MONTHYEARNOC-AE-240040, Change to South Texas Project Electric Generating Station (STPEGS) Emergency Plan2024-10-16016 October 2024 Change to South Texas Project Electric Generating Station (STPEGS) Emergency Plan NOC-AE-230039, Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/20230032023-12-12012 December 2023 Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/2023003 NOC-AE-230040, Update Foreign Ownership, Control, or Influence (FOCI)2023-12-0505 December 2023 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-230039, Submittal of Update Foreign Ownership, Control or Influence (FOCI)2023-07-11011 July 2023 Submittal of Update Foreign Ownership, Control or Influence (FOCI) NOC-AE-220039, Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 252023-02-0606 February 2023 Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 25 NOC-AE-220038, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2022-06-23023 June 2022 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask NOC-AE-210038, Submittal of Operations Quality Assurance Plan Changes QA-089, QA-091, and Revision 252022-01-0404 January 2022 Submittal of Operations Quality Assurance Plan Changes QA-089, QA-091, and Revision 25 NOC-AE-21003858, 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes2021-12-0606 December 2021 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes NOC-AE-21003853, Revised Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material2021-12-0303 December 2021 Revised Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material NOC-AE-21003848, Unit 1 Cycle 24 Core Operating Limits Report2021-11-18018 November 2021 Unit 1 Cycle 24 Core Operating Limits Report NOC-AE-21003846, Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material2021-11-0404 November 2021 Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material NOC-AE-21003842, 10 CFR 50.59 Summary Report2021-09-23023 September 2021 10 CFR 50.59 Summary Report NOC-AE-21003841, Request for Relief from ASME Section Xl Code Requirements for Weld Examinations (Relief Request RR-ENG-3-25)2021-09-23023 September 2021 Request for Relief from ASME Section Xl Code Requirements for Weld Examinations (Relief Request RR-ENG-3-25) NOC-AE-21003832, Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-09-0909 September 2021 Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-21003812, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-08-10010 August 2021 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-21003825, Update of Foreign Ownership, Control, or Influence Information (FOCI)2021-08-0505 August 2021 Update of Foreign Ownership, Control, or Influence Information (FOCI) NOC-AE-21003824, Update Foreign Ownership, Control, or Influence (FOCI)2021-07-29029 July 2021 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-21003823, Update Foreign Ownership Control or Influence (FOCI)2021-07-28028 July 2021 Update Foreign Ownership Control or Influence (FOCI) NOC-AE-21003820, Nuclear Insurance Protection2021-07-20020 July 2021 Nuclear Insurance Protection NOC-AE-21003819, Inservice Inspection Summary Report - 2RE212021-07-15015 July 2021 Inservice Inspection Summary Report - 2RE21 NOC-AE-21003816, Commitment Change Summary Report2021-06-30030 June 2021 Commitment Change Summary Report NOC-AE-21003814, Technical Specification Bases Control Program2021-06-24024 June 2021 Technical Specification Bases Control Program NOC-AE-21003810, Update Foreign Ownership, Control, or Influence (FOCI)- CPS Energy2021-06-17017 June 2021 Update Foreign Ownership, Control, or Influence (FOCI)- CPS Energy NOC-AE-21003811, Update Foreign Ownership, Control, or Influence (FOCI)- Nrg Energy2021-06-17017 June 2021 Update Foreign Ownership, Control, or Influence (FOCI)- Nrg Energy NOC-AE-21003806, Inservice Inspection Program Plan and Inservice Testing Program Snubber Inservice Test Plan for the Fourth Ten-Year Interval2021-05-20020 May 2021 Inservice Inspection Program Plan and Inservice Testing Program Snubber Inservice Test Plan for the Fourth Ten-Year Interval NOC-AE-21003801, Annual Dose Report for 20202021-04-26026 April 2021 Annual Dose Report for 2020 NOC-AE-21003802, 2020 South Texas Project Electric Generating Station Annual Environmental Operating Report2021-04-26026 April 2021 2020 South Texas Project Electric Generating Station Annual Environmental Operating Report NOC-AE-21003804, Operator Licensing Examination Schedule2021-04-21021 April 2021 Operator Licensing Examination Schedule NOC-AE-21003800, Radioactive Effluent Release Report2021-04-19019 April 2021 Radioactive Effluent Release Report NOC-AE-21003799, Changes to South Texas Project Electric Generating Station (STPEGS) Emergency Plan2021-04-15015 April 2021 Changes to South Texas Project Electric Generating Station (STPEGS) Emergency Plan NOC-AE-21003795, Cycle 22 Core Operating Limits Report2021-04-15015 April 2021 Cycle 22 Core Operating Limits Report NOC-AE-21003796, Update Foreign Ownership, Control, or Influence (FOCI)2021-04-15015 April 2021 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-21003790, Response to Apparent Violations in NRC Inspection Report 05000498/2020401 and 05000499/2020401: (EA-20-122) (Letter)2021-03-31031 March 2021 Response to Apparent Violations in NRC Inspection Report 05000498/2020401 and 05000499/2020401: (EA-20-122) (Letter) NOC-AE-21003791, Financial Assurance for Decommissioning - 2021 Update2021-03-31031 March 2021 Financial Assurance for Decommissioning - 2021 Update NOC-AE-210037, STP Fire Hazards Analysis Report, Amendment 26 (Redacted)2021-03-30030 March 2021 STP Fire Hazards Analysis Report, Amendment 26 (Redacted) NOC-AE-21003792, STP Fire Hazards Analysis Report, Amendment 26 (Redacted)2021-03-30030 March 2021 STP Fire Hazards Analysis Report, Amendment 26 (Redacted) NOC-AE-200037, License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications2021-03-11011 March 2021 License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications NOC-AE-21003784, Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing2021-03-0808 March 2021 Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing NOC-AE-21003786, Annual Fitness for Duty Performance Report for 20202021-03-0101 March 2021 Annual Fitness for Duty Performance Report for 2020 NOC-AE-21003785, Evidence of Financial Protection2021-02-23023 February 2021 Evidence of Financial Protection NOC-AE-21003781, Notice Regarding Withdrawal of Funds from Nuclear Decommissioning Trust Subaccounts2021-01-27027 January 2021 Notice Regarding Withdrawal of Funds from Nuclear Decommissioning Trust Subaccounts NOC-AE-21003780, Submittal of Update Foreign Ownership, Control, or Influence (FOCI)2021-01-0707 January 2021 Submittal of Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-20003778, Changes to South Texas Project Electric Generating Station Emergency Plan2020-12-17017 December 2020 Changes to South Texas Project Electric Generating Station Emergency Plan NOC-AE-20003777, STPNOC Concerns Regarding the Proposed Change to the Evaluated Force-on-Force Inspection Guidance During the COVID-19 Public Health Emergency2020-12-10010 December 2020 STPNOC Concerns Regarding the Proposed Change to the Evaluated Force-on-Force Inspection Guidance During the COVID-19 Public Health Emergency NOC-AE-20003766, Supplement to Change Implementation Date for License Amendment Request to Revise the STPEGS Emergency Plan2020-12-0202 December 2020 Supplement to Change Implementation Date for License Amendment Request to Revise the STPEGS Emergency Plan NOC-AE-20003767, Request for a One-Time Exemption from 10 CFR 73, Appendix 8, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-16016 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix 8, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic NOC-AE-20003765, Inservice Testing Program Description for the Fourth Ten-Year Interval2020-10-28028 October 2020 Inservice Testing Program Description for the Fourth Ten-Year Interval NOC-AE-20003764, 1 RE22 Inspection Summary Report for Steam Generator Tubing2020-10-0707 October 2020 1 RE22 Inspection Summary Report for Steam Generator Tubing NOC-AE-20003762, Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-374, Revision 0, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil Using the Consolidated Line Item Improvemen2020-09-22022 September 2020 Supplement to License Amendment Request to Revise Technical Specifications to Adopt TSTF-374, Revision 0, Revision to TS 5.5.13 and Associated TS Bases for Diesel Fuel Oil Using the Consolidated Line Item Improvemen NOC-AE-20003761, Supplement to Exemption Request from 10 CFR 50 Appendix E Due to COVID-19 Pandemic2020-09-10010 September 2020 Supplement to Exemption Request from 10 CFR 50 Appendix E Due to COVID-19 Pandemic 2024-10-16
[Table view] |
Text
Nuclear Operating Company rrnh Tew Pm/d Ekd&c Gcnmt~n,;Ss-t&on PO. & 289 Mpdswr. r 77483 D March 04, 2004 NOC-AE-04001692 File: G25 STI: 31708043 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket Nos. STN 50-498, STN 50-499 Clarification of Component Unavailability Considerations in PRA Applications
Reference:
- 1) SECY-97-229, "Graded Quality Assurance/Probabilistic Risk Assessment Implementation Plan for the South Texas Project Electric Generating Station," dated October 6, 1997
- 2) Letter, J. A. Zwolinski to W. T. Cottle, "South Texas Project Units 1 and 2 - Safety Evaluation on Exemption Requests from Special Treatment Requirements of 10CFR Parts 21, 50, and 100 (TAC Nos. MA6057 and MA6058)," dated August 3, 2001 South Texas Project (STP), as the industry's proto-type pilot for the 10CFR 50.69 effort, is implementing a methodology change when considering component unavailability in planned maintenance sensitivity studies. This methodology change does not alter the language in the Operations Quality Assurance Program (OQAP) or in UFSAR Section 13.7, nor do we believe the change impacts the intent of the basis for approval of the exemption from certain special treatment requirements. However, STP wishes to keep the NRC staff inforned of lessons learned which add efficiency and robustness into the categorization process. Therefore, STP is not seeking NRC approval of this change, but is providing the change to the NRC for information.
The NRC approved the basis for revisions to the STP Operations Quality Assurance Program utilizing a risk-informed approach as stated in the Reference 1 safety evaluation report. In addition, STP was granted an exemption from certain special treatment requirements of 10CFR Parts 21, 50, and 100 as stated in Reference 2. The STP UFSAR contains commitments with respect to the exemption as well as allowances for making changes to UFSAR Section 13.7 without prior NRC approval.
ObeQualiy and UcAsinVUAP/ c200_NOC-AE04001692 OQAComponent UnavaAbiliry Leg'u
NOC-AE-04001 692 Page 2 of 4 During recent data updates to the STP Probabilistic Risk Assessment (PRA) Model, STP identified that the methodology to address component unavailability in the PRA sensitivity study for planned maintenance is extremely conservative. While the planned maintenance sensitivity study is included as a part of the basis for the Graded Quality Assurance (GQA) Safety Evaluation Report (SER), the detail of how this sensitivity study is to be accomplished is not stated in the basis for the GQA SER or in the approved exemption from certain special treatment requirements. When the GQA SER was issued, the planned maintenance sensitivity study assumed the affected trains of components are unavailable for a full calendar year. The GQA SER specifically states in Section 3.2.2:
The licensee performed a variety of sensitivity studies to provide additional assurance that important SSCs are not inappropriately categorized because of PRA modeling limitations and uncertainties. Toward this end, the licensee's PSA Risk Ranking procedure (Reference 14) includes the following bounding values and analyses:
equipment planned to be out of service during each of the plant's scheduled maintenance states is set to unavailable In addition, UFSAR Section 13.7 addresses aggregate sensitivity studies, but does not specify a level of detail describing planned maintenance sensitivity studies.
To date, the STP implementing procedures have conservatively assumed for each planned maintenance sensitivity study that the affected trains/components are unavailable for a full year. This assumption is not considered realistic, results in unnecessary conservatisms, and does not provide the needed insight to determine component importance. Since the GQA SER basis does not specify that affected trains/components in planned maintenance sensitivity studies must be considered unavailable for a full year, STP has modified its approach to consider affected trains/components as being unavailable for a more reasonable, yet bounding, period of time when performing planned maintenance sensitivity studies.
The STP planned maintenance sensitivity studies consist of approximately 16 different evaluations (different component out-of-service combinations for Trains A, B, and C; Train D Auxiliary Feedwater and Steam Generator PORV out of service; and three different 'no maintenance' states) which are performed one maintenance state at a time.
Previously, each combination of components was assumed to be out-of-service for a full calendar year when performing the sensitivity studies. STP is now implementing a methodology which utilizes a more realistic, bounding analysis similar to the "Increase the Failure Rate of all Modeled LSS Components by a Factor of 10" sensitivity study which the NRC approved with the STP exemption from certain special treatment requirements (Reference 2). Specifically, when performing planned maintenance sensitivity studies, the probability of being in a given maintenance state (i.e., components set to "unavailable'") is increased by a factor of 10 for each planned maintenance state in the PRA. The duration of planned maintenance states is based on actual historical unavailability as tracked by STP.
NOC-AE-04001692 Page 3 of 4 This methodology change does not impact the basis for NRC approval of the risk-informed Operations Quality Assurance Program or the exemption from certain special treatment requirements. STP, as the industry's proto-type pilot for 10CFR 50.69 activities, is communicating this change to keep the NRC staff informed of lessons learned which add efficiency and robustness into the categorization process.
If there are any questions regarding this change, please contact me at (361) 972-7136.
Scott M. Head Manager, Licensing
NOC-AE-04001688 Page 4 of 4 cc:
(paper copy) (electronic copy)
Bruce S. Mallett A. H. Gutterman, Esquire Regional Administrator, Region IV Morgan, Lewis & Bockius LLP U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 L. D. Blaylock Arlington, Texas 76011-8064 City Public Service U. S. Nuclear Regulatory Commission David H. Jaffe Attention: Document Control Desk U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike R. L. Balcom Rockville,MD 20852 Texas Genco, LP Richard A. Ratliff A. Ramirez Bureau of Radiation Control City of Austin Texas Department of Health 1100 West 49th Street C. A. Johnson Austin, TX 78756-3189 AEP Texas Central Company Jeffrey Cruz Jon C. Wood U. S. Nuclear Regulatory Commission Matthews & Branscomb P. O. Box 289, Mail Code: MNM16 Wadsworth, TX 77483 C. M. Canady City of Austin Electric Utility Department 721 Barton Springs Road Austin, TX 78704