Tech Spec Pages for Amendments 191 and 182 on Auxiliary Feedwater Pumps Surveillance Frequency
ML033370044
Person / Time
Site: San Onofre  
(NPF-010, NPF-015)
Issue date: 11/25/2003
From:
NRC/NRR/DLPM
To:
References
TAC MB6938, TAC MB6939
Download: ML033370044 (2)


Text

AFW System 3.7.5 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.7.5.1 Verify each AFW manual, power operated, and 31 days automatic valve in each water flow path and in both steam supply flow paths to the steam turbine driven pump, that is.not locked, sealed, or otherwise secured in position, is in the correct position.

SR 3.7.5.2


NOTE--------------------

Not required to be performed for the turbine driven AFW pump until 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> after reaching 800 psig in the steam generators.

Verify the developed head of each AFW pump In accordance at the flow test point is greater than or with the equal to the required developed head.

Inservice Testing Program SR 3.7.5.3


NOTE--------------------

Not required to be performed for the turbine driven AFW pump until 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> after reaching 800 psig in the steam generators.

Verify each AFW automatic valve actuates to 24 months the correct position on an actual or simulated actuation signal, except valves HV-8200 and HV-8201.

(continued)

SAN ONOFRE--UNIT 2 3.i-14 Amendment No. 277147,191

AFW System 3.7.5 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.7.5.1 Verify each AFW manual, power operated, and 31 days automatic valve in each water flow path and in both steam supply flow paths to the steam turbine driven pump, that is not locked, sealed, or otherwise secured in position, is in the correct position.

SR 3.7.5.2 NOTE--------------------

Not required to be performed for the turbine driven AFW pump until 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> after reaching 800 psig in the steam generators.

Verify the developed head of each AFW pump In accordance at the flow test point is greater than or with the equal to the required developed head.

Inservice Testing Program SR 3.7.5.3


NOTE--------------------

Not required to be performed for.the turbine driven AFW pump until 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> after reaching 800 psig in the steam generators.

Verify each AFW automatic valve actuates to 24 months the correct position on an actual or simulated actuation signal, except valves HV-8200 and HV-8201.

(continued)

SAN ONOFRE--UNIT 3 3.7-14 Amendment No. 467139,182