Duke EE Powere A Duke Energy Company MICHAEL S. TUCKMAN Executive Vice President Nuclear Generation Duke Power P.O. Box 1006 Charlotte, NC 28201-1006 Mailing Address:
526 South Church Street Charlotte, NC 28202 704 382 2200 704 382 4360 fax September 15, 2003 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555
Subject:
Duke Energy Corporation Oconee Nuclear Station, Docket Nos. 50-269, -270, -287 McGuire Nuclear Station, Docket Nos. 50-369, -370 Catawba Nuclear Station, Docket Nos. 50-413, -414 Monthly Performance and Operation Status - June, 2003 Please find attached information concerning the performance and operation status of the Oconee, McGuire and Catawba Nuclear Stations for the month of August, 2003.
Any questions or comments may be directed to Roger A. Williams at (704) 382-5346.
Sincerely,
-Yn S
r M. S. Tuckman j" e-, -a q
www. duke-energy. corn
Page 2 U.S. Nuclear Regulatory Commission Monthly Performance and Operation Status September 15, 2003 xc:
L. A. Reyes, Regional Administrator U.S. Nuclear Regulatory Commission Sam Nunn Atlanta Federal Center 61 Forsythe Street, SW, Suite 23T85 Atlanta, GA 30303-8931 R. E. Martin, Senior Project Manager U.S. Nuclear Regulatory Commission Mail Stop 0-8 H12 Washington, DC 20555 L. N. Olshan, Senior Project Manager U.S. Nuclear Regulatory Commission Mail Stop 0-8 H12 Washington, DC 20555 Ms. Margaret Aucoin Nuclear Assurance Corporation 3930 E. Jones Bridge Road #300 Norcross, GA 30092-2107 INPO Records Center 700 Galleria Parkway Atlanta, GA 30339-5957 Dottie Sherman, ANI Library American Nuclear Insurers Town Center, Suite 300S 29 South Main Street West Hartford, CT 06107-2445 M. Shannon, Senior Resident Inspector, Oconee Nuclear Station J. Brady, Senior Resident Inspector, McGuire Nuclear Station E. Guthrie, Senior Resident Inspector, Catawba Nuclear Station
VI Operating Data Report Docket No.
Date Completed By Telephone Operating Status
- 1. Unit Name:
Oconee 1
- 2. Reporting Period:
August 1, 2003 -August 31, 2003
- 3. Licensed Thermal Power (MWt):
2568
- 4. Nameplate Rating (Gross MWe):
934
- 5. Design Electrical Rating (Net Mwe):
886
- 6. Maximum Dependable Capacity (Gross MWe):
886
- 7. Maximum Dependable Capacity(Net MWe):
846
- 8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
50-269 September 15.2003 Roger Williams 704-382-5346 Notes: Year-to-date and cumulative capacity factors are calculated using a weighted average for maximum dependable capacity.
- 9. Power Level To Which Restricted, If Any (Net MWe):
- 10. Reason for Restrictions, If any:
This Month
- 11. Hours in Reporting Period 744.0
- 12. Number of Hours Reactor was Critical 744.0
- 13. Reactor Reserve Shutdown Hours 0.0
- 14. Hours Generator On-Line 744.0
- 15. Unit Reserve Shutdown Hours 0.0
- 16. Gross Thermal Energy Generated (MWH) 1842797
- 17. Gross Electrical Energy Generated (MWH) 638163
- 18. Net Electrical Energy Generated (MWH) 608610
- 19. Unit Service Factor 100.0
- 20. Unit Availability Factor 100.0
- 21. Unit Capacity Factor (Using MDC Net) 96.7
- 22. Unit Capacity Factor (Using DER Net) 92.3
- 23. Unit Forced Outage Rate 0.0
- 24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
YTD 5831.0 5831.0 0.0 5831.0 0.0 14811404 5192728 4972715 100.0 100.0 100.8 96.3 0.0 Cumulative 264096.0 209394.1 0.0 205891.1 0.0 510014058 176444035 167846761 78.0 78.0 74.5 71.7 9.0
- 25. If ShutDown At End Of Report Period, Estimated Date of Startup
- 26. Units in Test Status (Prior to Commercial Operation)
Forcast Achieved Initial Criticality Initial Electricity Commercial Operation NRC Calculated from Generator Nameplate Data:
1 037 937 KVA x 0.90 Pf=934 MW 3A - 9/15/2003
Page: 1 of 1 UNIT SHUTDOWNS
.Y DOCKET NO. 50-269 UNIT NAME: Oconee 1 DATE: September 15.2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: August. 2003 No.
Date:
Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.
No Outages for the Month Summary:
(1) Reason A - Equipment failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C - 9/15/2003
I MONTHLY REFUELING INFORMATION REQUEST
- 1.
Facility name:
Oconee Unit 1
- 2.
Scheduled next refueling shutdown: September 2003
- 3.
Scheduled restart following refueling: December 2003 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
- 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
If yes, what will these be?
If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?
- 5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
- 6.
Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
- 7.
Number of Fuel assemblies (a) in the core: 177 (b) in the spent fuel pool: 878*
(c) in the ISFSI: 1848****
- 8.
Present licensed fuel pool capacity: 1312 Size of requested or planned increase: **
- 9.
Projected date of last refueling which can be accommodated by present capacity: January 2005***
DUKE POWER COMPANY DATE: Seutember 15. 2003 Name of
Contact:
R. A. Williams Phone: (704) - 382-5346 Represents the combined total for Units 1 and 2 On March 29, 1990, received a site specific license for ISFSI which will store 2112 assemblies (88 modules). Forty (40) site specific modules were constructed and loaded.
In 1999 Oconee transitioned to its general license. Forty-four (44) general license modules were installed and 30 modules have now been loaded.
Additional modules will be installed on an as-needed basis.
Represents the combined total for Units 1,2, and 3
&k Operating Data Report Docket No.
Date Completed By Telephone Operating Status
- 1. Unit Name:
Oconee 2
- 2. Reporting Period:
August 1, 2003 -August 31, 2003
- 3. Licensed Thermal Power (MWt):
2568
- 4. Nameplate Rating (Gross MWe):
934
- 5. Design Electrical Rating (Net Mwe):
886
- 6. Maximum Dependable Capacity (Gross MWe):
886
- 7. Maximum Dependable Capacity(Net MWe):
846
- 8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
50-270 September 15.2003 Roger Williams 704-382-5346 Notes: Year-to-date and cumulative capacity factors are calculated using a weighted average for maximum dependable capacity.
- 9. Power Level To Which Restricted, If Any (Net MWe):
- 10. Reason for Restrictions, If any:
This Month
- 11. Hours in Reporting Period 744.0
- 12. Number of Hours Reactor was Critical 744.0
- 13. Reactor Reserve Shutdown Hours 0.0
- 14. Hours Generator On-Line 744.0
- 15. Unit Reserve Shutdown Hours 0.0
- 16. Gross Thermal Energy Generated (MWH) 1911208
- 17. Gross Electrical Energy Generated (MWH) 666839
- 18. Net Electrical Energy Generated (MWH) 637763
- 19. Unit Service Factor 100.0
- 20. Unit Availability Factor 100.0
- 21. Unit Capacity Factor (Using MDC Net) 101.3
- 22. Unit Capacity Factor (Using DER Net) 96.8
- 23. Unit Forced Outage Rate 0.0
- 24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
YTD 5831.0 5831.0 0.0 5831.0 0.0 14963017 5264701 5048717 100.0 100.0 102.3 97.7 0.0 Cumulative 254016.0 206916.8 0.0 204337.7 0.0 505516572 173917685 165775035 80.4 80.4 76.5 73.7 8.4
- 25. If ShutDown At End Of Report Period, Estimated Date of Startup
- 26. Units in Test Status (Prior to Commercial Operation)
Forcast Initial Criticality Initial Electricity Commercial Operation Achieved NRC Calculated from Generator Nameplate Data:
1 037 937 KVA x 0.90 Pf=934 MW 3A - 9/15/2003
Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50-270 UNIT NAME: Oconee 2 DATE: Semtember 15.2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: August 2003 No.
Date:
Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.
No Outages for the Month Summary:
(1) Reason A - Equipment failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C-9/15/2003
MONTHLY REFUELING INFORMATION REQUEST
- 1.
Facility name:
Oconee Unit 2
- 2.
Scheduled next refueling shutdown: March, 2004
- 3.
Scheduled restart following refueling: June, 2004 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
- 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
If yes, what will these be?
If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?
- 5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
- 6.
Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
- 7.
Number of Fuel assemblies (a) in the core: 177 (b) in the spent fuel pool: 878*
(c) in the ISFSI: See unit 1 ****
- 8.
Present licensed fuel pool capacity: 1312 Size of requested or planned increase: **
- 9.
Projected date of last refueling which can be accommodated by present capacity: January 2005***
DUKE POWER COMPANY DATE: September 15.2003 Name of
Contact:
R. A. Williams Phone: (704) - 382-5346 Represents the combined total for Units 1 and 2 See footnote on Unit 1 In 1999 Oconee transitioned to its general license. Forty-four (44) general license modules were installed and 30 modules have now been loaded.
Additional modules will be installed on an as-needed basis.
See footnote on Unit 1
Operating Data Report Docket No.
Date Completed By Telephone Operating Status
- 1. Unit Name:
Oconee 3
- 2. Reporting Period:
August 1, 2003 -August 31, 2003
- 3. Licensed Thermal Power (MWt):
2568
- 4. Nameplate Rating (Gross MWe):
934
- 5. Design Electrical Rating (Net Mwe):
886
- 6. Maximum Dependable Capacity (Gross MWe):
886
- 7. Maximum Dependable Capacity(Net MWe):
846
- 8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
50-287 Seotember 15.2003 Roger Williams 704-382-5346 Notes: Year-to-date and cumulative capacity factors are calculated using a weighted average for maximum dependable capacity.
- 9. Power Level To Which Restricted, If Any (Net MWe):
- 10. Reason for Restrictions, If any:
This Month
- 11. Hours in Reporting Period 744.0
- 12. Number of Hours Reactor was Critical 744.0
- 13. Reactor Reserve Shutdown Hours 0.0
- 14. Hours Generator On-Line 744.0
- 15. Unit Reserve Shutdown Hours 0.0
- 16. Gross Thermal Energy Generated (MWH) 1910592
- 17. Gross Electrical Energy Generated (MWH) 663453
- 18. Net Electrical Energy Generated (MWH) 634644
- 19. Unit Service Factor 100.0
- 20. Unit Availability Factor 100.0
- 21. Unit Capacity Factor (Using MDC Net) 100.8
- 22. Unit Capacity Factor (Using DER Net) 96.3
- 23. Unit Forced Outage Rate 0.0
- 24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
YTD 5831.0 4637.7 0.0 4538.9 0.0 11398221 3987275 3806578 77.8 77.8 77.2 73.7 9.1 Cumulative 251663.0 199690.6 0.0 196945.0 0.0 492657881 170536550 162706223 78.3 78.3 75.8 73.0 9.0
- 25. If ShutDown At End Of Report Period, Estimated Date of Startup
- 26. Units in Test Status (Prior to Commercial Operation)
Forcast Initial Criticality Initial Electricity Commercial Operation Achieved NRC Calculated from Generator Nameplate Data:
1 037 937 KVA x 0.90 Pf=934 MW 3A - 9/15/2003
UNIT SHUTDOWNS Page: 1 of 1 g
DOCKET NO. 50-287 UNIT NAME: Oconee 3 DATE: Septembe 15.2003 COMPLETED BY: Roger Williams TELEPHONE: 7042382-5346 REPORT MONTH: August. 2003 No.
Date:
Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.
No Outages for the Month Summary:
(1) Reason A - Equipment failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C - 9/15/2003
MONTHLY REFUELING INFORMATION REQUEST
- 1.
Facility name:
Oconee Unit 3
- 2.
Scheduled next refueling shutdown: October 2004
- 3.
Scheduled restart following refueling: December 2004 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
- 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
If yes, what will these be?
If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?
- 5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
- 6.
Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
- 7.
Number of Fuel assemblies (a) in the core: 177 (b) in the spent fuel pool: 476 (c) in the ISFSI: See Unit 1 *
- 8.
Present licensed fuel pool capacity: 825 Size of requested or planned increase: **
- 9.
Projected date of last refueling which can be accommodated by present capacity: January 2005***
DUKE POWER COMPANY DATE: Seotember 15.2003 Name of
Contact:
R. A. Williams Phone: (704) - 382-5346 See footnote of Unit 1 In 1999 Oconee transitioned to its general license. Forty-four (44) general license modules were installed and 30 modules have now been loaded.
Additional modules will be installed on an as-needed basis.
See footnote on Unit 1
OCONEE NUCLEAR STATION MONTHLY OPERATING STATUS REPORT JULY 2003
- 1.
Personnel Exposure -
The total station liquid release for JULY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.
The total station gaseous release for JULY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.
Operating Data Report Docket No.
Date Completed By Telephone Operating Status
- 1. Unit Name:
McGuire 1
- 2. Reporting Period:
August 1, 2003 - August 31, 2003
- 3. Licensed Thermal Power (MWt):
3411
- 4. Nameplate Rating (Gross MWe):
1305
- 5. Design Electrical Rating (Net Mwe):
1180
- 6. Maximum Dependable Capacity (Gross MWe):
1144
- 7. Maximum Dependable Capacity(Net MWe):
1100
- 8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
50-369 September 15.2003 Roger Williams 704-382-5346 Notes: *Nameplate Rating (GrossMWe) calculated as 1450.000 MVA *.90 power factor per Page iii, NUREG-0020.
- 9. Power Level To Which Restricted, If Any (Net MWe):
- 10. Reason for Restrictions, If any:
This Month
- 11. Hours in Reporting Period 744.0
- 12. Number of Hours Reactor was Critical 744.0
- 13. Reactor Reserve Shutdown Hours 0.0
- 14. Hours Generator On-Line 744.0
- 15. Unit Reserve Shutdown Hours 0.0
- 16. Gross Thermal Energy Generated (MWH) 2520630
- 17. Gross Electrical Energy Generated (MWH) 848259
- 18. Net Electrical Energy Generated (MWH) 816077
- 19. Unit Service Factor 100.0
- 20. Unit Availability Factor 100.0
- 21. Unit Capacity Factor (Using MDC Net) 99.7
- 22. Unit Capacity Factor (Using DER Net) 93.0
- 23. Unit Forced Outage Rate 0.0
- 24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
YTD 5831.0 5831.0 0.0 5831.0 0.0 19754261 6845263 6603021 100.0 100.0 102.9 96.0 0.0 Cumulative 190655.0 148856.5 0.0 147555.5 0.0 476659516 164347921 157518864 77.4 77.4 72.9 70.0 9.0
- 25. If ShutDown At End Of Report Period, Estimated Date of Startup
- 26. Units in Test Status (Prior to Commercial Operation)
Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A - 9/15/2003
Page: 1 of 1 UNIT SHURDOWNS VI DOCKET NO. 50-369 UNIT NAME: McGuire 1 DATE: September 15.2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: August. 2003 No.
Date:
Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown RIX Event Report S - Scheduled No.
No Outages for the Month Summary:
(1) Reason A - Equipment failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C - 9/15/2003
MONTHLY REFUELING INFORMATION REQUEST
- 1.
Facility name:
McGuire Unit 1
- 2.
Scheduled next refueling shutdown: March 2004
- 3.
Scheduled restart following refueling: April 2004 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
- 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
If yes, what will these be?
If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?
- 5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
- 6.
Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
- 7.
Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1011
- 8.
Present licensed fuel pool capacity: 1463 Size of requested or planned increase: ---
- 9.
Projected date of last refueling which can be accommodated by present license capacity:
November 2005 DUKE POWER COMPANY DATE: September 15. 2003 Name of
Contact:
R. A. Williams Phone: (704) - 382-5346
Operating Data Report Docket No.
Date Completed By Telephone Operating Status
- 1. Unit Name:
McGuire 2
- 2. Reporting Period:
August 1, 2003 - August 31, 2003
- 3. Licensed Thermal Power (MWt):
3411
- 4. Nameplate Rating (Gross MWe):
1305 *
- 5. Design Electrical Rating (Net Mwe):
1180
- 6. Maximum Dependable Capacity (Gross MWe):
1144
- 7. Maximum Dependable Capacity(Net MWe):
1100
- 8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
50-370 September 15.2003 Roger Williams 704-382-5346 Notes: *Nameplate Rating (GrossMWe) calculated as 1450.000 MVA *.90 power factor per Page Hii, NUREG-0020.
- 9. Power Level To Which Restricted, If Any (Net MWe):
- 10. Reason for Restrictions, If any:
This Month
- 11. Hours in Reporting Period 744.0
- 12. Number of Hours Reactor was Critical 744.0
- 13. Reactor Reserve Shutdown Hours 0.0
- 14. Hours Generator On-Line 744.0
- 15. Unit Reserve Shutdown Hours 0.0
- 16. Gross Thermal Energy Generated (MWH) 2535741
- 17. Gross Electrical Energy Generated (MWH) 855967
- 18. Net Electrical Energy Generated (MWH) 824819
- 19. Unit Service Factor 100.0
- 20. Unit Availability Factor 100.0
- 21. Unit Capacity Factor (Using MDC Net) 100.8
- 22. Unit Capacity Factor (Using DER Net) 94.0
- 23. Unit Forced Outage Rate 0.0
- 24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
YTD 5831.0 5831.0 0.0 5831.0 0.0 19695970 6827743 6586086 100.0 100.0 102.7 95.7 0.0 Cumulative 170951.0 141617.8 0.0 140364.0 0.0 463884330 161383848 154968880 82.1 82.1 80.4 76.8 5.3
- 25. If ShutDown At End Of Report Period, Estimated Date of Startup
- 26. Units in Test Status (Prior to Commercial Operation)
Forcast Achieved Initial Criticality Initial Electricity Commercial Operation 3A - 9115/2003
Page: 1of 1P UNIT SHUTDOWNS DOCKET NO. 50-37 UNIT NAME: McGuire 2 DATE: September 15.2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: August. 2003 No.
Date:
Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown RIX Event Report S - Scheduled No.
No Outages for the Month Sunmary:
(1) Reason A - Equipment failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3c-9/15/2003
MONTHLY REFUELING INFORMATION REQUEST
- 1.
Facility name:
McGuire Unit 2
- 2.
Scheduled next refueling shutdown: September 2003
- 3.
Scheduled restart following refueling: October 2003 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
- 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
If yes, what will these be?
If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?
- 5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
- 6.
Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
- 7.
Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 1061 (c) in the ISFSI: 320
- 8.
Present licensed fuel pool capacity: 1463 Size of requested or planned increase: =
- 9.
Projected date of last refueling which can be accommodated by present license capacity:
June 2003 DUKE POWER COMPANY DATE: September 15.2003 Name of
Contact:
R. A. Williams Phone: (704) - 382-5346
I McGUIRE NUCLEAR STATION MONTHLY OPERATING STATUS REPORT JULY 2003
- 1.
Personnel Exposure -
The total station liquid release for JULY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.
The total station gaseous release for JULY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.
Operating Data Report Docket No.
Date Completed By Telephone Operating Status
- l. Unit Name:
Catawba 1
- 2. Reporting Period:
August 1, 2003 - August 31, 2003
- 3. Licensed Thermal Power (MWt):
3411
- 4. Nameplate Rating (Gross MWe):
1305 *
- 5. Design Electrical Rating (Net Mwe):
1145
- 6. Maximum Dependable Capacity (Gross MWe):
1192
- 7. Maximum Dependable Capacity(Net MWe):
1129
- 8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
50-413 September 15.2003 Roger Williams 704-382-5346 Notes: *Nameplate Rating (GrossMWe) calculated as 1450.000 MVA *.90 power factor per Page iii, NUREG-0020.
- 9. Power Level To Which Restricted, If Any (Net MWe):
- 10. Reason for Restrictions, If any:
This Month
- 11. Hours in Reporting Period 744.0
- 12. Number of Hours Reactor was Critical 674.1
- 13. Reactor Reserve Shutdown Hours 0.0
- 14. Hours Generator On-Line 674.1
- 15. Unit Reserve Shutdown Hours 0.0
- 16. Gross Thermal Energy Generated (MWH) 2237777
- 17. Gross Electrical Energy Generated (MWH) 792633
- 18. Net Electrical Energy Generated (MWH) 747855
- 19. Unit Service Factor 90.6
- 20. Unit Availability Factor 90.6
- 21. Unit Capacity Factor (Using MDC Net) 89.0
- 22. Unit Capacity Factor (Using DER Net) 87.8
- 23. Unit Forced Outage Rate 9.4
- 24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
YTD 5831.0 5730.7 0.0 5724.0 0.0 19414180 6935333 6577667 98.2 98.2 99.9 98.5 1.8 Cumulative 159312.0 132835.9 0.0 131319.6 0.0 434278665 154181256 145475353 82.4 82.4 80.7 79.8 5.4
- 25. If ShutDown At End Of Report Period, Estimated Date of Startup
- 26. Units in Test Status (Prior to Commercial Operation)
Forcast Initial Criticality Initial Electricity Commercial Operation Achieved 3A - 9/15/2003
I Page: 1 of 1
,I UNIT SHUTDOWNS DOCKET NO. 50-413 UNIT NAME: Catawba 1 DATE: September 15.2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: August. 2003 No.
Date:
Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.
AUTOMATIC TRIP WAS INITIATED DUE TO RESISTANCE 2
08/29/03 F
69.95 A
3 TEMPERATURE DETECTOR TRIPPED BY FAILURE OF PRESSURIZER CHANNEL 2 FAILING LOW Summary:
Catawba unit 1 began the month of August operating at approximately 100% power. On 08/14/03 at 1130 the unit began decreasing power and held at 95% power from 1529 to to 08/29/03 at 0203 to evaluate options for repair of the reactor coolant loop " IA" hot leg resistance temperature detector failure. On 08/29/03 at 0203 a automatic reactor trip was initiated due to resistance temperature detector tripped by failure of pressurizer pressure channel 2 failing low. The unit was in the outage the remainder of the month.
(1) Reason A - Equipment failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C-9/15/2003
k r 4
MONTHLY REFUELING INFORMATION REQUEST
- 1.
Facility name:
Catawba Unit 1
- 2.
Scheduled next refueling shutdown: November 2003
- 3.
Scheduled restart following refueling: December 2003 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
- 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
If yes, what will these be?
If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?
- 5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
- 6.
Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
- 7.
Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 944
- 8.
Present licensed fuel pool capacity: 1418 Size of requested or planned increase: _
- 9.
Projected date of last refueling which can be accommodated by present license capacity:
November 2009 DUKE POWER COMPANY DATE: Seotember 15. 2003 Name of
Contact:
R. A. Williams Phone: (704) - 382-5346
Operating Data Report Docket No.
Date Completed By Telephone Operating Status
- 1. Unit Name:
Catawba 2
- 2. Reporting Period:
August 1, 2003 -August 31, 2003
- 3. Licensed Thermal Power (MWt):
3411
- 4. Nameplate Rating (Gross MWe):
1305 *
- 5. Design Electrical Rating (Net Mwe):
1145
- 6. Maximum Dependable Capacity (Gross MWe):
1192
- 7. Maximum Dependable Capacity(Net MWe):
1129
- 8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
50-414 September 15.2003 Roger Williams 704-382-5346 Notes: *Nameplate Rating (GrossM[We) calculated as 1450.000 MVA *.90 power factor per Page iii, NUREG-0020.
- 9. Power Level To Which Restricted, If Any (Net MWe):
- 10. Reason for Restrictions, If any:
This Month
- 11. Hours in Reporting Period 744.0
- 12. Number of Hours Reactor was Critical 744.0
- 13. Reactor Reserve Shutdown Hours 0.0
- 14. Hours Generator On-Line 744.0
- 15. Unit Reserve Shutdown Hours 0.0
- 16. Gross Thermal Energy Generated (MWH) 2530663
- 17. Gross Electrical Energy Generated (MWH) 898023
- 18. Net Electrical Energy Generated (MWH) 852748
- 19. Unit Service Factor 100.0
- 20. Unit Availability Factor 100.0
- 21. Unit Capacity Factor (Using MDC Net) 101.5
- 22. Unit Capacity Factor (Using DER Net) 100.1
- 23. Unit Forced Outage Rate 0.0
- 24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)
YTD 5831.0 5219.5 0.0 5188.0 0.0 17452210 6249519 5932534 89.0 89.0 90.1 88.9 0.2 Cumulative 149328.0 125024.5 0.0 123568.8 0.0 406422037 144895568 136917349 82.7 82.7 81.1 80.1 6.6
- 25. If ShutDown At End Of Report Period, Estimated Date of Startup
- 26. Units in Test Status (Prior to Commercial Operation)
Forcast Initial Criticality Initial Electricity Commercial Operation Achieved 3A - 9/15/2003
I,
Page: 1 of 1 UNIT SHUTDOWNS DOCKET NO. 50414 UNIT NAME: Catawba 2 DATE: September 15.2003 COMPLETED BY: Roger Williams TELEPHONE: 704-382-5346 REPORT MONTH: August. 2003 No.
Date:
Type Duration (1) Reason (2) Method of Licensed Cause and Corrective Action to Prevent Recurrence F - Forced Hours Shutdown R/X Event Report S - Scheduled No.
No Outages for the Month Summary:
(1) Reason A - Equipment failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory restriction E - Operator Training/License Examination F - Administrative G - Operator Error (Explain)
H - Other (Explain)
(2) Method 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain) 3C - 9/15/2003
MONTHLY REFUELING INFORMATION REQUEST
- 1.
Facility name:
Catawba Unit 2
- 2.
Scheduled next refueling shutdown: Seotember 2004
- 3.
Scheduled restart following refueling: October 2004 THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.
- 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
If yes, what will these be?
If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?
- 5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
- 6.
Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
- 7.
Number of Fuel assemblies (a) in the core: 193 (b) in the spent fuel pool: 917
- 8.
Present licensed fuel pool capacity: 1418 Size of requested or planned increase: --
- 9.
Projected date of last refueling which can be accommodated by present license capacity:
May 2012 DUKE POWER COMPANY DATE: September 15.2003 Name of
Contact:
R. A. Williams Phone: (704) - 382-5346
CATAWBA NUCLEAR STATION MONTHLY OPERATING STATUS REPORT JULY 2003
- 1.
Personnel Exposure -
The total station liquid release for JULY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.
The total station gaseous release for JULY has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.