Summary of Meeting with FPL Energy Regarding Stretch Power Uprate Request for Seabrook Station, Unit No. 1
ML040770598
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 03/29/2004
From: Licata L
NRC/NRR/DLPM/LPD1
To: Darrell Roberts
NRC/NRR/DLPM/LPD1
Licata L NRR/DLPM/LPDI 415-4090
References
TAC MC1739
Download: ML040770598 (5)


Text

March 29, 2004 MEMORANDUM TO: Darrell J. Roberts, Acting Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM:

Lee A. Licata, Project Manager, Section 2

/RA/

Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF MARCH 3, 2004, MEETING WITH FPL ENERGY REGARDING STRETCH POWER UPRATE REQUEST FOR SEABROOK STATION, UNIT NO. 1 (TAC NO. MC1739)

Background

On March 3, 2004, the U.S. Nuclear Regulatory Commission (NRC) staff met with FPL Energy (FPLE) representatives at the NRC Headquarters in Rockville, Maryland, at FPLEs request.

The objective of the meeting was to discuss FPLEs planned request for a stretch power uprate (SPU) license amendment for Seabrook Station, Unit No. 1 (Seabrook). The meeting was classified as a Category 1 meeting. The meeting announcement and agenda are listed in the Agencywide Documents Access and Management System (ADAMS) under accession number ML040280013. The meeting presentation is in ADAMS under accession number ML040630431. The list of attendees is attached.

Discussion FPLE plans to submit a license amendment request which will justify increasing the rated thermal power of Seabrook from the current licensed level of 3411 megawatts thermal (MWt) to 3587 MWt. This proposed SPU would result in an approximate 5-percent thermal power increase from the current licensed level. FPLE reported that they plan to submit the SPU application in March of 2004. FPLE requested the NRC staff review be completed within approximately nine months of their submittal.

The NRC staff noted that a number of major modifications were being performed, and that a discussion needs to occur within the staff to determine if this uprate is a stretch power uprate or an extended power uprate. It was discussed that the Review Standard For Extended Power Uprates (RS-001) will be used as a guide for this power uprate request.

The following additional areas were discussed between the staff and FPLEs representatives:

Testing: The use of an integrated test plan to confirm that the plant is operating as expected following the completion of the SPU work was discussed. The use of DRAFT Standard Review Plan 14.2.1, Generic Guidelines for Extended Power Uprate Testing Programs, to manage post-SPU testing, temporary test instrumentation to confirm specific component performance, and baseline testing were also addressed.

Spent Fuel Pool: Heat load and criticality calculations of post-SPU fuel bundles were discussed.

Miscellaneous: The following additional items were briefly discussed:

1.

The change to residual heat removal system cooldown times.

2.

The effects of over-pressure during postulated accidents.

3.

Refuel water storage tank usage impact.

4.

Meeting current General Design, Licensing and Design Bases criteria.

5.

Main steam line pressure and vibration measurements post SPU.

6.

Setpoint methodology analytical and operational limits.

7.

New Hampshire Site Evaluation Committee determination.

Comments from members of the public Two members of the public attended the meeting. They had no comments or questions.

Conclusion The NRC staff did not make any regulatory decisions during the meeting.

Docket No. 50-443

Attachment:

As stated cc w/encl: See next page post-SPU testing, temporary test instrumentation to confirm specific component performance, and baseline testing were also addressed.

Spent Fuel Pool: Heat load and criticality calculations of post-SPU fuel bundles were discussed.

Miscellaneous: The following additional items were briefly discussed:

1.

The change to residual heat removal system cooldown times.

2.

The effects of over-pressure during postulated accidents.

3.

Refuel water storage tank usage impact.

4.

Meeting current General Design, Licensing and Design Bases criteria.

5.

Main steam line pressure and vibration measurements post SPU.

6.

Setpoint methodology analytical and operational limits.

7.

New Hampshire Site Evaluation Committee determination.

Comments from members of the public Two members of the public attended the meeting. They had no comments or questions.

Conclusion The NRC staff did not make any regulatory decisions during the meeting.

Docket No. 50-443

Attachment:

As stated cc w/encl: See next page DISTRIBUTION:

See next page ADAMS Accession Numbers: Memorandum: ML040770598;

Attachment:

ML ;

Package: ML040850060 OFFICE PD1-2/PM PD1-2/PM PDI-2/LA PD1-2/SC(A)

NAME LLicata LLicata for VNerses CRaynor DRoberts DATE 03/25/04 03/25/04 03/25/04 03/29/04 OFFICIAL RECORD COPY

DISTRIBUTION:

PUBLIC PD1-2 Reading LMarsh AHowe DRoberts LLicata CRaynor AMcMurtray (EPU Coordinator), OPA CWu VNerses JClifford JAlbright HGarg CBixler, RI JJolicoeur, EDO RI OGC ACRS/ACNW MBarillas

Seabrook Station, Unit No. 1 cc:

Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Peter Brann Assistant Attorney General State House, Station #6 Augusta, ME 04333 Resident Inspector U.S. Nuclear Regulatory Commission Seabrook Nuclear Power Station P.O. Box 1149 Seabrook, NH 03874 Town of Exeter 10 Front Street Exeter, NH 03823 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Attorney General One Ashburton Place, 20th Floor Boston, MA 02108 Board of Selectmen Town of Amesbury Town Hall Amesbury, MA 01913 Mr. Dan McElhinney Federal Emergency Management Agency Region I J.W. McCormack P.O. &

Courthouse Building, Room 401 Boston, MA 02109 Mr. Jack Devine Polestar Applied Technology One First Street, Suite 4 Los Altos, CA 94019 Mr. Stephen McGrail, Director ATTN: James Muckerheide Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399 Philip T. McLaughlin, Attorney General Steven M. Houran, Deputy Attorney General 33 Capitol Street Concord, NH 03301 Mr. Donald Bliss, Director New Hampshire Office of Emergency Management State Office Park South 107 Pleasant Street Concord, NH 03301 Mr. Daniel G. Roy Nuclear Training Manager Seabrook Station FPL Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 Mr. Gene F. St. Pierre Station Director Seabrook Station FPL Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 Mr. M. S. Ross, Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Mark E. Warner, Site Vice President c/o James M. Peschel Seabrook Station PO Box 300 Seabrook, NH 03874