Clarification Regarding Relief Request Concerning risk-informed Inservice Inspection
ML033040149
Person / Time
Site: Turkey Point NextEra Energy icon.png
Issue date: 10/30/2003
From: Howe A
NRC/NRR/DLPM/LPD2
To: Stall J
Florida Power & Light Co
Brown E, NRR/DLPM, 415-2315
References
TAC MB5551
Download: ML033040149 (7)


Text

October 30, 2003 Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

TURKEY POINT NUCLEAR PLANT, UNIT 4 - CLARIFICATION REGARDING RELIEF REQUEST CONCERNING RISK-INFORMED INSERVICE INSPECTION (TAC NO. MB5551)

Dear Mr. Stall:

By a letter dated July 8, 2002, as supplemented by letters dated January 15, 2003, February 13, 2003, and May 14, 2003, Florida Power and Light Company (FPL) submitted a relief request, Risk-informed Inservice Inspection Program, for implementation during the third inspection period of the 10-year inspection interval of Turkey Point Plant, Unit 4. The proposed Risk-Informed Inservice Inspection (RI-ISI) program, developed in accordance with Westinghouse Owners Group Topical Report WCAP-14572, Revision 1-NP-A, was presented as an alternative to the current American Society of Mechanical Engineers Code,Section XI, Inservice Inspection Program, for Class 1 piping at Turkey Point Unit 4. The U.S. Nuclear Regulatory Commission (NRC) staff reviewed and approved your request for relief in a letter dated August 1, 2003 [ADAMS Accession No. ML032130558].

Section 3.3 of the NRC staffs evaluation states that as a minimum, 18 examinations will be performed during the third period of the third interval of the B-F and B-J risk informed population. By letter dated October, 13, 2003, the licensee provided a clarification to its implementation plan. The licensee stated that FPL will perform 26 examinations during the third period of the third interval as follows:

- 13 ultrasonic examinations and 11 VT-2 visual examination segments will be performed during the Turkey Point Unit 4 Fall 2003 Refueling Outage.

- The remaining two ultrasonic examinations will be performed as part of the allowed extension of the third period of the third 10-year interval, during the Unit 4 Spring 2005 Refueling Outage.

Mr. J. A. Stall The NRC staff finds the licensees implementation acceptable, since all RI-ISI risk significant segments will have received examination during the licensees third inspection interval.

Sincerely,

/RA/

Allen G. Howe, Chief, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-251 cc: See next page

ML033040149 OFFICE PDII-2/PM PDII-2/LA EMCB/SC SPSB/SC OGC(NLO) PDII-2/SC NAME EBrown BClayton TChan MRubin RHoefling AHowe DATE 10/22/03 10/22/03 10/24/03 10/27/03 10/29/03 10/30/03 Mr. J. A. Stall TURKEY POINT PLANT Florida Power and Light Company cc:

M. S. Ross, Attorney Attorney General Florida Power & Light Company Department of Legal Affairs P.O. Box 14000 The Capitol Juno Beach, FL 33408-0420 Tallahassee, Florida 32304 T. O. Jones, Site Vice President Plant General Manager Turkey Point Nuclear Plant Turkey Point Nuclear Plant Florida Power and Light Company Florida Power and Light Company 9760 SW. 344th Street 9760 SW. 344th Street Florida City, FL 33035 Florida City, FL 33035 County Manager Walter Parker Miami-Dade County Licensing Manager 111 NW 1 Street, 29th Floor Turkey Point Nuclear Plant Miami, Florida 33128 9760 SW 344th Street Florida City, FL 33035 Senior Resident Inspector Turkey Point Nuclear Plant Mr. William Jefferson U.S. Nuclear Regulatory Commission Vice President, Nuclear Operations Support 9762 SW. 344th Street P.O. Box 14000 Florida City, Florida 33035 Juno Beach, FL 33408-0420 Mr. William A. Passetti, Chief Mr. Rajiv S. Kundalkar Department of Health Vice President - Nuclear Engineering Bureau of Radiation Control Florida Power & Light Company 2020 Capital Circle, SE, Bin #C21 P.O. Box 14000 Tallahassee, Florida 32399-1741 Juno Beach, FL 33408-0420 Mr. Craig Fugate, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100