9/05/03-SER Appendix B Chronology
ML032481328
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 09/05/2003
From: Kuo P
NRC/NRR/DRIP/RLEP
To: Ridenoure R
Omaha Public Power District
Burton W, NRR/DRIP/RLEP, 301-415-2853
Shared Package
ML032481209 List:
References
Download: ML032481328 (2)


Text

B-1 APPENDIX B CHRONOLOGY This appendix contains a chronological listing of routine licensing correspondence between the U.S. Nuclear Regulatory Commission (NRC) staff and the Omaha Public Power District (OPPD) regarding the NRC staffs safety review of the Fort Calhoun Station, Unit 1, application for license renewal (Docket No. 50-285).

January 9, 2002 FCS Application for Renewed Operating License January 9, 2002 Transmittal of Boundary Drawings February 6, 2002 Receipt and Availability of the FCS LRA March 14, 2002 Status Letter on Acceptability Review April 5, 2002 Supplemental LRA Information April 16, 2002 LRA Acceptance Letter August 22, 2002 Request for Partial Fee Waiver August 23, 2002 Telecon Summary (conducted on August 7, 2002) - LRA Sections 2.3.3.5, 2.3.3.8, and 2.3.3.9 August 26, 2002 Revised Review Schedule October 11, 2002 Transmittal of Staff Requests for Additional Information November 22, 2002 RAI Response Letter (first of three)

November 22, 2002 Boundary Drawings to Support First RAI Response Letter November 25, 2002 Revised Review Schedule December 12, 2002 RAI Response Letter (second of three)

December 12, 2002 Boundary Drawings to Support Second RAI Response Letter December 19, 2002 RAI Response Letter (third of three)

December 19, 2002 Boundary Drawings to Support Second RAI Response Letter December 20, 2002 Scoping and Screening Inspection Report

B-2 January 16, 2003 Telecon Summary (conducted on July 18, 2002 and September 5, 2002)

- LRA Sections 2.1.4, 2.2, 2.3.3.14, 2.3.3.19, 2.3.3.20, 2.3.4, B.3.2, and B.3.3 January 31, 2003 Granting of Partial Fee Waiver February 20, 2003 Potential Open Item Letter March 14, 2003 Responses to Potential Open Items March 14, 2003 Telecon Summary (conducted on August 8, 2002) - LRA Sections 2.3.3.2, 2.3.3.15, and 2.3.3.16 April 4, 2003 Revised Responses to Potential Open Items April 10, 2003 Telecon Summary (conducted on August 8, 2002) - LRA Sections 2.3.1.2, 2.3.1.3, 2.3.2.1, 2.3.3.3, 2.3.3.4, 2.3.3.6, 2.3.3.7, B.1.2, B.1.5, B.2.1, and B.3.6 April 12, 2003 Telecon Summary (conducted on September 19, 2002) - LRA Sections 4.7.1 and 4.7.2 April 17, 2003 Telecon Summary (conducted on September 16 and 17, 2002) - LRA Sections 2.5, 3.6, and B.3.4 May 2, 2003 Telecon Summary (conducted on March 18, 2003) - Potential Open Items 1(c), 6(a), 6(b), and 12 May 16, 2003 Fort Calhoun Station, Unit 1 Annual Update to Application for Renewed Operating License June 13, 2003 Telecon Summary (conducted on June 6, 2003) - Open Item 3.6.2.4.3.2-1 July 7, 2003 License Renewal Safety Evaluation Report for Fort Calhoun Station Unit 1-Comments and Responses to Open and Confirmatory Items August 7, 2003 License Renewal Safety Evaluation Report for Fort Calhoun Station Unit 1-Clarification of Responses to Open Items Meeting Summary (conducted on November 20 and 21, 2002) - LRA Sections 2.1, 2.1.4, 2.3.1.2, 2.3.2.1, 2.3.3.20, 2.3.3.5, 2.3.3.3, 2.3.3.15, 2.3.3.16, 2.3.4, 2.4.1, 2.4.2, 2.4.2.5, 2.4.2.6, 2.5, 3.1, 3.2, 3.6, 4.2, 4.7.1, B.1.7, B.2.9, B.3.1, B.3.2, and B.3.3 Meeting Summary (conducted December 3 and 4, 2003) - LRA Sections 2.3.3.19, 2.3.3.20, 3.3, 3.4, 3.5, 4.1, 4.3, 4.5, 4.6, B.1.3, B.1.4, B.1.7, B.2.3, B.2.4, and B.2.5

B-3 August 28, 2003 Meeting Summary (conducted on May 28 and 29, 2003) - Open Item 3.0-1 September 5, 2003 Telecon Summary (conducted on May 8, 2003) - Open Items 3.6.2.3.1.2-1, 3.6.2.4.3.2-1, 3.6.2.4.4.2-1, and 3.6.2.4.5.2-1