ML040631087

From kanterella
Jump to navigation Jump to search
Annual Assessment Letter - Cooper Nuclear Station (NRC Report 05000298-04-001)
ML040631087
Person / Time
Site: Cooper Entergy icon.png
Issue date: 03/03/2004
From: Mallett B
NRC Region 4
To: Edington R
Nebraska Public Power District (NPPD)
References
IR-04-001
Download: ML040631087 (10)


See also: IR 05000298/2004001

Text

March 3, 2004

Randall K. Edington, Vice

President-Nuclear and CNO

Nebraska Public Power District

P.O. Box 98

Brownville, NE 68321

SUBJECT:

ANNUAL ASSESSMENT LETTER - COOPER NUCLEAR STATION

(NRC REPORT 05000298/2004001)

Dear Mr. Edington:

On January 28, 2004, the NRC staff completed its end-of-cycle plant performance assessment

of the Cooper Nuclear Station. The end-of-cycle review for the Cooper Nuclear Station involved

the participation of all technical divisions in evaluating performance indicators for the most

recent quarter and inspection results for the period from January 1 through December 31, 2003.

The purpose of this letter is to inform you of our assessment of your safety performance during

this period and our plans for future inspections at your facility so that you will have an

opportunity to prepare for these inspections and to inform us of any planned inspections that

may conflict with your plant activities.

Overall, the Cooper Nuclear Station operated in a manner that preserved public health and

safety. While the Cooper Nuclear Station met all cornerstone objectives, plant performance

remained within the Multiple/Repetitive Degraded Cornerstone Column of the Action Matrix as

discussed further below. The Cooper Nuclear Station entered the Multiple/Repetitive Degraded

Cornerstone Column of the NRCs Action Matrix on April 1, 2002. The White findings that

contributed to the initial placement in the Repetitive Degraded Cornerstone were identified

during the 2000 and 2001 assessment periods and were described in the annual assessment

letters dated May 29, 2001, and March 4, 2002.

Upon entry into the Multiple/Repetitive Degraded Cornerstone Column of the Action Matrix, and

with oversight by the NRC, you developed a plan to improve performance at the Cooper

Nuclear Station. On June 10, 2002, you submitted Revision 1 of The Strategic Improvement

Plan to the NRC. On August 22, 2002, we completed a supplemental inspection using

Inspection Procedure 95003, Inspection for Repetitive Degraded Cornerstones, Multiple

Degraded Cornerstones, Multiple Yellow Inputs, or One Red Input." Following completion of

the NRC supplemental inspection, you revised the improvement plan and submitted Revision 2

of the plan to the NRC on November 25, 2002. On January 30, 2003, we issued a Confirmatory

Action Letter to Nebraska Public Power District (NPPD). The purpose of the Confirmatory

Action Letter was to confirm the commitments made by NPPD regarding completion of those

actions in the improvement plan developed to address regulatory performance issues. Your

actions confirmed in the Confirmatory Action Letter addressed long-standing performance

issues in the areas of emergency preparedness, human performance, material condition and

Nebraska Public Power District

-2-

equipment reliability, plant modification and configuration control, corrective action program,

and engineering programs. In addition to baseline inspections, the NRC conducted periodic

inspections to verify completion of these actions and the effectiveness of these actions in

addressing the specific performance issues. Four of these inspections were completed in

2003. On the basis of inspection activities conducted in 2003, we have concluded that you

have corrected the specific performance deficiencies associated with the White inspection

findings in the Emergency Preparedness Cornerstone and that performance has improved in

this cornerstone. This has been demonstrated during the performance of a graded emergency

preparedness exercise and confirmed during NRC baseline inspection and quarterly

Confirmatory Action Letter inspections. In addition, the NPPD completed a comprehensive

assessment of the Cooper Nuclear Station emergency preparedness program in accordance

with the Strategic Improvement Plan and committed to in the Confirmatory Action Letter. This

assessment, which was also reviewed by the NRC staff, found that performance had improved

in this area.

With respect to the other five regulatory issues discussed in the Confirmatory Action Letter,

NPPD is scheduled to complete the applicable improvement plan actions by March 31, 2004.

Based on the results of inspections of your progress in completing the actions of the

Confirmatory Action Letter, the NRC has found that NPPD is completing the actions on

schedule. We have assessed that you have made some progress in addressing performance

issues in these five areas, but actions taken in several areas have not yet resulted in sustained

improved performance. These areas include human performance, corrective action program,

material condition, and equipment reliability. Following NPPDs completion of the actions of the

Confirmatory Action Letter, the NRC will conduct a comprehensive assessment of the

effectiveness of these actions in addressing the performance issues. Accordingly, Cooper

Nuclear Station will remain in the Multiple/Repetitive Degraded Cornerstone Column of the

Action Matrix until the satisfactory completion of the actions listed in this Confirmatory Action

Letter and you have demonstrated sustained improvements in plant performance.

During the most recent quarter of the inspection cycle, the NRC staff identified that the Cooper

Nuclear Station crossed the threshold from Green to White for the Unplanned Scrams per

7000 Critical Hours performance indicator. Therefore, we plan to conduct a supplemental

inspection in accordance with NRC Inspection Procedure 95001, Inspection for One or Two

White Inputs in a Strategic Performance Area, to review the actions taken in response to this

White performance indicator. The purpose of this supplemental inspection will be to provide

assurance that the root and contributing causes for the White performance indicator are

understood, to provide assurance that the extent of condition and extent of cause are identified,

and to provide assurance that the corrective actions are sufficient to address the root and

contributing causes and prevent their recurrence.

In addition, NRC Inspection Report 05000298/2004009, dated February 11, 2004, documented

a preliminary White finding associated with your failure to demonstrate satisfactory licensed

operator requalification program performance as described in NUREG-1021, "Operator

Licensing Examination Standards for Power Reactors," Revision 8, Supplement 1, Examination

Standard 601, Section E.3.a(1). Examination Standard 601 E.3.a(1) specifies, in part, that, for

a requalification program to maintain satisfactory performance, 75 percent or greater of the

participants must pass all portions of the biennial examinations. Failures during the biennial

Nebraska Public Power District

-3-

cycle included a 36 percent failure rate on the biennial written examination. The NRC will

review your response to this preliminary White finding before making a final significance

determination.

In our annual assessment letters dated March 4, 2002, and March 4, 2003, we advised you of a

substantive crosscutting issue in the area of Human Performance. In the area of Human

Performance, our inspections confirmed that Strategic Improvement Plan action steps

implemented during the third Quarter of 2003 have provided for some improvement in human

performance as evidenced by an improving trend in your Human Performance Error Rate

performance indicator. Specific actions that have had a positive impact included: (1) increased

use of management observations in the field; (2) maintenance department implementation of

job-site specific reviews of human performance tools; and (3) a monthly Management

Performance Review Meeting which focuses site upper management on progress in improving

site-wide human performance. We note that you are in the process of implementing additional

actions to improve human performance. These activities include: (1) a human performance

mock-up trainer in which site-wide staff training was initiated in November 2003; (2) a paired

observation program to establish common standards and alignment on the observation and

oversight of field work; (3) formal performance management skills training; (4) meetings for

first-line supervisors focusing on human performance improvements; and (5) development of

departmental human performance improvement plans. Despite these improvements, we

identified multiple instances (at the Green finding level) throughout the assessment cycle in the

Initiating Events, Mitigating Systems, Barrier Integrity, and Occupational Radiation Safety

Cornerstones where the contributor to the performance problems was human performance.

Examples include a number of instances of operators and workers failing to follow procedures.

In one example that occurred early in the assessment cycle, plant operators failed to reduce

power to less than 25 percent within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> of a partial loss of feedwater heating.

Also, in our annual assessment letters dated March 4, 2002, and March 4, 2003, we advised

you of a substantive crosscutting issue in the area of Problem Identification and Resolution. In

that area, our inspections have generally indicated that your staff adequately identified issues.

We also noted that you have implemented a number of Strategic Improvement Plan actions

with the goal of improving the implementation effectiveness of your corrective action,

self-assessment, and operating experience review programs. Despite these improvements, we

identified multiple instances of inadequate corrective actions (at the Green finding level)

throughout the assessment period in the Initiating Events, Mitigating Systems, and Barrier

Integrity Cornerstones. Examples include two preventable fires and a repetitive problem with

the clogging of an emergency diesel generator fuel oil transfer system filter. Causal factors

associated with these and other corrective action findings primarily involved failures to identify

the extent of condition, symptom-based problem solving, inadequate treatment of plant-specific

and industry operating experience, and failures to adequately implement identified corrective

actions. These are the very types of problems that your improvement initiatives are intended to

address. Your ongoing actions to address these substantive crosscutting issues have been

discussed during several public meetings, including a meeting conducted on March 1, 2004.

The NRC will continue to review the implementation of these improvement activities and any

changes resulting from these activities. The reviews will be performed during the scheduled

quarterly inspections of the actions described in the Confirmatory Action Letter and as part of

the baseline inspection program.

Nebraska Public Power District

-4-

In accordance with IMC 0305, Operating Reactor Assessment Program, your plant will be

discussed at the upcoming Agency Action Review Meeting. We will notify you via separate

correspondence if any agency actions change as an outcome of the meeting.

As you are aware, the NRC has issued several Orders and threat advisories to enhance

security capabilities and improve guard force readiness since the terrorist attacks on

September 11, 2001. We have conducted inspections to review your implementation of these

requirements and have monitored your actions in response to changing threat conditions. For

calendar year 2004, we plan to continue inspections of Order implementation combined with

newly developed portions of the security baseline inspection program. This letter advises you

of our planned inspection effort resulting from the Cooper Nuclear Stations end-of-cycle review.

The enclosed inspection plan details the inspections scheduled through September 30, 2005.

In addition to the baseline inspections, quarterly inspections to verify the actions taken with

respect to the improvement plan and the Confirmatory Action Letter will be conducted as

shown. The inspection plan is provided to minimize the resource impact on your staff and to

allow for scheduling conflicts and personnel availability to be resolved in advance of inspector

arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous

nature. The inspections in the last 12 months of the inspection plan are tentative and may be

revised at the midcycle review meeting.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document

system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

If circumstances arise which cause us to change this inspection plan, we will contact you to

discuss the change as soon as possible. Please contact Mr. Kriss Kennedy at 817/860-8144

with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Bruce S. Mallett

Regional Administrator

Docket: 50-298

License: DPR-46

Enclosure:

Cooper Nuclear Station Inspection/Activity Plan

Nebraska Public Power District

-5-

cc w/enclosure:

Clay C. Warren, Vice President-Nuclear

Nebraska Public Power District

P.O. Box 98

Brownville, NE 68321

John R. McPhail, General Counsel

Nebraska Public Power District

P.O. Box 499

Columbus, NE 68602-0499

P. V. Fleming, Licensing and

Regulatory Affairs Manager

Nebraska Public Power District

P.O. Box 98

Brownville, NE 68321

Michael J. Linder, Director

Nebraska Department of

Environmental Quality

P.O. Box 98922

Lincoln, NE 68509-8922

Chairman

Nemaha County Board of Commissioners

Nemaha County Courthouse

1824 N Street

Auburn, NE 68305

Sue Semerena, Section Administrator

Nebraska Health and Human Services System

Division of Public Health Assurance

Consumer Services Section

301 Centennial Mall, South

P.O. Box 95007

Lincoln, NE 68509-5007

Ronald A. Kucera, Deputy Director

for Public Policy

Department of Natural Resources

P.O. Box 176

Jefferson City, MO 65101

Jerry Uhlmann, Director

State Emergency Management Agency

P.O. Box 116

Jefferson City, MO 65102-0116

Nebraska Public Power District

-6-

Chief, Radiation and Asbestos

Control Section

Kansas Department of Health

and Environment

Bureau of Air and Radiation

1000 SW Jackson, Suite 310

Topeka, KS 66612-1366

Daniel K. McGhee

Bureau of Radiological Health

Iowa Department of Public Health

401 SW 7th Street, Suite D

Des Moines, IA 50309

William J. Fehrman, President

and Chief Executive Officer

Nebraska Public Power District

1414 15th Street

Columbus, NE 68601

Marlin Logan

Presiding Commissioner

Atchison County

P.O. Box 280

Rock Port, MO 64482

Dennis Martin, Sheriff

Atchison County Sheriff's Office

511 West Clay

Rock Port, MO 64482

Brent Lottman, Sheriff

1805 N Street

Auburn, NE 68305

Dick Moody, Chairman

Nemaha County Board of Commissioners

Nemaha County Courthouse

1824 N Street

Auburn, NE 68305

Dick Hainje, Regional Director

Federal Emergency Management Agency

Region VII

2323 Grand Blvd., Suite 900

Kansas City, MO 64108-2670

Nebraska Public Power District

-7-

Robert Leopold, State Liaison Officer

Nebraska Health and Human Services

Department of Regulation and

Licensure Assurance

301 Centennial Mall, South

P.O. Box 95007

Lincoln, NE 68509-5007

Al Berndt, Assistant Director

Emergency Management Agency

1300 Military Road

Lincoln, NE 68508

Scott Clardy, Director

Section for Environmental Public Health

P.O. Box 570

Jefferson City, MO 65102-0570

Institute of Nuclear Power Operations (INPO)

700 Galleria Parkway SE, Suite 100

Atlanta, GA 30339

Nebraska Public Power District

-8-

Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

Senior Resident Inspector (SCS)

Branch Chief, DRP/C (KMK)

Senior Project Engineer, DRP/C (WCW)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (NBH)

Dan Merzke, Pilot Plant Program (DXM2)

RidsNrrDipmLipb

V. Dricks, PAO (VLD)

W. A. Maier, RSLO (WAM)

C. J. Gordon (CJG)

DRS Branch Chiefs (LJS, TWP, ATG, CSM)

W. D. Travers, EDO (WDT)

S. J. Collins, DEDO (SJC1)

S. A. Richards, Chief, NRR/DIPM/IIPB (SAR)

R. K. Frahm, PPR Program Manager, NRR/DIPM/IIPB (RKF)

J. W. Craig, Associate Dir. for Inspection and Programs (JWC1)

B. W. Sheron, Associate Dir. for Project Licensing and Technical Analysis (BWS)

T. A. Bergman, Chief, Regional Operations Staff, OEDO (TAB)

H. N. Berkow, NRR Project Director (HNB)

R. A. Gramm, Chief, Section 1, NRR/DLPM (RAG)

M. Honcharik, NRR Project Manager (MCH3)

ADAMS:  Yes

G No Initials: __wcw___

 Publicly Available G Non-Publicly Available

G Sensitive

 Non-Sensitive

S:\\DRP\\DRPDIR\\EOC for 03\\Assessment Letters\\CNS.wpd

RIV:C:DRP/C

D:DRS

D:DRP

DRA

RA

KMKennedy;df

DDChamberlain

ATHowell

TPGwynn

BSMallett

WCWalker for

/RA/

/RA/

/RA/

/RA/

2/19/04

2/26/04

3/2/04

3/2/04

3/3/04

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

Cooper

Inspection / Activity Plan

03/01/2004 - 10/01/2005

Inspection

Type

Inspection Activity

Planned Dates

Start End

No. of Staff

on Site

Title

Unit

Number

Page 1 of 2

03/01/2004

15:32:50

Report 22

1

PEB-12B

- MAINTENANCE EFFECTIVENESS

Baseline Inspections

03/15/2004

03/19/2004

Maintenance Effectiveness

IP 7111112B

1

5

PEB-05T

- TRIENNIAL FIRE PROTECTION

Baseline Inspections

04/05/2004

04/09/2004

Fire Protection

IP 7111105T

1

Baseline Inspections

04/19/2004

04/23/2004

Fire Protection

IP 7111105T

1

4

CNS CAL

- CAL QUARTERLY INSPECTION

Other Routine

03/22/2004

03/26/2004

Identification and Resolution of Problems

IP 71152

1

2

EB-17

- PERM. PLANT MODIFICATIONS

Baseline Inspections

03/29/2004

04/02/2004

Permanent Plant Modifications

IP 7111117B

1

2

PSB-S1

- AA-AC-FFD-PI

Baseline Inspections

04/05/2004

04/09/2004

Access Authorization

IP 7113001

1

Baseline Inspections

04/05/2004

04/09/2004

Access Control

IP 7113002

1

Baseline Inspections

04/05/2004

04/09/2004

Fitness For Duty Program

IP 7113008

1

Baseline Inspections

04/05/2004

04/09/2004

Performance Indicator Verification

IP 71151

1

4

CNS CAL

- CAL QUARTERLY INSPECTION

Other Routine

06/21/2004

06/26/2004

Identification and Resolution of Problems

IP 71152

1

1

PEB-07B

- HX & HEAT SINK PERFORMANCE TESTING

Baseline Inspections

07/19/2004

07/23/2004

Heat Sink Performance

IP 7111107B

1

1

ALARA1

- ALARA PLANNING AND CONTROLS

Baseline Inspections

09/13/2004

09/17/2004

ALARA Planning and Controls

IP 7112102

1

3

OB-EP2

- EP EXERCISE

Baseline Inspections

09/20/2004

09/24/2004

Exercise Evaluation

IP 7111401

1

Baseline Inspections

09/20/2004

09/24/2004

Emergency Action Level and Emergency Plan Changes

IP 7111404

1

Baseline Inspections

09/20/2004

09/24/2004

Performance Indicator Verification

IP 71151

1

4

OB-INIT

- INITIAL EXAM

Not Applicable

05/09/2005

05/14/2005

COOPER (06/05) - INITIAL EXAM

X02288

1

Not Applicable

06/06/2005

06/17/2005

COOPER (06/05) - INITIAL EXAM

X02288

1

1

ACCESSPI

- ACRSA/PIV

Baseline Inspections

10/25/2004

10/29/2004

Access Control to Radiologically Significant Areas

IP 7112101

1

1

EB08G

- ISI

Baseline Inspections

01/24/2005

01/28/2005

Inservice Inspection Activities - BWR

IP 7111108G

1

1

ACRSA

- ACCESS CONTROLS TO RAD SIGNIFICANT AREAS

Baseline Inspections

01/24/2005

01/28/2005

Access Control to Radiologically Significant Areas

IP 7112101

1

1

ALARA2

- ALARA PLANNING AND CONTROLS

Baseline Inspections

04/11/2005

04/15/2005

ALARA Planning and Controls

IP 7112102

1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Cooper

Inspection / Activity Plan

03/01/2004 - 10/01/2005

Inspection

Type

Inspection Activity

Planned Dates

Start End

No. of Staff

on Site

Title

Unit

Number

Page 2 of 2

03/01/2004

15:32:50

Report 22

6

EB21/02

- SSD&PCI/50.59

Baseline Inspections

05/02/2005

05/06/2005

Safety System Design and Performance Capability

IP 7111121

1

Baseline Inspections

05/09/2005

05/13/2005

Safety System Design and Performance Capability

IP 7111121

1

Baseline Inspections

05/16/2005

05/20/2005

Evaluation of Changes, Tests, or Experiments

IP 7111102

1

Baseline Inspections

05/16/2005

05/20/2005

Safety System Design and Performance Capability

IP 7111121

1

1

OB-EP2

- EMERG PREPAREDNESS PROGRAM INSPECTION

Baseline Inspections

05/16/2005

05/20/2005

Alert and Notification System Testing

IP 7111402

1

Baseline Inspections

05/16/2005

05/20/2005

Emergency Response Organization Augmentation Testing

IP 7111403

1

Baseline Inspections

05/16/2005

05/20/2005

Emergency Action Level and Emergency Plan Changes

IP 7111404

1

Baseline Inspections

05/16/2005

05/20/2005

Correction of Emergency Preparedness Weaknesses and Deficiencies

IP 7111405

1

Baseline Inspections

05/16/2005

05/20/2005

Performance Indicator Verification

IP 71151

1

4

RP TEAM

- RADIATION SAFETY TEAM INSPECTION

Baseline Inspections

06/06/2005

06/10/2005

Radiation Monitoring Instrumentation and Protective Equipment

IP 7112103

1

Baseline Inspections

06/06/2005

06/10/2005

Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems

IP 7112201

1

Baseline Inspections

06/06/2005

06/10/2005

Radioactive Material Processing and Transportation

IP 7112202

1

Baseline Inspections

06/06/2005

06/10/2005

Radiological Environmental Monitoring Program

IP 7112203

1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.