Inspection/Activity Plan - Oconee, for 03/01/2004 - 09/30/2005
ML040630407
Person / Time
Site: Oconee  
Issue date: 03/03/2004
From:
NRC/RGN-II
To:
Shared Package
ML040630387 List:
References
IR-04-001
Download: ML040630407 (3)


Text

Oconee Inspection / Activity Plan 03/01/2004 - 09/30/2005 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 3 03/03/2004 09:56:43 Report 22 1

EB2 HEAD

- REACTOR HEAD REPLACEMENT Other Routine 03/15/2004 03/20/2004 Reactor Vessel Head Replacement Inspection IP 71007 2

1 PS-RP

- RP-SGR-RX HEAD ASSESS CONTROLS-ISFIS Other Routine 03/22/2004 03/26/2004 Steam Generator Replacement Inspection IP 50001 2

Other Routine 03/22/2004 03/26/2004 Reactor Vessel Head Replacement Inspection IP 71007 2

Baseline Inspections 03/22/2004 03/26/2004 Access Control to Radiologically Significant Areas IP 7112101 1, 2, 3 1

2515/152

- U-2 2515/152:RPV LOWER HEAD PENETRATION Safety Issues 03/29/2004 04/02/2004 Reactor Pressure Vessel Lower Head Penetration Nozzles (NRC Bulletin 2003-02)

IP 2515/152 2

1 EB2-ISI

- INSERVICE INSPECTION-U2 Baseline Inspections 03/29/2004 04/02/2004 Inservice Inspection Activities - PWR IP 7111108P 2

1 EB2SGRP

- CONTAINMENT WELDING REPAIR Other Routine 05/10/2004 05/15/2004 Steam Generator Replacement Inspection IP 50001 2

1 EB2SGRP

- STEAM GENERATOR REPLACEMENT Other Routine 05/10/2004 05/15/2004 Steam Generator Replacement Inspection IP 50001 2

Other Routine 05/24/2004 05/29/2004 Steam Generator Replacement Inspection IP 50001 2

1 2515/153

- TI2515/153 RX CONTAINMENT SUMP BLOCKAGE Safety Issues 05/24/2004 05/28/2004 Reactor Containment Sump Blockage (NRC Bulletin 2003-01)

IP 2515/153 2, 3 1

EB2SGRP

- CONTAINMENT REPAIR Other Routine 05/24/2004 05/28/2004 Steam Generator Replacement Inspection IP 50001 2

2 OL PREP

- INITIAL EXAM PREP Not Applicable 05/24/2004 05/28/2004 OCONEE/EXAMS AT POWER FACILITIES V23216 1

1 2515/154

- TI 2515/154 - SPENT FUEL MC&A Safety Issues 06/14/2004 06/18/2004 Spent Fuel Material Control and Accounting at Nuclear Power Plants IP 2515/154 1, 2, 3 4

OL EXAM

- INITIAL EXAM Not Applicable 06/14/2004 06/25/2004 OCONEE/EXAMS AT POWER FACILITIES V23216 1

1 EB2-HS

- HEAT SINK Baseline Inspections 06/28/2004 07/02/2004 Heat Sink Performance IP 7111107B 1, 2, 3 2

EB1SSDPC - SSDPC PRE-INSPECTION VISIT Baseline Inspections 07/26/2004 07/30/2004 Safety System Design and Performance Capability IP 7111121 1, 2, 3 4

EB1SSDPC - SAFETY SYS DESIGN & PERF CAPABILITY Baseline Inspections 08/16/2004 08/20/2004 Safety System Design and Performance Capability IP 7111121 1, 2, 3 Baseline Inspections 08/30/2004 09/03/2004 Safety System Design and Performance Capability IP 7111121 1, 2, 3 3

PS-RP

- RP PUBLIC BASELINE Baseline Inspections 09/20/2004 09/24/2004 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2, 3 Baseline Inspections 09/20/2004 09/24/2004 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1, 2, 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Oconee Inspection / Activity Plan 03/01/2004 - 09/30/2005 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 3 03/03/2004 09:56:43 Report 22 3

PS-RP

- RP PUBLIC BASELINE Baseline Inspections 09/20/2004 09/24/2004 Radiological Environmental Monitoring Program IP 7112203 1, 2, 3 Baseline Inspections 09/20/2004 09/24/2004 Performance Indicator Verification IP 71151 1, 2, 3 2

PS-SEC

- SECURITY Baseline Inspections 09/27/2004 10/01/2004 Access Authorization IP 7113001 1, 2, 3 Baseline Inspections 09/27/2004 10/01/2004 Access Control IP 7113002 1, 2, 3 Baseline Inspections 09/27/2004 10/01/2004 Performance Indicator Verification IP 71151 1, 2, 3 1

EB2-ISI

- INSERVICE INSPECTION-U3 Baseline Inspections 10/18/2004 10/22/2004 Inservice Inspection Activities - PWR IP 7111108P 3

1 EB2-SGRP

- STEAM GENERATOR REPLACEMENT Other Routine 11/15/2004 11/19/2004 Steam Generator Replacement Inspection IP 50001 3

Other Routine 12/06/2004 12/10/2004 Steam Generator Replacement Inspection IP 50001 3

Other Routine 12/13/2004 12/17/2004 Steam Generator Replacement Inspection IP 50001 3

1 EB2-SGRP

- CONTAINMENT WELDING REPAIR Other Routine 12/06/2004 12/10/2004 Steam Generator Replacement Inspection IP 50001 3

1 PS-RP

- RADIATION PROTECTION - SGR Other Routine 12/06/2004 12/10/2004 Steam Generator Replacement Inspection IP 50001 3

1 EB2SGRP

- CONTAINMENT REPAIR Other Routine 12/13/2004 12/17/2004 Steam Generator Replacement Inspection IP 50001 3

1 2515/152

- U-3 2515/152: RPV LOWER HEAD PENETRATION Safety Issues 12/15/2004 12/22/2004 Reactor Pressure Vessel Lower Head Penetration Nozzles (NRC Bulletin 2003-02)

IP 2515/152 3

1 EB2-MR

- MAINTENANCE RULE Baseline Inspections 01/10/2005 01/14/2005 Maintenance Effectiveness IP 7111112B 1, 2, 3 3

EB2-MODS

- MODIFICATIONS/10CFR50.59 Baseline Inspections 02/14/2005 02/18/2005 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2, 3 Baseline Inspections 02/14/2005 02/18/2005 Permanent Plant Modifications IP 7111117B 1, 2, 3 2

OL RQ

- REQUAL INSPECTION Baseline Inspections 03/21/2005 03/25/2005 Licensed Operator Requalification Program IP 7111111B 1, 2, 3 1

EB2-ISI

- INSERVICE INSPECTION-U1 Baseline Inspections 04/04/2005 04/08/2005 Inservice Inspection Activities - PWR IP 7111108P 1

4 71152B

- PI&R INSPECTION Baseline Inspections 05/09/2005 05/13/2005 Identification and Resolution of Problems IP 71152B 1, 2, 3 Baseline Inspections 05/23/2005 05/27/2005 Identification and Resolution of Problems IP 71152B 1, 2, 3 4

EB1-TFP

- TFP PRE-INSPECTION VISIT Baseline Inspections 05/16/2005 05/20/2005 Fire Protection IP 7111105T 1, 2, 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Oconee Inspection / Activity Plan 03/01/2004 - 09/30/2005 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 3 of 3 03/03/2004 09:56:43 Report 22 3

OL PREP

- INITIAL EXAM PREP Not Applicable 05/30/2005 06/03/2005 OCONEE/EXAMS AT POWER FACILITIES V23216 1

4 EB1-TFP

- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 06/06/2005 06/10/2005 Fire Protection IP 7111105T 1, 2, 3 Baseline Inspections 06/20/2005 06/24/2005 Fire Protection IP 7111105T 1, 2, 3 3

OL EXAM

- INITIAL EXAM Not Applicable 06/20/2005 07/01/2005 OCONEE/EXAMS AT POWER FACILITIES V23216 1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.