Re Confirmation of Initial Operator License Examinations
ML040650724
Person / Time
Site: Byron  Constellation icon.png
Issue date: 03/04/2004
From: Lanksbury R
Division of Reactor Safety III
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
Download: ML040650724 (4)


Text

March 4, 2004 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

BYRON STATION CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATIONS

Dear Mr. Crane:

In a letter dated September 26, 2003, your staff responded to NRC Regulatory Issue Summary (RIS) 2003-14, "Preparation and Scheduling of Operator Licensing Examinations," for all Exelon Nuclear Stations. This letter responds to the request for initial license examinations at Byron Station, Units 1 and 2.

Initial license examinations were requested during the week of October 31, 2005, and during the week of November 5, 2007. The examination requested for October 31, 2005, has been scheduled and a chief examiner assigned to that examination. The examination requested for November 2007 will be scheduled as we approach that date.

On-site validation of the examinations will occur at Byron Station approximately 3 weeks before the examination administration date. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examinations at a mutually acceptable date.

As indicated in your RIS response letter, your staff will develop the examinations. Your letter also indicated that you are training 18 candidates for each of the examinations which requires two weeks to complete the examination. Please inform us if the number of candidates decreases below 10 as this will impact the examination schedule.

A supplementary letter will be sent to the training department approximately 120 days prior to the initial examination informing them of the chief examiners name. The letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination dates, and reconfirm the number of candidates you have in the training program. If you have any questions concerning this information, please contact Mr. H. Peterson of my staff at 630-829-9707.

C. Crane In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Roger D. Lanksbury, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66 cc:

Site Vice President - Byron Byron Station Plant Manager Regulatory Assurance Manager - Byron Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear Document Control Desk - Licensing M. Aguilar, Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer State Liaison Officer, State of Wisconsin Chairman, Illinois Commerce Commission Training Manager

C. Crane In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Roger D. Lanksbury, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66 cc:

Site Vice President - Byron Byron Station Plant Manager Regulatory Assurance Manager - Byron Chief Operating Officer Senior Vice President - Nuclear Services Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing Manager Licensing - Braidwood and Byron Senior Counsel, Nuclear Document Control Desk - Licensing M. Aguilar, Assistant Attorney General Illinois Department of Nuclear Safety State Liaison Officer State Liaison Officer, State of Wisconsin Chairman, Illinois Commerce Commission Training Manager DOCUMENT NAME: G:\\DRS\\ML040650724.wpd To receive a copy of this document, indicate in the box "C" = Copy w/o attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII:DRS RIII:DRS RIII:DRS NAME MABies:sd HPeterson RDLanksbury DATE 2/24/04 11/24/03 03/04/04 OFFICIAL RECORD COPY

C. Crane ADAMS Distribution:

AJM DFT GFD DCT RidsNrrDipmIipb GEG HBC RAS DRPIII DRSIII PLB1 JRK1 M. A. Bies (concurrence copy)