Category:Inspection Plan
MONTHYEARIR 05000298/20230052023-08-21021 August 2023 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2023005)- Mid Cycle Letter ML23214A2742023-08-0303 August 2023 Nuclear Station - Notification of Inspection (NRC Inspection Report 05000298/2023004) and Request for Information ML23173A0862023-06-26026 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000298/2023401 IR 05000298/20220062023-03-0101 March 2023 Annual Assessment Letter for Cooper Nuclear Station Report 05000298/2022006 IR 05000298/20220052022-08-18018 August 2022 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298 2022005) ML22179A3152022-06-28028 June 2022 Notification of Post-Approval Site Inspection for License Renewal (Phase 4) (NRC Inspection Report 05000298/2022011) and Request for Information IR 05000298/20210062022-03-0202 March 2022 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2021006) ML21305B8012021-11-0202 November 2021 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection 05000298/2022001 and Request for Information IR 05000298/20210052021-09-0101 September 2021 CNS Mid-Cycle Inspection Plan Transmittal Letter for Cooper Nuclear Station (Report 05000298/2021005) ML21217A1182021-08-0505 August 2021 Notification of Inspection (NRC Inspection Report 05000298/2021004) and Request for Information ML21083A2832021-03-24024 March 2021 Ti 2515/194 Inspection Documentation Request ML20315A3922020-11-10010 November 2020 Email 11-10-2020 - Cooper EP Prog Insp RFI IR 05000298/20200052020-09-0101 September 2020 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2020005) IR 05000298/20190062020-03-0303 March 2020 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2019006) IR 05000298/20190052019-08-30030 August 2019 Updated Inspection Plan for Cooper Nuclear Station - Report 05000298/2019005 IR 05000298/20180062019-03-0404 March 2019 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2018006) IR 05000298/20180052018-08-31031 August 2018 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2018005) IR 05000298/20170062018-03-0101 March 2018 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2017006) ML18023A1102018-01-23023 January 2018 CNS - Notification of NRC Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans (05000298/2018010) and Request IR 05000298/20170052017-08-28028 August 2017 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2017005) IR 05000298/20160062017-03-0101 March 2017 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2016006) IR 05000298/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Cooper Nuclear Station (Report 05000298/2016005) IR 05000298/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Cooper Nuclear Station (NRC Physical Security Inspection Report Number 05000298/2016401) ML16242A3292016-08-31031 August 2016 Mid-Cycle Assessment Letter for Cooper Nuclear Station (Report 05000298/2016005) IR 05000298/20150062016-03-0202 March 2016 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2015006) IR 05000298/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Cooper Nuclear Station (Report 05000298/2015005) IR 05000298/20154012015-09-0101 September 2015 Non-Public Security Inspection Plan for Cooper Nuclear Station (NRC Physical Security Inspection Report Number 05000298/2015401) ML15183A3602015-07-0202 July 2015 Notification of Inspection (NRC Inspection Report 05000298/2015003 and Request for Information ML14364A1532014-12-30030 December 2014 Notification of NRC Triennial Heat Sink Performance IR 05000298/2015001 and Request for Information IR 05000298/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Cooper Nuclear Station (NRC Physical Security Inspection Report Number 05000298/2014402) IR 05000298/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Cooper Nuclear Station (Report 05000298/2014006) IR 05000298/20130012014-03-0404 March 2014 Annual Assessment Letter for the Cooper Nuclear Station (Report 05000298/2013001) IR 05000298/20130062013-09-0303 September 2013 Mid-cycle Assessment Letter for Cooper Nuclear Station (Report 05000298-13-006) IR 05000298/20128012013-03-0404 March 2013 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2012801) IR 05000298/20120062012-09-0404 September 2012 Mid-Cycle Assessment Letter for Cooper Nuclear Station (Report 05000298/2012006) ML12243A4372012-09-0404 September 2012 Mid-Cycle Assessment Letter for Cooper Nuclear Station (Report 05000298-12-006) IR 05000298/20120012012-03-0505 March 2012 Annual Assessment Letter for Cooper Nuclear Station (Report Number 05000298/2012001) ML1124306512011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - Cooper Nuclear Station IR 05000298/20110012011-03-0404 March 2011 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298-11-001) ML1024305762010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Cooper Nuclear Station ML0906301572009-03-0404 March 2009 Annual Assessment Letter and Inspection Plan - 2009 - Cooper Nuclear Station ML0824606182008-09-0202 September 2008 2008 Midcycle Assessment Letter Cooper Nuclear Station IR 05000298/20080012008-03-0303 March 2008 Annual Assessment Letter - Cooper Nuclear Station End of Cycle 03-03-2008, (Inspection Report 05000298-08-001) ML0724309262007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - Cooper IR 05000298/20070012007-03-0202 March 2007 Annual Assessment Letter - Cooper Nuclear Station (NRC Inspection Report 05000298-07-001) ML0624306492006-08-31031 August 2006 Midcycle Performance Review and Inspection Plan - Cooper Nuclear Station IR 05000298/20060012006-03-0202 March 2006 Annual Assessment Letter - Cooper Nuclear Station (NRC Inspection Report 05000298-06-001) ML0524300922005-08-30030 August 2005 Midcycle 2005 Performance Review and Inspection Plan - Cooper Nuclear Station IR 05000298/20050012005-03-0202 March 2005 Annual Assessment Letter - Cooper Nuclear Station (IR 05000298-05-001) ML0602502552004-08-30030 August 2004 Midcycle Performance Review and Inspection Plan 8/30/04 2023-08-03
[Table view] Category:Letter
MONTHYEARML23334A2012024-01-0303 January 2024 Issuance of Amendment No. 274 Revision to Technical Specifications to Adopt TSTF-551, Revision 3, Revise Secondary Containment Surveillance Requirements ML23311A1122023-11-0909 November 2023 Project Manager Assignment ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000298/20230032023-11-0202 November 2023 Integrated Inspection Report 05000298/2023003 IR 05000298/20234012023-11-0101 November 2023 Cyber Security Report 05000298/2023401 Public ML23264A8052023-10-11011 October 2023 Issuance of Amendment No. 273 Revision to Technical Specifications to Adopt TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23233A1882023-09-0505 September 2023 Regulatory Audit Plan in Support of Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20243012023-09-0101 September 2023 Notification of NRC Initial Operator Licensing Examination 05000298/2024301 IR 05000298/20230052023-08-21021 August 2023 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2023005)- Mid Cycle Letter IR 05000298/20230022023-08-0808 August 2023 Integrated Inspection Report 05000298/2023002 IR 05000298/20234022023-08-0303 August 2023 NRC Security Inspection Report 05000298/2023402 ML23214A2742023-08-0303 August 2023 Nuclear Station - Notification of Inspection (NRC Inspection Report 05000298/2023004) and Request for Information IR 05000298/20234202023-08-0101 August 2023 Security Baseline Inspection Report 05000298/2023420 ML23173A0862023-06-26026 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000298/2023401 IR 05000298/20230102023-05-17017 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000298/2023010 IR 05000298/20234032023-05-0404 May 2023 Security Baseline Inspection Report 05000298/2023403 ML23129A2822023-04-20020 April 2023 Submittal of Revision 31 to Updated Safety Analysis Report ML23102A0282023-04-19019 April 2023 U.S. Nuclear Regulatory Commission Presentation at the May 8, 2023, Brownville Village Meeting IR 05000298/20230012023-04-17017 April 2023 Integrated Inspection Report 05000298/2023001 ML23060A1582023-03-0808 March 2023 Design Basis Assurance Inspection (Programs) Inspection Report 05000298/2023001 IR 05000298/20220062023-03-0101 March 2023 Annual Assessment Letter for Cooper Nuclear Station Report 05000298/2022006 ML23041A1622023-02-10010 February 2023 Licensed Operator Positive Fitness-for-Duty Test Request for Additional Information IR 05000298/20220042023-01-30030 January 2023 Integrated Inspection Report 05000298/2022004 IR 05000298/20220112022-12-23023 December 2022 License Renewal Phase 4 Inspection Report 05000298/2022011 ML22286A2072022-11-30030 November 2022 Issuance of Amendment No. 272 Revision to Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements IR 05000298/20220032022-10-27027 October 2022 Integrated Inspection Report 05000298/2022003 ML22304A0052022-10-26026 October 2022 Surveillance Capsule Location (Re-insertion Into the Reactor Vessel) IR 05000298/20223022022-10-20020 October 2022 NRC Initial Operator Licensing Examination Approval 05000298/2022302 ML22276A1562022-10-0505 October 2022 Notification of Commercial Grade Dedication Inspection 05000298/2023011 and Request for Information IR 05000298/20224022022-09-29029 September 2022 NRC Security Inspection Report 05000298/2022402 (Full Report) IR 05000298/20220052022-08-18018 August 2022 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298 2022005) IR 05000298/20223012022-08-10010 August 2022 NRC Examination Report 05000298/2022301 IR 05000298/20220022022-07-28028 July 2022 Integrated Inspection Report 05000298/2022002 ML22200A2772022-07-21021 July 2022 Correction to Proposed Inservice Testing Alternative RS-01, Revision of Error in Safety Evaluation ML22152A1232022-07-18018 July 2022 Issuance of Amendment No. 271 Request for Exception from Certain Primary Containment Leak Rate Testing Requirements IR 05000298/20224012022-06-29029 June 2022 Security Baseline Inspection Report 05000298/2022401 IR 05000298/20224032022-06-28028 June 2022 Security Baseline Inspection Report 05000298/2022403 IR 05000298/20220102022-06-16016 June 2022 Triennial Fire Protection Inspection Report 05000298/2022010 ML22140A1612022-06-0808 June 2022 Proposed Inservice Inspection Alternative RR5-01 Revision 1 ML22147A1122022-06-0101 June 2022 NRC Initial Operator Licensing Examination Approval 05000298/2022301 ML22111A1382022-05-13013 May 2022 Proposed Inservice Testing Alternative RS-01, Revision 0 IR 05000298/20220012022-04-28028 April 2022 Integrated Inspection Report 05000298/2022001 IR 05000298/20224042022-04-13013 April 2022 Material Control and Accounting Program Inspection Report 05000298/2022404 - (Public) ML22084A6032022-04-0404 April 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection 05000298/2022002 and Request for Information ML22090A2892022-04-0101 April 2022 John Larson'S Invitation to Participate in the 8th Nuclear Regulatory Commission'S Workshop on Vendor Oversight ML22045A0012022-03-31031 March 2022 Proposed Inservice Inspection Alternative RI5- 02 Revision 3 IR 05000298/20210062022-03-0202 March 2022 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2021006) IR 05000298/20210042022-01-24024 January 2022 Integrated Inspection Report 05000298/2021004 ML21350A0582021-12-21021 December 2021 Withdrawal of an Amendment Request ML21340A2362021-12-20020 December 2021 Issuance of Amendment No. 270 Adoption of Technical Specifications Task Force Traveler TSTF-582, Revision 0, RPV WIC Enhancements 2024-01-03
[Table view] |
Text
November 17, 2003 Clay C. Warren, Chief Nuclear Officer Nebraska Public Power District P.O. Box 98 Brownville, NE 68321
Subject:
REVISED INSPECTION SCHEDULE ARISING FROM REORGANIZATION OF THE NRC REGION IV DIVISION OF REACTOR SAFETY
Dear Mr. Warren:
The U.S. Nuclear Regulatory Commission (NRC), Region IV, has reorganized its Division of Reactor Safety (DRS) effective December 28, 2003.
The Divisions inspection duties were formerly divided among three branches:
Operations Branch Plant Support Branch Engineering & Maintenance Branch
- Operator licensing # Security # Safety System Design and
- Identification and # Radiological Performance Capability Resolution of Controls # Permanent Plant Problems (PI&R) # Emergency Modifications Preparedness # Inservice Inspection Activities
- Evaluation of Changes, Tests or Experiments
- Fire Protection
- Heat Sink Performance
- Maintenance Effectiveness Beginning in January, 2004, there will be four DRS inspection branches with inspection responsibilities as follows:
Operations Branch Performance Evaluation Branch
- Initial Operator Licensing # PI&R Lead Responsibility
- Operator Requalification Program # Fire Protection
- Emergency Preparedness # Heat Sink Performance
- PI&R Support # Maintenance Effectiveness
Nebraska Public Power District # PI&R Support Engineering Branch Plant Support Branch
- Safety System Design and # Security Performance Capability # Radiological Controls
- Permanent Plant Modifications # PI&R Support
- Inservice Inspection Activities
- Evaluation of Changes, Tests or Experiments The reorganization of DRS and the reallocation of inspection duties required changes to the 2004 calendar year inspection schedule. The new DRS inspection schedule for your plant is attached.
Sincerely,
/RA/
Dwight D. Chamberlain, Director Division of Reactor Safety
Enclosure:
as stated Docket: 50-298 License: DPR-46 cc w/enclosure:
Site Vice President Nebraska Public Power District P.O. Box 98 Brownville, NE 68321 John R. McPhail, General Counsel Nebraska Public Power District P.O. Box 499 Columbus, NE 68602-0499 P. V. Fleming, Licensing Manager Nebraska Public Power District P.O. Box 98 Brownville, NE 68321 Michael J. Linder, Director Nebraska Department of Environmental Quality P.O. Box 98922 Lincoln, NE 68509-8922
Nebraska Public Power District Chairman Nemaha County Board of Commissioners Nemaha County Courthouse 1824 N Street Auburn, NE 68305 Sue Semerena, Section Administrator Nebraska Health and Human Services System Division of Public Health Assurance Consumer Services Section 301 Centennial Mall, South P.O. Box 95007 Lincoln, NE 68509-5007 Ronald A. Kucera, Deputy Director for Public Policy Department of Natural Resources 205 Jefferson Street Jefferson City, MO 65101 Jerry Uhlmann, Director State Emergency Management Agency P.O. Box 116 Jefferson City, MO 65102-0116 Chief, Radiation and Asbestos Control Section Kansas Department of Health and Environment Bureau of Air and Radiation 1000 SW Jackson, Suite 310 Topeka, KS 66612-1366 Daniel K. McGhee Bureau of Radiological Health Iowa Department of Public Health 401 SW 7th Street, Suite D Des Moines, IA 50309 William J. Fehrman, President and Chief Executive Officer Nebraska Public Power District 1414 15th Street Columbus, NE 68601
Nebraska Public Power District Electronic distribution by RIV:
Regional Administrator (BSM1)
DRP Director (ATH)
Acting DRS Director (DDC)
Senior Resident Inspector (SCS)
Branch Chief, DRP/C (KMK)
Senior Project Engineer, DRP/C (WCW)
Staff Chief, DRP/TSS (PHH)
RITS Coordinator (NBH)
Jim Isom, Pilot Plant Program (JAI)
RidsNrrDipmLipb ADAMS: G Yes G No Initials: ______
G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive C:EMB C:OB C:PSB C:PBC D:DRS CSMarschall/lmb ATGody TWPruett KKennedy DDChamberlain
/RA/ /RA/ /RA/ /RA/ /RA/
11/13/03 11/10/03 11/13/03 11/13/03 11/17/03 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax