Additional Information Supporting the Request for License Amendment Regarding Reactor Vessel Specimen Removal Schedule
ML033180515
Person / Time
Site: Oyster Creek
Issue date: 11/03/2003
From: Gallagher M
AmerGen Energy Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
2130-03-20277
Download: ML033180515 (3)


Text

AmerGen SM AmerGen Energy Company, LLC www.exeloncorp.com An Exelon/British Energy Company 200 Exelon Way Suite 345 Kennett Square, PA 19348 2130-03-20277 November 3, 2003 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Oyster Creek Generating Station Facility Operating License No. DPR-16 NRC Docket No. 50-219

Subject:

Additional Information Supporting the Request for License Amendment Regarding Reactor Vessel Specimen Removal Schedule

References:

(1)

Letter from M. P. Gallagher (Exelon Generation Company, LLC) to U. S. NRC, "Request for License Amendment Regarding Reactor Vessel Specimen Removal Schedule," dated December 20, 2002 (2)

Letter from M. P. Gallagher (AmerGen Energy Company, LLC) to U. S. NRC, "Additional Information Supporting the Request for License Amendment Regarding Reactor Vessel Specimen Removal Schedule," dated September 10, 2003 In Reference 1, Exelon Generation Company, LLC (EGC) and AmerGen Energy Company, LLC (AmerGen) requested changes to the Updated Final Safety Analysis Reports (UFSARs) for the Clinton Power Station (CPS), Unit 1, the Dresden Nuclear Power Station (DNPS), Units 2 and 3, the LaSalle County Station (LSCS), Units 1 and 2, the Limerick Generating Station (LGS),

Units 1 and 2, the Oyster Creek Generating Station (Oyster Creek), the Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3, and the Quad Cities Nuclear Power Station (QCNPS),

Units 1 and 2. Additionally, EGC proposed changes to the Technical Specifications (TS) for LGS, Units 1 and 2. The requested changes would remove the current facility reactor material specimen surveillance schedules from the UFSARs and specify that these facilities will participate in an integrated surveillance program (ISP) developed by the Boiling Water Reactor Vessel and Internals Project (BWRVIP). For LGS, the proposed changes would also remove the current facility reactor material specimen surveillance schedule from the TS.

In Reference 2, EGC and AmerGen submitted additional information regarding the proposed changes for Oyster Creek. In a teleconference between Mr. T. Loomis of EGC and the NRC, the NRC requested that AmerGen submit revised UFSAR pages for Oyster Creek that document the information provided in Reference 2. The attachment to this letter provides the requested pages. The UFSAR pages provided in the attachment affect UFSAR Sections 4.3.2.8 and 4.3.5. These pages supplement the UFSAR pages provided in Reference 1, which affect UFSAR Sections 5.3.1.3 and 5.3.4.

AdDI

November 3, 2003 U.S. Nuclear Regulatory Commission Page 2 Should you have any questions related to this request, please contact Mr. Allan R. Haeger at (630) 657-2807.

I declare under penalty of perjury that the foregoing is true and correct.

Respectfully, Executed on Michael P. Gallagher Director of Licensing and Regulatory Affairs cc:

H. J. Miller, USNRC, Regional Administrator, Region I R. J. Summers, USNRC, Senior Resident Inspector - OCGS P. S. Tam, USNRC, Project Manager - NRR K. Tosch, New Jersey Department of Environmental Protection Mayor of Lacey Township, New Jersey

Insert for Section 4.3.2.8 In Reference 22, as part of the transition to the BWR Vessel and Internals Project Integrated Surveillance Program, Oyster Creek committed to perform a reactor vessel fluence evaluation using a method in accordance with Regulatory Guide (RG) 1.190, TCalculational and Dosimetry Methods for Determining Pressure Vessel Neutron Fluence," dated March 1, 2001. All future evaluations of reactor vessel fluence will be performed using a method in accordance with RG 1.190.

Insert for Section 4.3.5 (22)

Letter from M. P. Gallagher (AmerGen Energy Company, LLC) to U. S. NRC, "Additional Information Supporting the Request for License Amendment Regarding Reactor Vessel Specimen Removal Schedule," dated September 10, 2003