Summary of Meeting Regarding QA for Grand Gulf ESP Application
ML032680514
Person / Time
Site: Grand Gulf, PROJ0720  Entergy icon.png
Issue date: 10/14/2003
From: Stephen Koenick
Division of Regulatory Improvement Programs
To:
Office of Nuclear Reactor Regulation
Koenick S, NRR/DRIP/RNRP, 415-1239
Shared Package
ML032680509 List:
References
FOIA/PA-2005-0280
Download: ML032680514 (8)


Text

October 14, 2003 ORGANIZATION: Entergy Nuclear Potomac Company PROJECT: Early Site Permit (ESP) for the Grand Gulf Site

SUBJECT:

SUMMARY

OF MEETING HELD ON SEPTEMBER 2, 2003, REGARDING QUALITY ASSURANCE FOR THE GRAND GULF ESP APPLICATION On September 2, 2003, a meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Entergy Nuclear Potomac Company (Entergy). The purpose of this meeting was to discuss plans for the NRC staff to conduct inspections of Entergys quality assurance measures used in support of its prospective ESP application for the Grand Gulf Site. The meeting also provided Entergy an opportunity to discuss the quality assurance measures they used in preparation of their application. Meeting handouts (ADAMS Accession No. ML032471714) included: (1) meeting agenda, (2) presentation material by NRC staff, and (3) presentation material by Entergy. In addition, the staff compiled a list of meeting attendees (Attachment 1).

Entergy summarized its ESP project organization and its QA framework, discussed QA measures applied to information supporting the ESP application, and described how information was shared between Entergy and its various contractors. It was noted that Entergy had provided a copy of its Quality Assurance Project Planning Document for Entergy Nuclear Potomac Early Site Permit Project, Grand Gulf Nuclear Station Site by letter dated August 15, 2002, (Accession No. ML031540413).

The NRC staff opened the meeting and discussed its overall approach to review of QA measures for ESP applications including the ESP inspection program and staff guidance for review of ESP quality assurance controls. The staff also discussed information and documents needed to prepare for the QA inspection, which will be conducted soon after receipt of the ESP application. The NRC staff noted that it did conduct a site visit on August 1-2, 2002. The purpose of this visit was to observe activities associated with the gathering of data for demonstrating the suitability of a potential site for placement of a nuclear power plant. The trip report can be found in ADAMS (Accession No. ML022320222).

The NRC maintains an Agencywide Documents Access and Management System (ADAMS),

which provides text and image files of the NRCs public documents. The presentation materials and referenced documents may be accessed through the ADAMS system under the accession numbers mentioned above. If you do not have access to ADAMS or if there are problems in accessing the handouts located in ADAMS, contact the NRC Public Document Room (PDR)

Reference staff at 1-800-397-4209, 301-415-4737, or by e-mail to pdr@nrc.gov.

/RA/

Stephen S. Koenick, Project Manager New Reactors Section New, Research and Test Reactors Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No. 720

Attachment:

As stated cc w/encl: See next page

ML032680514-Meeting Summary ML032471714-Meeting Handouts ML032680509-Pkg.

OFFICE PM:RNRP:NRR SC:IEPB:NRR CIP:Region IV SC:RNRP:NRR NAME SKoenick DThatcher CPaulk LDudes DATE 10/ 8 /2003 10 / 8 /2003 10/8/2003 10/09/2003 Distribution for Meeting Summary dated October 14, 2003 Hard Copy RNRP R/F JLyons SKoenick LDudes E-Mail PUBLIC JDyer/RBorchardt (RidsNrrOd)

JCraig (RidsNrrAdip)

BSheron (RidsNrrAdpt)

TGwynn, RIV RBarrett BBoger DMatthews SKoenick NGilles MScott, RNRP JWilson, RNRP TKenyon MAshley TFoley DThatcher AFernandez, OGC WJohnson, RIV MEl-Zeftawy, ACRS JMoore, OGC RGardner, RIII CPaulk, RIV JBlake, RII KCoyne PPrescott KHeck

GRAND GULF EARLY SITE PERMIT SERVICE LIST Grand Gulf Federal, State and local George A. Zinke Attorney General Manager, Project Management Department of Justice Nuclear Business Development State of Louisiana Entergy Nuclear, M-ECH-683 P. O. Box 94005 1340 Echelon Parkway Baton Rouge, LA 70804-9005 Jackson, MS 39213 Attorney General Jerry C. Roberts Asst. Attorney General Director, Nuclear Safety Assurance State of Mississippi Grand Gulf Nuclear Station P. O. Box 220 Bald Hill Road - Waterloo Road Jackson, MS 39205-0220 Port Gibson, MS 39150 Mr. Robert W. Goff, Program Director William A. Eaton Division of Radiological Health Vice President Mississippi State Dept. of Health System Energy Resources Inc. P.O. Box 1700 Entergy Operations, M-ECH-38 Jackson, MS 39215-1700 1340 Echelon Parkway Jackson, MS 39213 Phil Bass, Director Office of Pollution Control Patricia L. Campbell Department of Environmental Quality Winston & Strawn P.O. Box 10385 1400 L. Street, N.W. Jackson, MS 39289 Washington, DC 20005-3502 Jerry Cain, Chief Michael D. Bourgeois Environmental Permits Division Manager, Project Management Department of Environmental Quality Nuclear Business Development P. O. Box 10385 Entergy Nuclear, M-ECH-683 Jackson, MS 39289 1340 Echelon Parkway Jackson, MS 39213 M.J. Mike Foster, Jr.

Office of the Governor Michael A. Krupa P.O. Box 94004, State of Louisiana Director, Nuclear Safety Assurance Baton Rouge, LA 70804-9004 Entergy Nuclear South, M-ECH-414 1340 Echelon Parkway Mr. Rick Foster, Director Jackson, MS 39213 Emergency Management for Tensas Parish William K. Hughey P.O. Box 768 Sr. Manager, Business Development St. Joseph, LA 71366 Entergy Nuclear, M-ECH-683 1340 Echelon Parkway Military Department Jackson, MS 39213 Louisiana Dept. of Homeland Security/Emergency Preparedness Bob Evans Col. Mike Brown, Asst. Director Enercon Services Inc. 7667 Independence Boulevard 12850 Middlebrook Road, Suite 108 Baton Rouge, LA 70806 Germantown, MD 20874 Robert R. Latham, Jr., Director Mississippi Emergency Management Agency P.O. Box 4501, Fondren Station Jackson, Mississippi 39296-4501

GRAND GULF EARLY SITE PERMIT SERVICE LIST Ms. Bobbie Young, Director Other Claiborne County Emergency Management Mr. David Lochbaum Agency Union of Concerned Scientists P. O. Box 558 1707 H Street, NW Port Gibson, MS 39150 Suite 600 Washington, DC 20006-3919 Thomas E. Reynolds Co-RAC Chair Mr. Paul Gunter FEMA Region IV Director of the Reactor Watchdog Project 3003 Chamblee-Tucker Road Nuclear Information & Resource Service Atlanta, GA 30341 1424 16th Street, NW, Suite 404 Washington, DC 20036 Prosanta Chowdhury, Project Leader Louisiana Department of Environmental Mr. James Riccio Quality Greenpeace Office of Environmental Compliance 702 H Street, NW, Suite 300 Nuclear Power Plant Emergency Washington, DC 20001 Preparedness P. O. Box 4312 Mr. David Ritter Baton Rouge, LA 70821-4312 Research Associate on Nuclear Energy Public Citizens Critical Mass Energy Lisa Hammond and Environmental Program Chief, Technological Services Branch 215 Pennsylvania Avenue, SE FEMA Region VI Washington, DC 20003 800 N. Loop 288 Denton, TX 76209-3606 Mr. Marvin Fertel Senior Vice President Ms. Vanessa E. Quinn, Chief and Chief Nuclear Officer Radiological Emergency Preparedness Nuclear Energy Institute Branch Suite 400 Department of Homeland Security/FEMA 1776 I Street, NW 500 C Street, SW Washington, DC 20006-3708 Washington, DC 20472 Mr. Ron Simard Dr. Gail H. Marcus Nuclear Energy Institute U.S. Department of Energy Suite 400 Room 5A-143 1776 I Street, NW 1000 Independence Ave., SW Washington, DC 20006-3708 Washington, DC 20585 Mr. Russell Bell Mr. Thomas P. Miller Nuclear Energy Institute U.S. Department of Energy Suite 400 Headquarters - Germantown 1776 I Street, NW 19901 Germantown Road Washington, DC 20006-3708 Germantown, MD 20874-1290 Mr. James F. Mallay, Director Mr. Gary Wright, Manager Regulatory Affairs Division of Nuclear Safety FRAMATOME, ANP Illinois Emergency Management Agency 3315 Old Forest Road 1035 Outer Park Drive Lynchburg, VA 24501 Springfield, IL 62704

GRAND GULF EARLY SITE PERMIT SERVICE LIST Mr. Ernie H. Kennedy Dr. Glenn R. George Vice President New Plants PA Consulting Group Nuclear Plant Projects 130 Potter Street Westinghouse Electric Company Haddonfield, NJ 08033 2000 Day Hill Road Windsor, CT 06095-0500 Dr. Regis A. Matzie Senior Vice President and Chief Technology Officer Westinghouse Electric Company 2000 Day Hill Road Windsor, CT 06095-0500 Mr. Vince Langman Licensing Manager Atomic Energy of Canada Limited 2251 Speakman Drive Mississauga, Ontario Canada L5K 1B2 Mr. Ed Wallace, General Manager Projects PBMR Pty LTD PO Box 9396 Centurion 0046 Republic of South Africa Mr. Tom Clements 6703 Guide Avenue Takoma Park, MD 20912 Mr. Paul Leventhal Nuclear Control Institute 1000 Connecticut Avenue, NW Suite 410 Washington, DC 20036 Mr. Jack W. Roe SCIENTECH, INC.

910 Clopper Road Gaithersburg, MD 20878 Mr. Charles Brinkman Westinghouse Electric Co.

Washington Operations 12300 Twinbrook Pkwy., Suite 330 Rockville, MD 20852

MEETING BETWEEN NRC AND ENTERGY NUCLEAR POTOMAC ON QUALITY ASSURANCE INSPECTIONS FOR THE GRAND GULF EARLY SITE PERMIT APPLICATION One White Flint North Rockville, Maryland September 2, 2003 NAME (Please Print) ORGANIZATION PHONE NUMBER Stephen Koenick NRC/NRR/RNRP 301-415-1239 Kevin Coyne NRC/DIPM/IEPB 301-415-1399 Paul Prescott NRC/DIPM/IEPB 301-415-3026 Eddie Grant Exelon 610-765-5001 Doug Whitson Enercon 918-665-7693 Al Schneider Enercon 770-919-1930 Kathryn Sutton Winston-Strawn, LLP 202-371-5738 Guy Cesare Enercon 301-972-5221 George Zinke Entergy 601-368-5381 Bob Evans Enercon 301-972-5221 Russ Bell NEI 202-739-8087 Michael Scott NRC/NRR 301-415-1421 Mary Ann Ashley NRC/NRR 301-415-1073 Paul Gunter NIRS 202-328-0002 Jerome Blake NRC/Region II 404-562-4607 Thomas Foley NRC/NRR/IIPB 301-415-1036 Nanette Gilles NRC/NRR/RNRP 301-415-1180 Ken Heck NRC/DIPM/IEPB 301-415-2682 Chuck Paulk NRC/RIV/DRS/EMB 817-360-8236 Dale Thatcher NRC/DIPM/IEPB 301-415-3260 Robert Weisman NRC/OGC 301-415-1696 Enclosure 1