Summary of Meeting with Carolina Power & Light Company to Discuss Request for Full Implementation of Alternate Source Term at H.B. Robinson Steam Electric Plant, Unit No. 2
ML040560392
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 02/25/2004
From: Chandu Patel
NRC/NRR/DLPM/LPD2
To:
Patel C P, NRR/DLPM, 415-3025
References
TAC MB5105
Download: ML040560392 (7)


Text

February 25, 2004 LICENSEE: Carolina Power & Light Company (Also doing business as Progress Energy)

FACILITIES: H. B. Robinson Steam Electric Plant, Unit No. 2

SUBJECT:

SUMMARY

OF THE OCTOBER 30, 2003, MEETING WITH CAROLINA POWER & LIGHT COMPANY TO DISCUSS REQUEST FOR FULL IMPLEMENTATION OF ALTERNATE SOURCE TERM AT H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 (TAC NO. MB5105)

On October 30, 2003, the U.S. Nuclear Regulatory Commission (NRC) staff conducted a meeting at the NRC Headquarters in Rockville, Maryland, with Carolina Power & Light Company (the licensee). The purpose of this meeting was to discuss the licensees request for full implementation of Alternate Source Term at H. B. Robinson Steam Electric Plant, Unit No. 2 (HBRSEP2). The licensee and the NRC staff discussed technical details of the licensees analysis of the Loss-of-Coolant Accident (LOCA) and Steam Generator Tube Rupture (SGTR) event at HBRSEP2. After some discussion, it was concluded that there were some differences between the NRC staffs and licensees assumptions for evaluating the LOCA event. These differences in assumptions explained the reason why the NRC staffs and licensees calculated radiological consequences for LOCA were different.

During the discussion of the SGTR event analysis, it became clear that there were inconsistencies between the licensees description of the analytical approach and the actual input used for the analysis. Based on these discussions, the licensee agreed to revise its LOCA analysis and to revise the discussion of the SGTR analysis to make it consistent with the actual analysis input. In addition, the NRC staff indicated that there were two other issues that needed additional internal discussion before communicating with the licensee. These two issues are related to the acceptance criteria for the waste gas decay tank failure analysis and steam generator isolation time assumed in the SGTR analysis. The list of attendees is attached. There were no handouts for the meeting.

/RA/

Chandu P. Patel, Project Manager, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-261

Attachment:

Attendance list cc w/attachment: See next page

ML040560396 OFFICE PDII-2/PM PDII-2/LA PDII-2/SC (A)

NAME CPatel EDunnington WBurton DATE 2/23/2004 2/23/2004 2/24/2004 DISTRIBUTION:

SUMMARY

OF THE OCTOBER 30, 2003, MEETING WITH CAROLINA POWER & LIGHT COMPANY TO DISCUSS REQUEST FOR FULL IMPLEMENTATION OF ALTERNATE SOURCE TERM AT H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 Dated:

Distribution:

PUBLIC PDII-2 R/F RidsNrrPMEBrown RidsNrrPMCPatel RidsOgcRp RidsAcrsAcnw RidsNrrDlpm (LMarsh/ELeeds)

RidsNrrDlpmii (EHackett)

RidsNrrDlpmii-2 (WBurton)

RidsNrrLAEDunnington (Hard Copy)

RidsEdoSRosenberg JAlbright By E-mail JHayes RDennig PFredrickson, RII

ATTENDANCE LIST NUCLEAR REGULATORY COMMISSION STAFF MEETING WITH CAROLINA POWER & LIGHT AT NRC HEADQUARTERS OCTOBER 30, 2003 Name Organization Chandu Patel NRC Allen Howe NRC Jack Hayes NRC Chuck Baucom CP&L Ray Crandall CP&L Bill Ziegler CP&L Jack Grant PSEG/Salem Jesus Arias PSEG/Salem Attachment

H. B. Robinson Steam Electric Plant, Unit No. 2 Carolina Power & Light Company cc:

Steven R. Carr Mr. C. T. Baucom Associate General Counsel - Legal Supervisor, Licensing/Regulatory Programs Department H. B. Robinson Steam Electric Plant, Progress Energy Service Company, LLC Unit No. 2 Post Office Box 1551 Carolina Power & Light Company Raleigh, North Carolina 27602-1551 3581 West Entrance Road Hartsville, South Carolina 29550 Ms. Margaret A. Force Assistant Attorney General Ms. Beverly Hall, Section Chief State of North Carolina N.C. Department of Environment Post Office Box 629 and Natural Resources Raleigh, North Carolina 27602 Division of Radiation Protection 3825 Barrett Dr.

U. S. Nuclear Regulatory Commission Raleigh, North Carolina 27609-7721 Resident Inspectors Office H. B. Robinson Steam Electric Plant Mr. Robert P. Gruber 2112 Old Camden Road Executive Director Hartsville, South Carolina 29550 Public Staff - NCUC 4326 Mail Service Center Mr. T. P. Cleary Raleigh, North Carolina 27699-4326 Plant General Manager H. B. Robinson Steam Electric Plant, Mr. Henry H. Porter, Assistant Director Unit No. 2 South Carolina Department of Health Carolina Power & Light Company Bureau of Land & Waste Management 3581 West Entrance Road 2600 Bull Street Hartsville, South Carolina 29550 Columbia, South Carolina 29201 Mr. Chris L. Burton Mr. James W. Holt Director of Site Operations Manager H. B. Robinson Steam Electric Plant, Performance Evaluation and Unit No. 2 Regulatory Affairs PEB 7 Carolina Power & Light Company Progress Energy 3581 West Entrance Road Post Office Box 1551 Hartsville, South Carolina 29550 Raleigh, North Carolina 27602-1551 Public Service Commission Mr. John H. ONeill, Jr.

State of South Carolina Shaw, Pittman, Potts, & Trowbridge Post Office Drawer 11649 2300 N Street NW.

Columbia, South Carolina 29211 Washington, DC 20037-1128 J. F. Lucas Mr. J. W. Moyer, Vice President Manager - Support Services - Nuclear H. B. Robinson Steam Electric Plant H. B. Robinson Steam Electric Plant, Unit No. 2 Unit No. 2 Carolina Power & Light Company Carolina Power & Light Company 3581 West Entrance Road 3581 West Entrance Road Hartsville, South Carolina 29550-0790 Hartsville, South Carolina 29550