P Duke OrPowere A Duke Energy Company D.M. JAMIL Vice President Duke Power Catawba Nuclear Station 4800 Concord Rd. I CN01 VP York, SC 29745-9635 January 7, 2004 803 831 4251 803 831 3221 fax U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555
Subject:
Catawba Nuclear Station, Unit 1 Docket No. 50-413 Errata: Steam Generator Tube Inspection Report Unit 1 End of Core (EOC) 14 By letter dated December 23, 2003, Catawba Nuclear Station submitted its Steam Generator Tube Inspection Report for Unit 1 EOC 14 pursuant to Technical Specifications 5.6.8.a. and 5.6.8.b. Your staff identified an error contained in the cover letter; specifically, the unit and docket numbers were incorrect. The submittal should have referenced Unit 1, Docket No. 50-413. Accordingly, please replace the effected cover letter dated December 23, 2003 with the attached cover letter dated January 7, 2004 that accurately reflects Unit 1 information.
Thank you for pointing out this error. If you have any questions, please contact Kay Nicholson at 803-831-3237.
Sincerely, Dhiaa M. Jamil
\\ken xc:
L. A. Reyes U. S. Nuclear Regulatory Commission Regional Administrator, Region II Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, GA 30333 S. E. Peters (addressee only)
U. S Nuclear Regulatory Commission Project Manager Mail Stop 0-8 G9 Washington, D. C. 20555-0001 I
I E. F. Guthrie, Senior Resident Inspector U. S. Nuclear Regulatory Commission Catawba Nuclear Station - CNOINC www. duke-energy. corn
Duke
- rPower.
A Duke Energy Company D.M. JAMIL Vice President Duke Power Catawba Nuclear Station 4800 Concord Rd. / CN01 VP York, SC 29745-9635 January 7, 2004 803 831 4251 803 831 3221 fax U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555
Subject:
Catawba Nuclear Station, Unit 1 Docket No. 50413 Steam Generator Tube Inspection Report Unit 1 End of Core (EOC) 14 Catawba Nuclear Station (CNS) Technical Specifications 5.6.8.a. and 5.6.8.b., requires the number of tubes plugged in each steam generator to be reported within 15 days and requires the complete results of the Steam Generator Tube Surveillance Program to be reported within 12 months, respectively, following the completion of the program.
The following provides the quantity of tubes inspected and tubes removed from service by plugging:
B C
D Tubes Inspected Full Length 6625 0
0 6629 Tubes Inspected Partial Length 0
6663 6626 0
Tubes Removed by Plugging 0
0 7
0 Attachments 1, 2, 3, and 4 identify tube imperfections in steam generators A, B, C, and D respectively. The location and size of the imperfections are also provided.
Attachments 5, 6, 7, and 8 identify tubes removed from service by plugging in steam generators A, B, C, and D respectively. The tubes to be plugged are also provided.
www.duke-energy.com
U. S. Nuclear Regulatory Commission Steam Generator Tube Inspection Report for 1 EOC 14 January 7, 2004 Page 2 Any questions concerning this submittal may be directed to Kay Nicholson at 803-831-3237.
Sincerely, Dhiaa M. Jamil
\\ken xc:
L. A. Reyes U. S. Nuclear Regulatory Commission Regional Administrator, Region II Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, GA 30333 S. E. Peters (addressee only)
U. S Nuclear Regulatory Commission Project Manager Mail Stop 0-8 G9 Washington, D. C. 20555-0001 E. F. Guthrie, Senior Resident Inspector U. S. Nuclear Regulatory Commission Catawba Nuclear Station - CNOINC