MONTHYEARML0404200432004-01-30030 January 2004 Correction to Technical Specification Change Request No. 318 - Operating Condition Mode Change Limitations Based on NRC Approved Industry/Technical Specification Task Force STS Change (TSTF) - 359 Revision 9 Project stage: Other ML0409002892004-03-29029 March 2004 Tech Spec Pages for Amendment 241 Regarding Increasing Flexibility in Mode Restraints Project stage: Other ML0407003902004-03-29029 March 2004 License Amendment 241 Regarding Increasing Flexibility in Mode Restraints Project stage: Approval 2004-01-30
[Table View] |
|
---|
Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARML24214A0372024-08-0101 August 2024 License Amendment Request to Revise Renewed Facility Operating License to Add License Condition 2.C.(18) to Include License Termination Plan Requirements ML21075A3372021-03-16016 March 2021 License Amendment Request to Revise Oyster Creek Nuclear Generating Station Permanently Defueled Technical Specificat Ions to Reflect Perm Anent Removal of Spent Fuel from Spent Fuel Pool ML21054A3212021-02-23023 February 2021 License Amendment Request to Approve Independent Spent Fuel Storage Installation Only Emergency Plan RA-18-080, License Amendment Request: License Condition Revision for Removal of Cyber Security Plan Requirements2018-11-12012 November 2018 License Amendment Request: License Condition Revision for Removal of Cyber Security Plan Requirements RA-18-098, License Amendment Request Supplement - Proposed Change of Effective and Implementation Dates of License Amendment No. 294, Oyster Creek Emergency Plan for Permanently Defueled Emergency Plan and Emergency Action Level Scheme2018-11-0606 November 2018 License Amendment Request Supplement - Proposed Change of Effective and Implementation Dates of License Amendment No. 294, Oyster Creek Emergency Plan for Permanently Defueled Emergency Plan and Emergency Action Level Scheme RA-18-092, License Amendment Request - Proposed Change of Effective and Implementation Dates of License Amendment No. 294, Oyster Creek Emergency Plan for Permanently Defueled Emergency Plan and Emergency Action Level Scheme2018-10-22022 October 2018 License Amendment Request - Proposed Change of Effective and Implementation Dates of License Amendment No. 294, Oyster Creek Emergency Plan for Permanently Defueled Emergency Plan and Emergency Action Level Scheme RA-17-072, License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition2017-11-16016 November 2017 License Amendment Request - Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition RA-17-055, License Amendment Request to Implement BWRVIP-18, Revision 2-A2017-08-30030 August 2017 License Amendment Request to Implement BWRVIP-18, Revision 2-A RA-17-049, License Amendment Request - Proposed Changes to the Oyster Creek Emergency Plan for Permanently Defueled Emergency Plan and Emergency Action Level Scheme2017-08-29029 August 2017 License Amendment Request - Proposed Changes to the Oyster Creek Emergency Plan for Permanently Defueled Emergency Plan and Emergency Action Level Scheme ML17100A8442017-04-10010 April 2017 License Amendment Request Regarding Revision to Cyber Security Plan Milestone 8 Completion Date RA-17-012, License Amendment Request - Proposed Changes to the Oyster Creek Emergency Plan for Permanently Defueled Condition2017-02-28028 February 2017 License Amendment Request - Proposed Changes to the Oyster Creek Emergency Plan for Permanently Defueled Condition NMP1L3095, License Amendment Request - Proposed Revision to Technical Specifications in Response to GE Energy - Nuclear 10 CFR Part 21 Safety Communication SC05-032016-08-0101 August 2016 License Amendment Request - Proposed Revision to Technical Specifications in Response to GE Energy - Nuclear 10 CFR Part 21 Safety Communication SC05-03 RA-16-021, License Amendment Request for Proposed Changes to Technical Specifications Section 6.0 Administrative Controls for Permanently Defueled Condition2016-05-17017 May 2016 License Amendment Request for Proposed Changes to Technical Specifications Section 6.0 Administrative Controls for Permanently Defueled Condition RA-14-057, License Amendment Request Regarding the Cyber Security Plan Implementation Schedule for Milestone 82014-08-29029 August 2014 License Amendment Request Regarding the Cyber Security Plan Implementation Schedule for Milestone 8 RA-14-032, License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors.2014-05-30030 May 2014 License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors. ML14164A0542014-05-30030 May 2014 License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors. NEI 99-01, License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors.2014-05-30030 May 2014 License Amendment Request to Adopt Emergency Action Level Schemes Pursuant to NEI 99-01, Revision 6, Development of Emergency Action Levels for Non-Passive Reactors. RA-14-046, Request for Amendment to Revise Oyster Creek Nuclear Generating Station Under Snubber Surveillance Requirements2014-04-30030 April 2014 Request for Amendment to Revise Oyster Creek Nuclear Generating Station Under Snubber Surveillance Requirements RA-13-101, License Amendment Request Related to Building Vital Area Access Control2013-12-19019 December 2013 License Amendment Request Related to Building Vital Area Access Control RA-13-077, Company License Amendment Request to Revise the Emergency Plan Requalification Training Frequency for Emergency Response Organization Personnel2013-10-30030 October 2013 Company License Amendment Request to Revise the Emergency Plan Requalification Training Frequency for Emergency Response Organization Personnel RS-13-070, Application to Revise Technical Specifications to Adopt TSTF-535, Revise Shutdown Margin Definition to Address Advanced Fuel Designs2013-08-0202 August 2013 Application to Revise Technical Specifications to Adopt TSTF-535, Revise Shutdown Margin Definition to Address Advanced Fuel Designs RA-10-027, Technical Specification Change Request No. 356, Elimination of Daily Testing of an Operable Emergency Diesel Generator (EDG) When the Other EDG Is Declared Inoperable2010-06-25025 June 2010 Technical Specification Change Request No. 356, Elimination of Daily Testing of an Operable Emergency Diesel Generator (EDG) When the Other EDG Is Declared Inoperable RA-10-050, Technical Specification Change Request No. 340, Proposed Revision to Appendix B Environmental Technical Specifications of the Facility Operating License2010-06-11011 June 2010 Technical Specification Change Request No. 340, Proposed Revision to Appendix B Environmental Technical Specifications of the Facility Operating License RA-10-009, Oyster Creek, License Amendment Request, Changes to Trunnion Room Secondary Containment Boundary2010-02-25025 February 2010 Oyster Creek, License Amendment Request, Changes to Trunnion Room Secondary Containment Boundary ML1006200112010-02-25025 February 2010 Oyster Creek, License Amendment Request, Changes to Trunnion Room Secondary Containment Boundary ML0932802342009-11-23023 November 2009 Request for Approval of the Exelon Cyber Security Plan RA-09-065, Application for Technical Specifications Change Regarding Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program (Adoption of TSTF-425, Rev 3)2009-10-30030 October 2009 Application for Technical Specifications Change Regarding Risk-Informed Justification for Relocation of Specific Surveillance Frequency Requirements to Licensee Controlled Program (Adoption of TSTF-425, Rev 3) RA-08-047, Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency, Clarification of SRM Insert Control Rod Action and Clarification of a Frequency Example Using the Consolidation Line Item I2008-06-0909 June 2008 Application for Technical Specification Change Regarding Revision of Control Rod Notch Surveillance Test Frequency, Clarification of SRM Insert Control Rod Action and Clarification of a Frequency Example Using the Consolidation Line Item Im RA-08-024, Amergen, Energy LLC, License Amendment Request to Remove References to NRC Generic Letter 82-12, Nuclear Power Plant Staff Working Hours.2008-04-21021 April 2008 Amergen, Energy LLC, License Amendment Request to Remove References to NRC Generic Letter 82-12, Nuclear Power Plant Staff Working Hours. RA-08-004, Technical Specification Change Request No. 348 - Relocation of Pressure and Temperature (P-T) Curves to the Pressure and Temperature Limits Report (PTLR)2008-03-10010 March 2008 Technical Specification Change Request No. 348 - Relocation of Pressure and Temperature (P-T) Curves to the Pressure and Temperature Limits Report (PTLR) RS-08-012, Amergen Company, Request for Amendment to Administrative Controls Section of Technical Specifications2008-02-28028 February 2008 Amergen Company, Request for Amendment to Administrative Controls Section of Technical Specifications ML0732400402007-11-13013 November 2007 Technical Specification Request No. 336 and Three Mile Island Technical Specification Change Request No. 330 Deletion of Technical Specification Requirements for Review and Audit, and Additional Administrative Changes RS-07-078, Amergen - License Amendment Request to Change Technical Specification Unit Staff Qualifications Education and Experience Eligibility Requirements for Licensed Operators2007-07-19019 July 2007 Amergen - License Amendment Request to Change Technical Specification Unit Staff Qualifications Education and Experience Eligibility Requirements for Licensed Operators RS-07-020, Exelon/Amergen Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process2007-04-12012 April 2007 Exelon/Amergen Application to Revise Technical Specifications Regarding Control Room Envelope Habitability in Accordance with TSTF-448, Revision 3, Using the Consolidated Line Item Improvement Process ML0633201962006-11-27027 November 2006 Technical Specification Change Request No. 341 - Revision to Required Submittal Date for Annual Radioactive Effluent Release Report ML0615703332006-06-0202 June 2006 2006/06/02-Oyster Creek Generating Station, Supplemental Information Related to Oyster Creek Generating Station License Renewal Application ML0615103502006-05-25025 May 2006 Technical Specification Change Request No. 328 - Response to Request for Additional Information Concerning a Revision to Surveillance Requirements for Testing of Main Steam Line Electromatic Relief Valve ML0534302552005-12-0202 December 2005 License Amendment Request Increase Safety Valve As-Found Setpoint Tolerance from 1% to 3% ML0534302562005-12-0202 December 2005 GE-NE-0000-0046-3343-NP, Rev 1, Oyster Creek, License Amendment Request Increase Safety Valve As-Found Setpoint Tolerance from 1% to 3%, Attachment 5 ML0529701902005-10-18018 October 2005 Technical Specification Change Request No. 328 - Modify Surveillance Requirements for Testing of Main Steam Line Electromatic Relief Valves ML0607902732005-09-0808 September 2005 2005/09/08-Oyster Creek License Renewal Scoping and Screening Procedures ((Form CD-Rom) (PA) ML0530504772005-07-22022 July 2005 Oyster Creek - Application for Renewed Operating License No. DPR-16 ML0520800482005-07-22022 July 2005 Oyster Creek Generating Station, Application for Renewed Operating License ML0513704932005-05-10010 May 2005 Oyster Creek Generating Station, Submittal of Changes to Technical Specifications Bases ML0509402342005-03-28028 March 2005 License Amendment Request No. 315 - Application of Alternative Source Term ML0508705402005-03-25025 March 2005 Technical Specification Change Request No. 332 - Upgrade of 69 Kv Offsite Power Transmission Line RS-05-024, Application for Approval of Indirect License Transfers2005-03-0303 March 2005 Application for Approval of Indirect License Transfers RS-05-006, Nuclear/Amergen, Proposed Changes to Delete the Reporting Requirement Section of the Facility Operating License2005-02-25025 February 2005 Nuclear/Amergen, Proposed Changes to Delete the Reporting Requirement Section of the Facility Operating License ML0505900852005-02-24024 February 2005 Technical Specification Change Request No. 319 - Revision to Table 3.1.1 Notes Aa and Bb Regarding Reactor Building Closed Cooling Water Pump and Service Water Pump Trip Conditions RS-04-157, Proposed Revision to Appendix B, Environmental Protection Plan (Non-Radiological) of the Facility Operating License2004-12-17017 December 2004 Proposed Revision to Appendix B, Environmental Protection Plan (Non-Radiological) of the Facility Operating License 2024-08-01
[Table view] |
Text
AmerGenm AmerGen Energy Company, LLC www.exeloncorp.com An Exelon/British Energy Company 200 Exelon Way Kennett Square, PA 19348 10 CFR 50.90 2130-04-20019 January 30, 2004 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
SUBJECT:
Oyster Creek Generating Station Facility Operating License No. DPR-1 6 NRC Docket No. 50-219 Correction to Technical Specification Change Request No. 318 - Operating Condition Mode Change Limitations Based on NRC Approved Industry/
Technical Specification Task Force STS Change (TSTF) -359 Revision 9 (TAC MC1 652).
REFERENCE:
AmerGen Letter No. 2130-03-20272, dated December 23, 2003, Technical Specification Change Request No. 318- Operating Condition Mode Change Limitations Based on NRC Approved Industry/Technical Specification Task Force STS Change (TSTF) -359 Revision 9 (TAC MC1652).
On December 23, 2003, AmerGen transmitted Letter No. 2130-03-20272, Technical Specification Change Request No. 318 - Operating Condition Mode Change Limitations Based on NRC Approved Industry/Technical Specification Task Force STS Change (TSTF) -359 Revision 9, to the NRC. During the initial review of the proposed amendment, NRC identified that there were two typographical errors on Technical Specification (TS) page 4.0-1 and that an incorrect Table of Contents page had been included in the submittal. The typographical errors are:
- 1) Enclosure 3, Retyped TS page 4.0-1, Specification 4.0.3, in the first sentence, "OPERATING CONDITION" should be "OPERATIONAL CONDITION".
- 2) Enclosure 3, Retyped TS page 4.0-1, Amendment No. should be "185" Also, Table of Contents, page iii, Amendment No. 186 was incorrectly submitted with Letter No. 2130-03-20272. The correct Table of Contents page iii should be Amendment No. 232. to this letter contains the corrected pages affected by the typographical errors and the correct Table of Contents page iii. The correction of the typographical errors and the replacement of Table of Contents page iii are purely editorial in nature and in no way affect the evaluation of the change or the No Significant Hazards Determination provided under Letter No.
2130-03-20272.
1.
U.S. Regulatory Commission January 30, 2004 Page 2 We are notifying the State of New Jersey of this correction to the application for changes to the Technical Specifications by transmitting a copy of this letter and its attachment to the designated State Official.
If any additional information is needed, please contact Dave Robillard at (610) 765-5952.
I declare under penalty of perjury that the foregoing is true and correct.
Sincerely, Eeu-30 -Zed Executed On Michael P. Gallagher Director, Licensing & Regulatory Affairs AmerGen Energy Company, LLC
Enclosure:
(1) Oyster Creek Technical Specification Change Request No. 318, Corrected Pages cc: H. J. Miller, Administrator, USNRC Region 1 P. S. Tam, USNRC Senior Project Manager, Oyster Creek
- R. J. Summers, USNRC Senior Resident Inspector, Oyster Creek File No. 03092
ENCLOSURE I Oyster Creek Technical Specification Change Request No. 318 Corrected Pages This enclosure consists of the corrected pages from AmerGen Letter No. 2130-03-20272.
The pages included in this enclosure are:
PAGES Enclosure 2, Inserts - Page 3 Pii TS Page 4.0-1
Specification 3.0.C.3 allows entry into an OPERATIONAL CONDITION or other specified condition in the Applicability with the Limiting Condition for Operation not met based on a Note in the Specification which states Specification 3.0.C.3 is applicable. These specific allowances permit entry into OPERATIONAL CONDITIONS or other specified conditions in the Applicability when the associated LCO requirements do not provide for continued operation for an unlimited period of time and a risk assessment has not been performed. This allowance may apply to all the LCO conditions or to a specific requirement of a Specification. The risk assessments performed to justify the use of Specification 3.0.C.2 usually only consider systems and components. For this reason, Specification 3.0.C.3 is typically applied to Specifications which describe values and parameters, and may be applied to other Specifications based on NRC plant-specific approval.
The provisions of this Specification should not be interpreted as endorsing the failure to exercise the good practice of restoring systems or components to OPERABLE status before entering an associated OPERATIONAL CONDITION or other specified condition in the Applicability.
The provisions of Specification 3.0.C shall not prevent changes in OPERATIONAL CONDITIONS or other specified conditions in the Applicability that are required to comply with LCO requirements. In addition, the provisions of Specification 3.0.C shall not prevent changes in OPERATIONAL CONDITIONS or other specified conditions in the Applicability that result from any unit shutdown. In this context, a unit shutdown is defined as a change in OPERATIONAL CONDITION or other specified condition in the Applicability associated with transitioning from POWER OPERATION to STARTUP MODE, STARTUP MODE to SHUTDOWN CONDITION, and SHUTDOWN CONDITION to COLD SHUTDOWN CONDITION.
Upon entry into an OPERATIONAL CONDITION or other specified condition in the Applicability with the Limiting Condition for Operation not met, Specification 3.0.A requires entry into the LCO requirements until the Condition is resolved, until the Limiting Condition for Operation is met, or until the unit is not within the Applicability of the Technical Specification.
Surveillances do not have to be performed on the associated inoperable equipment (or on variables outside the specified limits), as permitted by Specification 4.0.1. Therefore, utilizing Specification 3.0.C is not a violation of Specification 4.0.1 or Specification 4.0.3 for any Surveillances that have not been performed on inoperable equipment. However, Surveillance Requirements must be met to ensure OPERABILITY prior to declaring the associated equipment OPERABLE (or variable within limits) and restoring compliance with the affected Limiting Condition for Operation.
INSERT 4 4.0.3 Entry into an OPERATIONAL CONDITION or other specified condition in the Applicability of an LCO shall only be made when the LCO's Surveillances have been met within their specified frequency, except as provided by 4.0.2. When an LCO is not met due to surveillances not having been met, entry into an OPERATIONAL CONDITION or other specified condition in the Applicability shall only be made in accordance with LCO 3.0.C.
This provision shall not prevent entry into OPERATIONAL CONDITIONS or other specified conditions in the Applicability that are required to comply with LCO requirements or that are part of a shutdown of the unit.
TABLE OF CONTENTS (Cont'd) 4.10 ECCs Related Core Limits 4.10-1 4.11 Sealed Source Contamination 4.11-1 4.12 Alternate Shutdown Monitoring Instrumentation 4.12-1 4.13 Accident Monitoring Instrumentation 4.13-1 4.14 DELETED 4.14-1 4.15 Explosive Gas Monitoring Instrumentation 4.15-1 4.16 (Deleted) 4.16-1 4.17 Control Room Heating, Ventilating and Air Conditioning System 4.17-1 Section 5 Design Features 5.1 Site 5.1-1 5.2 Containment 5.2-1 5.3 Auxiliary Equipment 5.3-1 Section 6 Administrative Controls 6.1 Responsibility 6-1 6.2 Organization 6-1 6.3 Facility Staff Qualifications 6-2a 6.4 DELETED 6-3 6.5 Review and Audit 6-3 6-6 Reportable Event Action 6-9 6-7 Safety Limit Violation 6-9 6-8 Procedures and Programs 6-10 6-9 Reporting Requirements 6-13 6-10 Record Retention 6-17 6-11 Radiation Protection Program 6-18 6-12 (Deleted) 6-18 6-13 High Radiation Area 6-18 6-14 Environmental Qualification 6-19*
6-15 Integrity of Systems Outside Containment 6-19 6-16 Iodine Monitoring 6-19 6-17 Post Accident Sampling 6-20 6-18 Process Control Plan 6-20 6-19 Offsite Dose Calculation Manual 6-20 6-20 DELETED 6-20 6-21 Technical Specification (TS) Bases Control Program 6-21
- Issued by NRC Order dated 10-24-80 OYSTER CREEK iii Amendment No.:94, 97, 98, 108, 115, 434,466,486, 23-2
Section 4 Surveillance Requirements 4.0 Surveillance Requirement Applicability 4.0.1 Surveillance requirements shall be met during the modes or other specified conditions in the applicability for individual LCOs, unless otherwise stated in the surveillance requirements. Failure to meet a surveillance, whether such failure is experienced during the performance of the surveillance or between performances of the surveillance, shall be failure to meet the LCO. Failure to perform a surveillance within the specified frequency shall be failure to meet the LCO except as provided in 4.0.2. Surveillances do not have to be performed on inoperable equipment or variables outside specified limits.
4.0.2 If it is discovered that a surveillance was not performed within its specified frequency, then compliance with the requirement to declare the LCO not met may be delayed, from the time of discovery, up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or up to the limit of the specified frequency, whichever is greater. This delay period is permitted to allow performance of the surveillance. A risk evaluation shall be performed for any surveillance delayed greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and the risk impact shall be managed.
If the surveillance is not performed within the delay period, the LCO must immediately be declared not met, and the applicable condition(s) must be entered.
When the surveillance is performed within the delay period and the surveillance is not met, the LCO must immediately be declared not met, and the applicable condition(s) must be entered.
4.0.3 Entry into an OPERATIONAL CONDITION or other specified condition in the Applicability of an LCO shall only be made when the LCO's Surveillances have been met within their specified frequency, except as provided by 4.0.2. When an LCO is not met due to surveillances not having been met, entry into an OPERATIONAL CONDITION or other specified condition in the Applicability shall only be made in accordance with LCO 3.0.C.
This provision shall not prevent entry into OPERATIONAL CONDITIONS or other specified conditions in the Applicability that are required to comply with LCO requirements or that are part of a shutdown of the unit.
BASES: Surveillance Requirement 4.0.1 establishes the requirement that surveillance requirements must be met during the modes or other specified conditions in the applicability for which the requirements of the LCO apply, unless otherwise specified in the individual surveillance requirements. This specification is to ensure that surveillances are performed to verify the OPERABILITY of systems and components, and that variables are within specified limits. Failure to meet a surveillance within the specified frequency constitutes a failure to meet an LCO.
OYSTER CREEK 4.0-1 Amendment No. 485,