Brown Ferry, Unit 3 Amd No. 246
ML040580279
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 02/24/2004
From:
NRC/NRR/DLPM
To:
References
TAC MC0918
Download: ML040580279 (1)


Text

SLs SLs 2.0 2.0 SAFETY LIMITS (SLs) 2.1 SLs 2.1.1 Reactor Core SLs 2.1.1.1 With the reactor steam dome pressure < 785 psig or core flow

< 10% rated core flow:

THERMAL POWER shall be < 25% RTP.

2.1.1.2 With the reactor steam dome pressure > 785 psig and core flow

> 10% rated core flow:

MCPR shall be 2 1.09 for two recirculation loop operation or > 1.11 I for single loop operation.

2.1.1.3 Reactor vessel water level shall be greater than the top of active irradiated fuel.

2.1.2 Reactor Coolant System Pressure SL Reactor steam dome pressure shall be < 1325 psig.

2.2 SL Violations With any SL violation, the following actions shall be completed within 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />s:

2.2.1 Restore compliance with all SLs; and 2.2.2 Insert all insertable control rods.

BFN-UNIT 3 2.0-1 Amendment No. 216-,234-,246