NRC FORM 658 U.S. NUCLEAR REGULATORY COMMISSION (91909)

TRANSMITTAL OF MEETING HANDOUT MATERIALS FOR IMMEDIATE PLACEMENT IN THE PUBLIC DOMAIN This form is to be filled out (typed or hand-printed) by the person who announced the meeting (i.e., the person who issued the meeting notice). The completed form, and the attached copy of meeting handout materials, will be sent to the Document Control Desk on the same day of the meeting; under no circumstances will this be done later than the working day after the meeting.

Do not Include proprietary materials.

DATE OF MEETING The attached document(s), which was/were handed out in this meeting, is/are to be placed 0912912003 in the public domain as soon as possible. The minutes of the meeting will be issued in the near future. Following are administrative details regarding this meeting:

Docket Number(s) 50-259,50-260,50-296 Plant/Facility Name Browns Ferry Units 1, 2 & 3 TAC Number(s) (if available)

Reference Meeting Notice 09/10/03 Purpose of Meeting (copy from meeting notice)

To discuss the forthcoming license renewal application for Browns Ferry Nuclear Plant NAME OF PERSON WHO ISSUED MEETING NOTICE TITL Stephen T. Hoffman Sr. Project Manager OFFICE NRR DIVISION DRIP BRANCH RLEP Distribution of this form and attachments:

Docket File/Central File PUBLIC

'g l

NRC FORM 6s8 (-139N)

PRINTED ON RECYCLED PAPER This f(xm was designed using InFornis

Ar'

 j,.1 I.

Tennessee Valley Authority Bro wis. Ferry Nuclear Plant U nits 1,2, and 3

., 1:,..,-.,..,...,:  ...,

License Renewal Application 17 I

r- -r A...

I Agenda Introduction and Background License Renewal Project Status Application Format and Content Application Overview Items From Previous Meetings Closing Remarks Tim Abney Ray Alexander Mike Morrison Gary Adkins Gary Adkins Tim Abney 1

. I Introduction

  • .* Meeting Objectives

> Demonstrate TVA's approach to the preparation of a three-unit license renewal application for Browns Ferry Nuclear Plant (BFN) using the latest standard application format

> Present an overview of the BFN draft application Tim Abney 2

.I Previous TVA/NRC Meeting Highlights

  • A three-unit application is acceptable for BFN
  • The Unit 1 current licensing basis (CLB) provides an adequate basis for an LRA
  • Operating experience for Units 2 and 3 is applicable to Unit 1
  • The BFN application will resemble multi-site applications previously reviewed by the staff
  • Differences between the Unit 1 CLB and the Units 2/3 CLB will be annotated in the application
  • TVA was requested to address the following items in the application:

Description and schedule for the resolution of Unit 1 CLB differences Effect of Unit 1 layup on the application

  • A final inspection of Unit 1 prior to restart may be needed to verify that actions required as a result of the renewal review have been completed TVA will provide notification when the documentation is available on-site
  • All three renewed licenses will be issued at the completion of the renewal review Additional license condition for Ul is acceptable Review may take longer than standard (proposed 1-3 months)

Tim Abney 3

License Renewal Project Status

  • TVA will submit the BFN application in December 2003
    • Draft application prepared (including environmental report)
  • Industry peer review completed
    • Site reviews in progress
  • .* Remaining / Ongoing activities Update the application for recent RAls, SER open item closures, etc.

Implement program to ensure the basis for the renewed licenses is maintained during the renewal term Train site personnel Prepare documentation to support the new process for reviewing license renewal applications Ray Alexander 4

Application Format and Content

  • Application conforms to the May 2003 standard format As modified by the presentation of Unit 1 CLB differences Temporarv differences enclosed in bold border ("boxes")

Permanent differences will be described in the text - currently none have been identified

    • TVA will submit a list of commitments with the application
    • Final and draft interim staff guidance addressed
  • .* Submittal will include a text-searchable copy of the UFSAR linked to the application Boundary drawings provided for mechanical systems Red for 10 CR 54.4(a)(1) and 10 CFR 54.4(a)(3) scoping results Blue for 10 CR 54.4(a)(2) scoping results
  • . 39 aging management programs identified 31 existing programs, 8 new programs 36 GALL programs, 3 plant specific programs Mike Morrison 5

Application Overview

Electrical commodities

  • Appendix B
  • Appendix F Plan and schedule for the resolution of unit 1 CLB differences

Items From Previous Meetings

  • BWR RPV integrity Unit 1 will conform to the BWRVIP at restart Implementation plan provided in Appendix F Unit 1 restart inspection plans will be available for on-site inspection
    • Permanent Unit 1 licensing basis differences will be identified in the application text None have been identified to date
    • NRC asked to be informed of any changes to the plans for the resolution of Unit 1 differences as described in Appendix F after submittal The Staff will be notified as soon as any deviation from this plan becomes known
    • TVA requested to ensure the LRA does not reference out-of-date FSAR information The BFN FSAR contains some historical information which is clearly identified No historical information used to support the application Gary Adkins 7

Closing Remarks

- 11

-I  I -

-.- - -

I - I --- --

I I

I --- I - --1 I

I I

Tim Abney 8