January 12, 2004 Mr. Robert Christman, - Superintendent of Operations Training Entergy Nuclear Northeast Indian Point Nuclear Power Plant, Unit 3 Training Department P. O. Box 308 295 Broadway, Suite 3 Buchanan NY 10511
Dear Mr. Christman:
The purpose of this letter is to inform you of the individual examination results for your applicants on the initial written examination conducted on December 11, 2003, and the operating tests administered December 8 -10, 2003 at your facility. This meets the intent of section E.1 of the Examiner Standards (ES 501) in NUREG 1021. Four individuals were administered the examination and three passed. This information is considered to be "proprietary" in accordance with 10 CFR 2.790 and it supplements the information contained in the related examination report for your facility which will be issued shortly. is the completed ES-501-2, Power Plant Licensing Examination Results Summary, and is a summary of overall examination results. contains the individual results ES-303-1 and 303-2, Operator License Examination Report, for the applicants. Contained therein are the deficiencies noted for each applicant. In accordance with your Systems Approach to Training (SAT) Program, we expect that you will review these results and provide appropriate remedial training for the individual independent of the overall pass status. The applicant has authorized the release of this information to your facility by signing Block 19A of NRC Form 398. is a copy of the licenses.
Thank you for your cooperation in this matter. Please refer any questions you have to me at (610) 337-5183.
Sincerely,
/RA/
Richard J. Conte, Chief Operational Safety Branch Division of Reactor Safety Docket No. 50-286 License No. DPR-64
Mr. Robert Christman
Enclosures:
- 1. ES-501-2, Power Plant Licensing Examination Results Summary
- 2. ES-303-1 and 303-2, Individual Examination Results
- 3. Licenses cc w/licenses:
F. R. Dacimo, Site Vice President
Mr. Robert Christman Distribution: w/o enclosures:
Master Exam File DOCUMENT NAME: G:\\OSB\\Blamey/IP3ExamDec2003/ExamNotificationLtr.wpd ADAMS PACKAGE: ML031480347 To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy
!
!
" !
!
!
#$%