ML040430086
Letter Sequence Approval | |
---|---|
TAC:MC1936, (Approved, Closed) | |
Initiation
Administration Questions
| |
MONTHYEARML0404300862004-02-0606 February 2004
[Table View]1 TS Page Callaway Plant, #1 - Issuance of Amd. 158 Required Action Completion Time for Inoperable Turbine-Driven Auxiliary Feedwater Pump (Tac. MC1936) Project stage: Approval ML0404106952004-02-0606 February 2004 2/6/04 Callaway Plant, Unit 1 - Issuance of Amd. 158 - Required Action Completion Time for Inoperable Turbine-Driven Auxiliary Feedwater Pump (Tac. MC1936) Project stage: Approval ML0423803202004-08-25025 August 2004 Palo Verde - Request to Use Subsequent Editions and Addenda of the ASME Code for Inservice Testing of Manual Valves Project stage: Other 2004-02-06 |
ML040430086 | |
Person / Time | |
---|---|
Site: | Callaway |
Issue date: | 02/06/2004 |
From: | Donohew J NRC/NRR/DLPM/LPD4 |
To: | Randolph G Union Electric Co |
Donohew J N, NRR/DLPM,415-1307 | |
Shared Package | |
ML040410713 | List: |
References | |
TAC MC1936 | |
Download: ML040430086 (1) | |
Similar Documents at Callaway | |
---|---|
Category:Technical Specification
MONTHYEARULNRC-06880, Proposed Technical Specification Bases Changes (Mark-up)2024-06-0606 June 2024
[Table view]Proposed Technical Specification Bases Changes (Mark-up) ML24158A5232024-06-0606 June 2024 Application to Revise Technical Specifications to Adopt Tstf-569, Rev. 2, Revise Response Time Testing Definition ML24158A5252024-06-0606 June 2024 Revised Technical Specification Pages (Clean Pages) ML24158A5242024-06-0606 June 2024 Proposed Technical Specification Changes (Mark-up) ULNRC-06827, Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029)2023-11-20020 November 2023 Supplement to License Amendment Request Regarding Support System Requirements for Residual Heat Removal and Control Room Air Conditioning Systems Under Technical Specifications 3.4.8, 3.7.11, and 3.9.6 (LDCN 22-0029) ML23310A0512023-11-0606 November 2023 EIP-ZZ.OO1O1, Addendum 2, Revision 22, Emergency Action Level Technical Bases Document ULNRC-06830, Corrected Proposed Technical Specification 5.5.16 Changes (Clean Pages)2023-08-15015 August 2023 Corrected Proposed Technical Specification 5.5.16 Changes (Clean Pages) ML23227A1272023-08-15015 August 2023 Corrected Proposed Technical Specification 55.16 Changes (Markup) ML23206A2252023-07-25025 July 2023 Corrected Proposed Technical Specification 5.5.16 Changes (Clean Pages) ML23206A2242023-07-25025 July 2023 Corrected Proposed Technical Specification 5.5.16 Changes (Markup) ML23093A0952023-05-10010 May 2023 Issuance of Amendment No. 232 Regarding Technical Specification Changes for Spent Fuel Storage ML23088A1222023-03-29029 March 2023 Attachment 2: Revised (Clean) Technical Specification Pages ML23088A1232023-03-29029 March 2023 Attachment 3: Marked-Up Technical Specification, Bases Pages ML23088A1212023-03-29029 March 2023 Attachment 1: Marked-Up Technical Specification Pages ML23088A2542023-03-23023 March 2023 EIP-ZZ-00101, Addendum 2, Revision 020, Emergency Action Level Technical Bases Document ML23052A0472023-02-21021 February 2023 Enclosure 5 - Revised Technical Specification Bases (for Information Only) ML23067A1822022-12-29029 December 2022 Rev. 18 to Technical Specification, Bases Change, Chapter 3.8, Electrical Power Systems ML23067A1752022-12-29029 December 2022 Rev. 18 to Technical Specification, Bases Change, Chapter 3.3, Instrumentation ML23067A1742022-12-29029 December 2022 Rev. 18 to Technical Specifications, Bases Change, Chapter 3.7, Plant Systems ML23067A1842022-12-29029 December 2022 Rev. 18 to Technical Specification, Bases Change, Chapter 3.4, Reactor Coolant System ML23067A1792022-12-29029 December 2022 Rev. 18 to Technical Specification Bases, Implemented Change Notice Log ML23067A1762022-12-29029 December 2022 Rev. 18 to Technical Specification Bases, Chapter 3.5, Emergency Core Cooling System S(Eccs) ML23067A1862022-12-29029 December 2022 Rev. 18 to Technical Specification, Bases Change, Chapter 3.2, Power Distribution Limits ML23067A1772022-12-29029 December 2022 Rev. 18 to Technical Specification Bases Change, Chapter B3, Safety Limits (Sls) ML23067A1782022-12-29029 December 2022 Rev. 18 to Technical Specification, Bases Change, Chapter 3.6, Containment Systems ML23067A1852022-12-29029 December 2022 Rev. 18 to Technical Specification, Bases Change, Chapter B 3.9, Refueling Operations ML23067A1832022-12-29029 December 2022 Rev. 18 to Technical Specification, Bases Change, Table of Contents ML23067A1812022-12-29029 December 2022 Rev. 18 to Technical Specification, Bases Change, Chapter B2, Safety Limits (Sls) ML23067A1802022-12-29029 December 2022 Rev. 18 to Technical Specification Bases, Chapter 3.1, Reactivity Control Systems ULNRC-06782, Rev. 18 to Technical Specification Bases, List of Effective Sections2022-12-29029 December 2022 Rev. 18 to Technical Specification Bases, List of Effective Sections ULNRC-06781, Attachment 2 - Proposed TS Bases Changes (Markups)2022-12-0101 December 2022 Attachment 2 - Proposed TS Bases Changes (Markups) ML22335A5092022-12-0101 December 2022 Description and Assessment of the Proposed Change ML22307A3152022-11-0303 November 2022 Attachment 3: Proposed Technical Specification 5.5.16 Changes (Clean Pages) ML22307A3142022-11-0303 November 2022 Attachment 2: Proposed Technical Specification 5.5.16 Changes (Markup) ML22285A1202022-10-12012 October 2022 Attachment 3 to Enclosure 1: Marked-Up Technical Specifications Bases (for Information Only) ULNRC-06766, Attachment 2: Retyped TS Pages for TS 3.6.82022-09-0808 September 2022 Attachment 2: Retyped TS Pages for TS 3.6.8 ML22242A1262022-08-29029 August 2022 Attachment 2 to Enclosure 1 - Revised Clean Technical Specifications ML22242A1272022-08-29029 August 2022 Attachment 3 to Enclosure 1 - Marked-Up Technical Specification Bases ML22242A1252022-08-29029 August 2022 Attachment 1 to Enclosure 1 - Marked-Up Existing Technical Specifications ML22216A2422022-08-0404 August 2022 Proposed Technical Specification Changes (Mark-Up) ML22181B1342022-06-30030 June 2022 Attachment 4 - Replacement for Attachment 4, Proposed Changes to Technical Specification Bases Changes (Mark-Up) Pages (for Information), of ULNRC-06688 ML22153A1792022-06-0202 June 2022 Attachment 3 - Marked-Up Technical Specifications Bases ULNRC-06686, Attachment 4: Proposed Technical Specifications Bases Changes (Mark-Up)2021-12-0909 December 2021 Attachment 4: Proposed Technical Specifications Bases Changes (Mark-Up) ML21335A4572021-12-0101 December 2021 Enclosure 5: Proposed Technical Specification Bases Changes (Mark-up - for Info Only) ML21294A4102021-10-21021 October 2021 Enclosure 10 - Program Implementation ML21294A4112021-10-21021 October 2021 Enclosure 11 - Monitoring Program ML21294A4092021-10-21021 October 2021 Enclosure 9 - Key Assumptions and Sources of Uncertainty ML21294A4122021-10-21021 October 2021 Enclosure 12 - Risk Management Action Examples ML21294A4072021-10-21021 October 2021 Enclosure 7 - PRA Model Update Process ML21294A4062021-10-21021 October 2021 Enclosure 6 - Justification of Application of At-Power PRA Models to Shutdown Modes 2024-06-06 Category:Amendment MONTHYEARML23206A2242023-07-25025 July 2023
[Table view]Corrected Proposed Technical Specification 5.5.16 Changes (Markup) ML23206A2252023-07-25025 July 2023 Corrected Proposed Technical Specification 5.5.16 Changes (Clean Pages) ML23093A0952023-05-10010 May 2023 Issuance of Amendment No. 232 Regarding Technical Specification Changes for Spent Fuel Storage ML23088A1222023-03-29029 March 2023 Attachment 2: Revised (Clean) Technical Specification Pages ML23088A1212023-03-29029 March 2023 Attachment 1: Marked-Up Technical Specification Pages ULNRC-06766, Attachment 2: Retyped TS Pages for TS 3.6.82022-09-0808 September 2022 Attachment 2: Retyped TS Pages for TS 3.6.8 ML22242A1262022-08-29029 August 2022 Attachment 2 to Enclosure 1 - Revised Clean Technical Specifications ML22242A1252022-08-29029 August 2022 Attachment 1 to Enclosure 1 - Marked-Up Existing Technical Specifications ML21294A3992021-10-21021 October 2021 Attachment 5 - Cross-Reference of TSTF-505 and Callaway Technical Specifications ML21294A4122021-10-21021 October 2021 Enclosure 12 - Risk Management Action Examples ML21294A4102021-10-21021 October 2021 Enclosure 10 - Program Implementation ML21294A4112021-10-21021 October 2021 Enclosure 11 - Monitoring Program ML21294A4092021-10-21021 October 2021 Enclosure 9 - Key Assumptions and Sources of Uncertainty ML21294A4082021-10-21021 October 2021 Enclosure 8 - Attributes of the Real Time Risk Model ML21294A4072021-10-21021 October 2021 Enclosure 7 - PRA Model Update Process ML21294A4062021-10-21021 October 2021 Enclosure 6 - Justification of Application of At-Power PRA Models to Shutdown Modes ML21294A4052021-10-21021 October 2021 Enclosure 5 - Baseline Core Damage Frequency (CDF) and Large Early Release Frequency (LERF) ML21294A4042021-10-21021 October 2021 Enclosure 4 - Information Supporting Justification of Excluding Sources of Risk Not Addressed by the PRA Models ML21294A4032021-10-21021 October 2021 Enclosure 3 - Information Supporting Technical Adequacy of PRA Models Without PRA Standards Endorsed by Regulatory Guide 1.200, Revision 2 ML21294A4022021-10-21021 October 2021 Enclosure 2 - Information Supporting Consistency with Regulatory Guide 1.200, Revision 2 ML21294A4012021-10-21021 October 2021 Enclosure 1 - List of Revised Required Actions to Corresponding PRA Functions ML21294A4002021-10-21021 October 2021 Attachment 6 - Description and Assessment Specific to TSTF-439 ML21294A3972021-10-21021 October 2021 Attachment 3 - Revised Technical Specification Pages ML21294A3962021-10-21021 October 2021 Attachment 2 - Proposed Technical Specification Changes (Mark-Up) ML21294A3952021-10-21021 October 2021 Attachment 1 - Description and Assessment ML20070R1212020-03-10010 March 2020 Technical Specification Page Markup ML20070R1142020-03-10010 March 2020 Description and Assessment of the Proposed Change ULNRC-06433, License Amendment Request for Emergency Action Level (EAL) Changes2018-09-0404 September 2018 License Amendment Request for Emergency Action Level (EAL) Changes ULNRC-06264, Revision of TS 2.1.1.1 and 5.6.5 to Remove Uncertainties from the DNBR Safety Limit and Adopt Approved WCAP-14565-P-A Methodology2015-11-0909 November 2015 Revision of TS 2.1.1.1 and 5.6.5 to Remove Uncertainties from the DNBR Safety Limit and Adopt Approved WCAP-14565-P-A Methodology ML15062A0522015-03-0606 March 2015 NRC-Callaway-TS-renewed License ULNRC-05832, Revision of Technical Specification 3.3.8, TAC No. ME51732011-12-13013 December 2011 Revision of Technical Specification 3.3.8, TAC No. ME5173 ML1130706942011-11-0303 November 2011 Attachment 5 - Control Building Room Locations and P&ID Excerpts ML1130706832011-11-0303 November 2011 Attachment 1 - Technical Specification Page Mark Up ML1130706812011-11-0303 November 2011 Enclosure Page 1 of 22, Evaluation of the Proposed Change ULNRC-05804, Facility Operating License NPF-30 - Proposed Revision to Technical Specification 3.6.6, Containment Spray and Cooling Systems, (License Amendment Request LDCN 09-0025)2011-06-30030 June 2011 Facility Operating License NPF-30 - Proposed Revision to Technical Specification 3.6.6, Containment Spray and Cooling Systems, (License Amendment Request LDCN 09-0025) ULNRC-05793, Application for Amendment to Facility Operating License NPF-30 (LDCN 10-0036) Revision of Technical Specification 3.3.8,2011-06-16016 June 2011 Application for Amendment to Facility Operating License NPF-30 (LDCN 10-0036) Revision of Technical Specification 3.3.8, ULNRC-05682, Application for Amendment, Revision of Technical Specification 3.3.92010-03-0404 March 2010 Application for Amendment, Revision of Technical Specification 3.3.9 ULNRC-05560, Revision of Technical Specifications 3.8.4 and 3.8.5, Application for Amendment to Facility Operating License NPF-30 (LDCN 08-002)2008-12-29029 December 2008 Revision of Technical Specifications 3.8.4 and 3.8.5, Application for Amendment to Facility Operating License NPF-30 (LDCN 08-002) ML0824602412008-11-24024 November 2008 Issuance of Amendment No. 187, Revise Technical Specification 5.5.8, Inservice Testing Program, Testing Frequencies ULNRC-05494, Application for Amendment to Facility Operating License NPF-30 OL1283 - Revision of Technical Specifications 3.3, 3.7, and 3.82008-06-0303 June 2008 Application for Amendment to Facility Operating License NPF-30 OL1283 - Revision of Technical Specifications 3.3, 3.7, and 3.8 ML0706803502007-03-21021 March 2007 License and Technical Specification Pages - Amendment No. 182 Revision to Technical Specifications for Use of Beacon Power Distribution Monitoring System ML0632801852006-11-17017 November 2006 Callaway - Proposed Revision to Technical Specification 3.9.2 Unborated Water Source Isolation Valves and Associated Revisions to Technical Specification 3.3.9 Boron Dilution Mitigation System (Bdms) (License Amendment Request OL 1238) ULNRC-05345, Proposed Revision to Technical Specification 3.9.2 Unborated Water Source Isolation Valves and Associated Revisions to Technical Specification 3.3.9 Boron Dilution Mitigation System (Bdms).2006-11-17017 November 2006 Proposed Revision to Technical Specification 3.9.2 Unborated Water Source Isolation Valves and Associated Revisions to Technical Specification 3.3.9 Boron Dilution Mitigation System (Bdms). ULNRC-05314, Exigent Request for Revision to Technical Specification 3.4.15, RCS Leakage Detection Instrumentation.2006-07-19019 July 2006 Exigent Request for Revision to Technical Specification 3.4.15, RCS Leakage Detection Instrumentation. ULNRC-05301, Proposed Revision to Technical Specification TSs 3.7.10, 3.7.11 and 3.7.132006-06-0707 June 2006 Proposed Revision to Technical Specification TSs 3.7.10, 3.7.11 and 3.7.13 ULNRC-05297, Proposed Revision to Technical Specifications for Use of Beacon Power Distribution Monitoring System2006-05-25025 May 2006 Proposed Revision to Technical Specifications for Use of Beacon Power Distribution Monitoring System ULNRC-05269, Proposed Revision to Technical Specification 3.9.2 Unborated Water Source Isolation Valves and Associated Revisions to Technical Specification 3.3.9 Boron Dilution Mitigation System (Bdms) (License Amendment Request OL 1238)2006-03-28028 March 2006 Proposed Revision to Technical Specification 3.9.2 Unborated Water Source Isolation Valves and Associated Revisions to Technical Specification 3.3.9 Boron Dilution Mitigation System (Bdms) (License Amendment Request OL 1238) ULNRC-05206, License Amendment Request OL 1258 Revision to Technical Specification 3.7.3, Main Feedwater Isolation Valves (Mfiv'S)2005-09-0909 September 2005 License Amendment Request OL 1258 Revision to Technical Specification 3.7.3, Main Feedwater Isolation Valves (Mfiv'S) ML0506903182005-03-0808 March 2005 Technical Specification Pages Re Elimination of Requirements to Provide Monthly Operating Reports & Annual Occupational Radiation Exposure Reports ULNRC-05117, Technical Specification Revisions Associated with the Steam Generator Replacement Project2005-02-11011 February 2005 Technical Specification Revisions Associated with the Steam Generator Replacement Project 2023-07-25 |
Text
AFW System 3.7.5 3.7 PLANT SYSTEMS 3.7.5 Auxiliary Feedwater (AFW) System LCO 3.7.5 Three AFW trains shall be OPERABLE.
APPLICABILITY: MODES 1, 2, and 3.
ACTIONS CONDITION REQUIRED ACTION TIME A One steam supply to A.1 Restore steam supply to 7 days turbine driven AFW pump OPERABLE status.
inoperable. AND 10 days from discovery of failure to meet the LCO B. One ESW supply to turbine B.1 Restore ESW supply to 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> driven AFW pump OPERABLE status.
inoperable AND 10 days from discovery of failure to meet the LCO C. One AFW train inoperable C.1 Restore AFW train to 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />s*
for reasons other than OPERABLE status.
Condition A or B. AND 10 days from discovery of failure to meet the LCO (continued)
- With the exception that the Completion Time associated with the Condition C entry on 2/3/04 for the turbine driven auxiliary feedwater pump has been extended on a one-time only basis to 144 hours0.00167 days <br />0.04 hours <br />2.380952e-4 weeks <br />5.4792e-5 months <br />. At the time a formal cause of the inoperability is determined, Condition D will be entered immediately.
CALLAWAY PLANT 3.7-12 Amendment No.158