January 30, 2004 Mr. Fred J. Cayia Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - WITHDRAWAL OF PROPOSED EMERGENCY PLAN AND EMERGENCY PLAN IMPLEMENTING PROCEDURE CHANGES (TAC NOS. MB1410 AND MB1411)

Dear Mr. Cayia:

By letter dated November 25, 2003, you submitted proposed changes to the Point Beach Nuclear Plant (PBNP) Emergency Plan and Emergency Plan Implementing Procedure 1.2. You requested Nuclear Regulatory Commission (NRC) staff review and approval of the proposed changes.

We performed an acceptability review of your submittal in accordance with 10 CFR 50.4. On January 7, 2004, we held a telephone conference with your staff to inform you of the results of our acceptance review. We indicated that your submittal was not of sufficient detail to provide a "stand alone" justification to support NRC review based on the following: 1) the submittal was not clear as to whether your 10 CFR 50.54(q) review concluded that any of the proposed changes would result in a decrease in the effectiveness of the emergency plan, and 2) the submittal did not include a detailed description of each proposed change, an evaluation of each proposed change against the prior NRC-approved emergency plan section to which the change was being made, and a statement of whether each proposed change would or would not decrease the effectiveness of the NRC-approved emergency plan. Therefore, we informed your staff of our plans to not accept your application for review.

As a result of our January 7, 2004, discussions with your staff, by letter dated January 16, 2004, you requested to withdraw the changes proposed in your November 25, 2003, letter.

Accordingly, TAC Nos. MC1410 and MC1411 are closed.

Sincerely,

/RA/

Deirdre W. Spaulding, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: See next page

ML040200809 Point Beach Nuclear Plant, Units 1 and 2 cc:

Jonathan Rogoff, Esquire Mr. Jeffery Kitsembel Vice President, Counsel & Secretary Electric Division Nuclear Management Company, LLC Public Service Commission of Wisconsin 700 First Street P.O. Box 7854 Hudson, WI 54016 Madison, WI 53707-7854 Mr. Richard R. Grigg Nuclear Asset Manager President and Chief Operating Officer Wisconsin Electric Power Company Wisconsin Electric Power Company 231 West Michigan Street 231 West Michigan Street Milwaukee, WI 53201 Milwaukee, WI 53201 John Paul Cowan Manager, Regulatory Affairs Executive Vice President & Chief Nuclear Point Beach Nuclear Plant Officer Nuclear Management Company, LLC Nuclear Management Company, LLC 6610 Nuclear Road 700 First Street Two Rivers, WI 54241 Hudson, WI 54016 Mr. Ken Duveneck Douglas E. Cooper Town Chairman Senior Vice President - Group Operations Town of Two Creeks Palisades Nuclear Plant 13017 State Highway 42 Nuclear Management Company, LLC Mishicot, WI 54228 27780 Blue Star Memorial Highway Covert, MI 49043 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspectors Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 November 2003