Correction of License and Technical Specifications TAC No. MC1763
ML040330202
Person / Time
Site: Millstone 
Issue date: 03/04/2004
From: Nerses V
NRC/NRR/DLPM/LPD1
To: Christian D
Dominion Nuclear Connecticut
Nerses V, NRR//DLPM, 415-1484
References
TAC MC1763
Download: ML040330202 (7)


Text

March 4, 2004 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

CORRECTION OF LICENSE AND TECHNICAL SPECIFICATIONS FOR MILLSTONE POWER STATION, UNIT NO. 3 (TAC NO. MC1763)

Dear Mr. Christian:

The purpose of this letter is to provide you with the results of the U.S. Nuclear Regulatory Commission (NRC) staff review of the license and technical specifications for the subject plant.

The NRC is conducting a comparison of its license authority files to the licensees records to ensure errors in licenses and technical specifications are identified and corrected. I have completed the comparison of the NRCs license authority file and your records to determine whether corrections were necessary. The differences found were administrative in nature. The enclosures provide the differences found during this comparison review. I discussed the corrections (Enclosure 1) that are necessary with Mohamed A. Elmaghrabi of your staff on January 27, 2004.

If you would like a copy of any of the amendments referenced in Enclosure 1, please give me a call.

While reviewing the license and technical specifications, it was discovered through a cursory look at the Bases pages that several pages were different than the copy in our authority file. contains a listing of the Bases pages differences found during this review.

If you have any questions you can contact me at 301-415-1484.

Sincerely,

/RA/

Victor Nerses, Senior Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-423

Enclosures:

As stated cc w/encls: See next page

March 4, 2004 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

CORRECTION OF LICENSE AND TECHNICAL SPECIFICATIONS FOR MILLSTONE POWER STATION, UNIT NO. 3 (TAC NO. MC1763)

Dear Mr. Christian:

The purpose of this letter is to provide you with the results of the U.S. Nuclear Regulatory Commission (NRC) staff review of the license and technical specifications for the subject plant.

The NRC is conducting a comparison of its license authority files to the licensees records to ensure errors in licenses and technical specifications are identified and corrected. I have completed the comparison of the NRCs license authority file and your records to determine whether corrections were necessary. The differences found were administrative in nature. The enclosures provide the differences found during this comparison review. I discussed the corrections (Enclosure 1) that are necessary with Mohamed A. Elmaghrabi of your staff on January 27, 2004.

If you would like a copy of any of the amendments referenced in Enclosure 1, please give me a call.

While reviewing the license and technical specifications, it was discovered through a cursory look at the Bases pages that several pages were different than the copy in our authority file. contains a listing of the Bases pages differences found during this review.

If you have any questions you can contact me at 301-415-1484.

Sincerely,

/RA/

Victor Nerses, Senior Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-423

Enclosures:

As stated cc w/encls: See next page DISTRIBUTION:

CRaynor CHolden PUBLIC DRoberts SBloom PDI-2 R/F BMcDermott, RI GHill (2)

VNerses ADAMS Accession Number: ML040330202 OFFICE PDI-2/PM PDI-2/LA PDI-2/SC NAME VNerses CRaynor DRoberts DATE 02/13/04 02/10/04 03/03/04 OFFICIAL RECORD COPY

DIFFERENCES IN LICENSE AND TECHNICAL SPECIFICATIONS FOUND DURING NRC REVIEW The review by the NRC staff comparing a copy of the license and Technical Specifications (TSs) provided by you as a copy of Controlled Copy No. 20 through change number 222, issued to: Master, with the NRC Authority File provided the following issues.

Millstone 3 copy - M3 NRC Authority File - AF 1.

Index page xv M3 - There are two (2) copies of this page. One is through Amendment 214 and the other is through Amendment 192.

AF - Only Amendment 214 2.

The following M3 pages have missing change bars.

Index page xviii, Amendment 173 dated August 13, 1999 3/4 2-9, Amendment 99, dated December 12, 1994 3/4 2-12, Amendment 120, dated October 18, 1995 3/4 3-5, Amendment 164, dated October 21, 1998 3/4 3-16, Amendment 187, dated November 3, 2000 3/4 3-31, Amendment 134, dated March 11, 1997 3/4 3-82, Amendment 164, dated October 21, 1998 3/4 9-17, Amendment 189, dated November 28, 2000 3.

TS page 3/4 3-39 and 3-41 M3 - The text is correct but the correction letter date of March 29, 2002 is latest change date not February 20, 2002.

4.

TS page 3/4 7-21 M3 - Change bar in wrong location from Amendment 206, dated July 24, 2002.

5.

TS pages 3/4 8-23 thru 8-37 M3 - Pages are deleted AF - Pages are included Licensee letter dated July 24, 1990, had requested the deletion of pages 3/4 8-24 through 3/4 8-37 because previous text was moved forward and pages which were left intentionally blank were being removed. Amendment 64, dated March 9, 1992 moved TS 3.8.4.2.1 from page 3/4 8-28 to 3/4 8-21, TS 3.8.4.2.2 from page 3/4 8-32 to 3/4 8-22, and TS 3.8.4.3 from page 3/4 8-37 to 3/4 8-23; however it did not discuss the removal of pages 3/4 8-24 through 3/4 8-37 or indicate in the insert/remove page to remove them. Page 3/4 8-23 was subsequently removed by Amendment 121, dated November 29, 1995.

A letter under separate cover will be issued to show the removal of pages 3/4 8-23 through 3/4 8-37.

6.

TS page 6-19a M3 - Page should reflect Amendment 188, dated November 28, 2000, on the bottom of the page. The text is correct.

DIFFERENCES FOUND IN BASES PAGES DURING NRC REVIEW 1.

Bases page B3/4 4-1a M3 - Amendment 202 AF - Amendment 197 Amendment 202 did not change this page. Page now superceded by Amendment 217.

2.

Bases page B3/4 4-5 M3 - Section 3/4 4.7, Chemistry, not clear that letter dated May 8, 2002 deleted this.

AF - Revised April 2, 2002 3.

Bases page B3/4 5-2 thru 2d; All M3 pages are different than AF pages.

M3 - Page B3/4 5-2c, LBDCR 3-7-02, July 3, 2002 M3 - Page B3/4 5-2d, LBDCR 3-17-01, February 14, 2002 AF - No B3/4 5-2c or d page Pages B 3/4 5-2, 2a, 2b, and 2c will be addressed under the review of licensees submittal dated July 31, 2003. Please provide page B 3/4 5-2d for our files.

4.

Bases page B3/4 7-7a M3 - LBDCR 3-2-02, March 14, 2002 AF - Amendment 151 dated October 2, 1997 5.

Bases pages B3/4 7-23, 23a, 24, and 25 On February 20, 2002 Amendment 203 was issued. This amendment made changes to Bases page B3/4 7-23 and added page B3/4 7-23a. Subsequently Bases page changes were made in NRC letter dated June 3, 2002. However the June 3, 2002 changes did not reflect the changes previously made in Amendment 203. The M3 copy shows the Amendment 203 changes, but the NRC AF does not.

We believe the reason for this is that the M3 copy reflects Amendment 203 which moved text from page B3/4 7-23a to B3/4 7-24 and B3/4 7-25. Presently the AF has page B3/4 7-25 which has some text that is already on page B3/4 7-24. It is not clear which is correct.

6.

Bases page B3/4 8-1c and 1d M3 - LBDCR 3-2-03, 10/9/03 AF - Amendment 210 7.

Bases pages 3/4 9-8 and 9-9 On February 20, 2002 Amendment 203 was issued. This amendment made changes to Bases page B 3/4 9-8 and B 3/4 9-9. When the staff issued Bases changes in a letter dated June 3, 2002 the changes from Amendment 203 were not included. M3 did not delete the changes on their pages. It is not clear which is correct.

Millstone Power Station, Unit No. 3 cc:

Lillilan M. Cuoco, Esquire Senior Counsel Dominion Resources Services, Inc.

Rope Ferry Road Waterford, CT 06385 Edward L. Wilds, Jr., Ph.D.

Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 First Selectmen Town of Waterford 15 Rope Ferry Road Waterford, CT 06385 Mr. P. J. Parulis Manager - Nuclear Oversight Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. W. R. Matthews Senior Vice President - Nuclear Operations Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. John Markowicz Co-Chair Nuclear Energy Advisory Council 9 Susan Terrace Waterford, CT 06385 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terrys Plain Road Simsbury, CT 06070 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Mr. G. D. Hicks Director - Nuclear Station Safety and Licensing Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870 Mr. William D. Meinert Nuclear Engineer Massachusetts Municipal Wholesale Electric Company Moody Street P.O. Box 426 Ludlow, MA 01056 Mr. J. Alan Price Site Vice President Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. Chris Funderburk Director, Nuclear Licensing and Operations Support Dominion Resources Services, Inc.

5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. David W. Dodson Licensing Supervisor Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385

Millstone Power Station, Unit No. 3 cc:

Mr. S. E. Scace Assistant to the Site Vice President Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. M. J. Wilson Manager - Nuclear Training Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. A. J. Jordan, Jr.

Director - Nuclear Engineering Dominion Nuclear Connecticut, Inc.

Rope Ferry Road Waterford, CT 06385 Mr. S. P. Sarver Director - Nuclear Station Operations and Maintenance Dominion Nuclear Connecticut, Inc.