Text
Quality Assurance Program Description Consolidated Program for All Nuclear Facilities
MWA,4201. 0 0 Upwininiol 79 :
Purpose
- Discuss plans for a consolidated QA Program
- Obtain any feedback or' lessons learned from other submittals !
Program Applicability
- Have a Quality Assurance Program that will apply to multiple nuclear facilities
- Operation and decommissioning of Surry, North Anna, and Millstone and any associated ISFSI
- New acquisitions
- New construction
New QAPD
- Based on NQA-1-1994
- Upgrade to common commitments where practicable
- Include new design and construction activities
Program Scope
- All phases of the life of a nuclear facility
- Design
- Construction
- Operation
- Decommissioning
Applicable Facilities
- Nuclear Power Stations
- Independent Spent Fuel Storage Installations
Applicable Activities
- Those governed by 10 CFR 50, App. B
- Those requiring QA measures not governed by App. B
- Radioactive Material Shipping
- Security
- Other Programs
tro.granaForm-at \
- Follows the 18 criteria of 10 CFR 50, Appendix B
- Similar to SRP chapters 7.la172and Draft Review Standard RS - Stion 17. 1.1.
- SRP chapter 17.3 used as guidance since it addresses NQA-1 and withdrawal of certain Regulatory Guides not addressed in 17.1 and 17.2 acceptance criteria
Program Format
- Describes the high-level Quality Assurance program
- Will not describe details that are already contained within standards
AirDomiion Major Changes
- Transition to NQA-1-1994
- Reduce the use of multiple standards by incorporating administrative controls described in ANSI N1 8.7/ANS 3.2 that are not already included in NQA-1
- Generic organizational description
1\ajor Changes
- Common alternatives Where feasible
- Proposed QC program fpr North Anna and Surry currently in NRC review
- Independent review program that addresses the ISEG functions X
Major Changes
- New items not covered by the Operating QA Program
- Siting for new facilities, and any limited work activities covered under the early site permit
Areas to Resolve
- Level of detail required in describing the organizational structure
- Improved Technical Specifications
- Administrative Letter 95-06
- Generic descriptions allowed by 50.54(a)
- Comparison to other utilities' QAPD
Owl'r Bma~ainon Areas to Resolve Different standards for qualification of personnel
- Technical Specifications differ between sites
- Intend to refer to the applicable Technical Specifications, then to QAPD where not stated in Technical Specifications
- Otherwise this could require as many as nine TS changes
Submittal to NRC
- Submit as a new program
- Covers activities not addressed by the current existing Operational QA programs
- Change to the NQA- 1 standards
- Submittal in November 2003
Submittal to NTC Request Common Review
- One Project Manager coordination
- One set of reviewers
- One Quality Assurance Program for multiple dockets