October 28, 2003 Mr. Hank A. Sepp, Manager Regulatory Compliance and Plant Licensing Westinghouse Electric Company P.O. Box 355 Pittsburgh, PA 15230-0355

SUBJECT:

REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE (CAW-03-1609) (TAC NOS. MC0893 AND MC0894)

Dear Mr. Sepp:

By letter dated September 12, 2003, Pacific Gas and Electric Company submitted an affidavit dated March 13, 2003, executed by you, requesting that information in the following document be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.790:

WCAP-11082, Revision 6, "Westinghouse Setpoint Methodology for Protection Systems, Diablo Canyon Units 1 & 2, 24 Month Fuel Cycle Evaluation."

A nonproprietary copy of the document has been placed in the Nuclear Regulatory Commissions (NRCs) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.

The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

(i) The information sought to be withheld from public disclosure is owned and has been held in confidence by Westinghouse.

(ii) The information is of a type customarily held in confidence by Westinghouse and not customarily disclosed to the public.

(a) The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouses competitors without license from Westinghouse constitutes a competitive economic advantage over other companies.

(c) Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.

H. Sepp We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.790 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the document entitled WCAP-11082, Revision 6, "Westinghouse Setpoint Methodology for Protection Systems, Diablo Canyon Units 1 & 2, 24 Month Fuel Cycle Evaluation," marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.790(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at (301) 415-8439.

Sincerely,

/RA/

Girija Shukla, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323 cc: See next page

H. Sepp We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.790 and, on the basis of your statements, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the document entitled WCAP-11082, Revision 6, "Westinghouse Setpoint Methodology for Protection Systems, Diablo Canyon Units 1 & 2, 24 Month Fuel Cycle Evaluation," marked as proprietary, will be withheld from public disclosure pursuant to 10 CFR 2.790(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at (301) 415-8439.

Sincerely,

/RA/

Girija Shukla, Section 2 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-275 DISTRIBUTION:

and 50-323 PUBLIC PDIV-2 Reading cc: See next page RidsNrrDlpmPdiv (HBerkow)

RidsNrrPMGShukla RidsNrrLAEPeyton RidsOgcRp RidsRgn4MailCenter EMarinos ADAMS ACCESSION NO.: ML033020380 NRR-084 OFFICE PDIV-2/PM PDIV-2/LA EEIB OGC Nlo PDIV-2/SC NAME GShukla EPeyton:esp EMarinos BSmith SDembek DATE 10/8/03 10/8/03 10/14/03 10/24/03 10/27/03 DOCUMENT NAME: C:\ORPCheckout\FileNET\ML033020380.wpd OFFICIAL RECORD COPY

Diablo Canyon Power Plant, Units 1 and 2 cc:

NRC Resident Inspector Richard F. Locke, Esq.

Diablo Canyon Power Plant Pacific Gas & Electric Company c/o U.S. Nuclear Regulatory Commission P.O. Box 7442 P.O. Box 369 San Francisco, CA 94120 Avila Beach, CA 93424 Mr. David H. Oatley, Vice President Mr. Pete Wagner and General Manager Sierra Club California Diablo Canyon Power Plant 2650 Maple Avenue P.O. Box 56 Morro Bay, California 93442 Avila Beach, CA 93424 Ms. Nancy Culver City Editor San Luis Obispo The Tribune Mothers for Peace 3825 South Higuera Street P.O. Box 164 P.O. Box 112 Pismo Beach, CA 93448 San Luis Obispo, CA 93406-0112 Chairman Mr. Ed Bailey, Radiation Program Director San Luis Obispo County Board of Radiologic Health Branch Supervisors State Department of Health Services Room 370 P.O. Box 942732 (MS 178)

County Government Center Sacramento, CA 94234-7320 San Luis Obispo, CA 93408 Mr. James D. Boyd, Commissioner Mr. Truman Burns California Energy Commission Mr. Robert Kinosian 1516 Ninth Street (MS 31)

California Public Utilities Commission Sacramento, CA 95814 505 Van Ness, Room 4102 San Francisco, CA 94102 Mr. James R. Becker, Vice President Diablo Canyon Operations Diablo Canyon Independent Safety and Station Director Committee Diablo Canyon Power Plant ATTN: Robert R. Wellington, Esq. P.O. Box 3 Legal Counsel Avila Beach, CA 93424 857 Cass Street, Suite D Monterey, CA 93940 Mr. Gregory M. Rueger Senior Vice President, Generation and Regional Administrator, Region IV Chief Nuclear Officer U.S. Nuclear Regulatory Commission Pacific Gas and Electric Company Harris Tower & Pavillion Diablo Canyon Power Plant 611 Ryan Plaza Drive, Suite 400 P.O. Box 3 Arlington, TX 76011-8064 Avila Beach, CA 93424