of license renewal." In order for the staff to determine that you have not omitted any structures, systems, and components that should be within the scope of license renewal according to 10 CFR 54.4(a), describe the details of the process used to confirm whether you have included all the structures, systems, and components in such systems and structures within the scope of license renewal.
RAI 2.3-2 In the preface to the LRA on Page 1 it is stated in the third paragraph that, "....the Tables provide a reference to the results of the aging management review for each component and commodity type. The descriptions of systems in Section 2 identify license renewal drawings that document the components subject to aging management review for mechanical systems.
The drawings are provided in a separate submittal."
Also, in Section 2.1.1, "Scoping Methodology," you have stated that, "License renewal drawings were prepared to indicate components subject to aging management review. Components that are subject to aging management review based only on the criterion of 10CFR54.4(a)(2) are not indicated on the drawings."
In order for the staff to determine that you have not omitted any structures, systems, and components that should be within the scope of license renewal according to 10 CFR 54.4(a),
describe the process used to confirm whether you have included all the structures, systems, and components in the scope of license renewal for the HVAC Systems.
RAI 2.3-3 The staff requests that the applicant:
a.
Clarify whether the sealants used on the main control room envelope (MCRE) to prevent unfiltered inleakages are included in the scope of license renewal in accordance with 10 CFR 54.4(a), and subject to an aging management review in accordance with 10 CFR 54.21(a)(1). If so, provide the relevant information to complete Table 2.3.3.10. Additionally, does structural sealants ("Elastomers"),
as listed in Table 2.4-4 of the LRA, include the MCRE ductwork and component housing sealants ? If the sealants are not considered subject to an AMR, provide justification for their exclusion.
b.
Clarify whether sealants used as a pressure boundary function for the auxiliary building ventilation system are within the scope of license renewal in accordance with 10 CFR 54.4(a), and subject to an aging management review in accordance with 10 CFR 54.21(a)(1). If they are, provide the relevant information about the sealants to complete Table 2.3.3.9. If the sealants are excluded from the scope of license renewal and not subject to an AMR, provide justification for this exclusion.
RAI 2.3-4 It seems that the penetration rooms ventilation system (see ANO-2 FSAR Section 6.5, "Penetration Rooms Ventilation System") is excluded from the license renewal application. If it is addressed as part of other ventilation systems, provide related information for the penetration rooms ventilation system components that are within the scope of license renewal in accordance with 10 CFR 54.4(a), and subject to an aging management review in accordance with 10 CFR 54.21(a)(1) or provide justification for the exclusion of the penetration rooms ventilation system from the LRA.
Additionally, provide the relevant information in the AMR table about the penetration room sealant materials use for a pressure boundary function that are within the scope of the license renewal in accordance with 10 CFR 54.4(a) and subject to an aging management review in accordance with 10 CFR 54.21(a)(1) or provide justification for its exclusion.
RAI 2.3-5 Table 2.3.2-5 for Hydrogen Control System Components Subject to Aging Manangement Review does not list Separators 2F-254 and 2F-256 shown on ANO-2 piping and instrument diagram LRA-M-2261 Sheet 3, as components requiring an AMR. Please identify where the LRA addresses the AMR of these components or provide a justification for excluding these components from an AMR.
DISTRIBUTION: Ltr. to Jforbes, Re: ANO-2, Dated: April 8, 2004 ML040990230 HARD COPY RLEP RF Project Manager E-MAIL:
PUBLIC J. Craig D. Matthews F. Gillespie C. Grimes RidsNrrDe E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair S. Black B. Boger D. Thatcher R. Pettis G. Galletti C. Li M. Itzkowitz R. Weisman M. Mayfield A. Murphy S. Smith (srs3)
S. Duraiswamy Y. L. (Renee) Li RLEP Staff J. Minns R. Gramm A. Howell T. Alexion Linda Smith RIV
Arkansas Nuclear One, Unit 2 cc:
Executive Vice President
& Chief Operating Officer Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Director, Division of Radiation Control and Emergency Management Arkansas Department of Health 4815 West Markham Street, Slot 30 Little Rock, AR 72205-3867 Winston & Strawn 1400 L Street, N.W.
Washington, DC 20005-3502 Mr. Mike Schoppman Framatome ANP, Richland, Inc.
Suite 705 1911 North Fort Myer Drive Rosslyn, VA 22209 Senior Resident Inspector U.S. Nuclear Regulatory Commission P. O. Box 310 London, AR 72847 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 County Judge of Pope County Pope County Courthouse Russellville, AR 72801 Vice President, Operations Support Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Wise, Carter, Child & Caraway P. O. Box 651 Jackson, MS 39205 Garry Young 1448 SR 333 Russellville, AR 72802 Mr. Fred Emerson Nuclear Energy Institute 1776 I St., N.W., Suite 400 Washington, DC 20006-3708