CPSES-200302398, Unit 2, Seventh Refueling Outage (2RF07) Steam Generator Inservice Inspection Tube Plugging Special Report No. 2-SR-03-001-00

From kanterella
(Redirected from ML033180430)
Jump to navigation Jump to search
Unit 2, Seventh Refueling Outage (2RF07) Steam Generator Inservice Inspection Tube Plugging Special Report No. 2-SR-03-001-00
ML033180430
Person / Time
Site: Comanche Peak 
Issue date: 11/06/2003
From: Walker R
TXU Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
10010.1, CPSES-200302398, RP-39, TXX-03189
Download: ML033180430 (3)


Text

Nth TXU

,"4"49 TXU Energy Comanche Peak Steam Electric Station P.O. Box 1002 EO1)

Glen Rose,TX 76043 Tel: 254 897 5209 Fax: 254 897 6652 mike.blevins@txu.com Mike Blevins Senior Vice President & Principal Nuclear Officer Ref: 10CFR50.55a CPSES-200302398 Log# TXX-03189 File#

10010.1 RP-39 November 6, 2003 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) -UNIT 2 DOCKET NO. 50-446 UNIT 2, SEVENTH REFUELING OUTAGE (2RF07)

STEAM GENERATOR INSERVICE INSPECTION TUBE PLUGGING SPECIAL REPORT NO. 2-SR-03-001-00 Gentlemen:

Attached is a 15-day special report submitted pursuant to CPSES Technical Specification 5.6.10a. If there are any questions or if additional information is needed, please contact Mr. Bob Kidwell at (254) 897-5310.

This communication contains no new licensing basis commitments regarding CPSES Units 1 and 2.

A1q A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway Comanche Peak Diablo Canyon

  • Palo Verde
  • Wolf Creek

fTXU TXX-03 189 Page 2 of 2 Sincerely, TXU Generation Company LP By:

TXU Generation Management Company LLC, Its General Partner M. R. Blevins Senior Vice President and Principal Nuclear Officer By:

OICA 6i t/>

Roget. Walker Regulatory Affairs Manager RJK/rjk Attachment cc -

B. Mallett, Region IV W. D. Johnson, Region IV M. C. Thadani, NRR Resident Inspectors, CPSES l

Attachment to TXX-03 189 Page 1 of 1 TXU ENERGY COMANCHE PEAK STEAM ELECTRIC STATION - UNIT 2 SPECIAL REPORT NO. 2-SR-03-001-00 UNIT 2, SEVENTH REFUELING OUTAGE (2RF07)

STEAM GENERATOR INSERVICE INSPECTION TUBE PLUGGING This letter provides the Inservice Inspection (ISI) Special Report on the steam generator tube ISI for Comanche Peak Steam Electric Station's seventh refueling outage (2RF07) on Unit 2. This report is being provided to you pursuant to CPSES Technical Specification 5.6.1Oa.

Steam Generators 1 and 4 were inspected during 2RF07. The examinations were completed on October 24, 2003. The number of tubes plugged during this outage in each steam generator is as follows:

CPSES Unit 2 Steam Generator No. 1:

Three (3)

CPSES Unit 2 Steam Generator No. 4:

One (1)

Additional details on the plugged tubes and inspection effort will be provided in the 12-month report pursuant to CPSES Technical Specification 5.6.10b.