ML040650783
| ML040650783 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 03/04/2004 |
| From: | Lanksbury R Division of Reactor Safety III |
| To: | Crane C Exelon Generation Co, Exelon Nuclear |
| References | |
| Download: ML040650783 (4) | |
Text
March 4, 2004 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
DRESDEN NUCLEAR POWER STATION CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATIONS
Dear Mr. Crane:
In a letter dated September 26, 2003, your staff responded to NRC Regulatory Issue Summary (RIS) 2003-14, "Preparation and Scheduling of Operator Licensing Examinations," for all Exelon Nuclear Stations. This letter responds to the request for initial license examinations at Dresden Nuclear Power Station, Units 1 and 2.
Initial license examinations were requested during the week of August 16, 2004, during the week of August 22, 2005, and during the week of August 21, 2006. The initial license examination scheduled for August 16, 2004, has been scheduled and a chief examiner assigned to the examination. Because of a heavy work load, the examination requested for August 2005 was rescheduled to the week of September 19, 2005, per a telephone conversation between Mr. M. Carey, Dresden Station Operations Training Manager, and Mr. D. McNeil of my staff. That examination has been scheduled and a chief examiner assigned to that examination. The examination requested for August 2006 will be scheduled as we approach that date.
On-site validation of the examinations will occur at Dresden Nuclear Power Station approximately 3 weeks before the examination administration date. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examinations at a mutually acceptable date.
As indicated in your RIS response letter, your staff will develop the examination. Your letter also indicated that you are training less than 10 candidates for each of the examinations.
Please inform us if the number of candidates rises above 10 as this will impact the examination schedule.
A supplementary letter will be sent to the training department approximately 120 days prior to the initial examination informing them of the chief examiners name. The letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination dates, and reconfirm the number of candidates you have in the training program. If you have any questions concerning this information, please contact Mr. C. Phillips of my staff at 630-829-9739.
C. Crane In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Roger D. Lanksbury, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 cc:
Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager Regulatory Assurance Manager - Dresden Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing M. Aguilar, Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer Chairman, Illinois Commerce Commission Training Department
C. Crane In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Roger D. Lanksbury, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25 cc:
Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager Regulatory Assurance Manager - Dresden Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing M. Aguilar, Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer Chairman, Illinois Commerce Commission Training Department DOCUMENT NAME: G:\\DRS\\ML040650783.wpd To receive a copy of this document, indicate in the box "C" = Copy w/o attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII:DRS RIII:DRS RIII:DRS NAME MABies:sd CPhillips RDLanksbury DATE 02/24/04 02/24/04 03/04/04 OFFICIAL RECORD COPY
C. Crane ADAMS Distribution:
AJM DFT MXB RidsNrrDipmIipb GEG HBC DRC1 DRPIII DRSIII PLB1 JRK1 DCT M. A. Bies (concurrence copy)