5 REVIEW BY THE ADVISORY COMMITTEE ON REACTOR SAFEGUARDS The Advisory Committee on Reactor Safeguards (ACRS) will review the 10 CFR Part 54 portion of the Fort Calhoun Station, Unit 1 (FCS) license renewal application (LRA). The Omaha Public Power District and the staff will meet with the ACRS full committee to discuss issues associated with the review of the LRA.

After the ACRS completes its review of the FCS LRA and SER, the full committee will issue a report discussing the results of its review. This ACRS report will be included in an update to this SER. The staff will address any issues and concerns identified in that report.

5-1

6 CONCLUSIONS The staff reviewed the Fort Calhoun Station, Unit 1, license renewal application in accordance with Commission regulations and NUREG-1800, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants, dated July, 2001. In accordance with 10 CFR 54.29, the staff identifies the standards for issuance of a renewed license.

On the basis of its evaluation of the application as discussed above, the staff has determined that the requirements of 10 CFR 54.29 have been met.

The staff notes the requirements of Subpart A of 10 CFR Part 51 are documented in NUREG-1427, Supplement 12, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, dated August 15, 2003.

6-1