Farley Inspection / Activity Plan 09/01/2003 - 09/30/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 1 08/26/2003 10:36:22 Report 22 5
EB2-PIMR
- BIENNIAL PI&R AND MAINTANCE RULE Baseline Inspections 09/15/2003 09/17/2003 Maintenance Effectiveness IP 7111112B 1, 2 Baseline Inspections 09/15/2003 09/19/2003 Identification and Resolution of Problems IP 71152B 1, 2 Baseline Inspections 09/29/2003 10/03/2003 Identification and Resolution of Problems IP 71152B 1, 2 2
PS-SEC
- SECURITY Baseline Inspections 09/10/2003 09/12/2003 Access Control (Search of Personnel, Packages, and Vehicles: Identification and Authorizati IP 7113002 1, 2 Baseline Inspections 09/10/2003 09/12/2003 Response to Contingency Events (Protective Strategy and Implementation of Protective Stra IP 7113003 1, 2 3
PS-RP
- RADIATION PROTECTION Baseline Inspections 12/01/2003 12/05/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Radiological Environmental Monitoring Program IP 7112203 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Performance Indicator Verification IP 71151 1, 2 2
EB1SSDPC - SSDPC PRE-INSPECTION VISIT Baseline Inspections 01/05/2004 01/09/2004 Safety System Design and Performance Capability IP 7111121 1, 2 5
EB1SSDPC - SAFETY SYS DESIGN & PERFORMANCE CAPABILI Baseline Inspections 01/26/2004 01/30/2004 Safety System Design and Performance Capability IP 7111121 1, 2 Baseline Inspections 02/09/2004 02/13/2004 Safety System Design and Performance Capability IP 7111121 1, 2 1
EB2-ISI
- INSERVICE INSPECTION-U2 Baseline Inspections 03/22/2004 03/26/2004 Inservice Inspection Activities - PWR IP 7111108P 2
1 2515/150
- 2515/150 REV1 UNIT 2 Safety Issues 03/29/2004 04/02/2004 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-0 IP 2515/150 2
4 LIC RENE
- FIRST LICENSE RENEWAL INSPECTION License Renewal Insp 05/10/2004 05/14/2004 License Renewal Inspection IP 71002 1, 2 2
- REQUAL INSPECTION Baseline Inspections 07/26/2004 07/30/2004 Licensed Operator Requalification IP 7111111B 1, 2 1
EB2-HS
- HEAT SINK Baseline Inspections 08/09/2004 08/13/2004 Heat Sink Performance IP 7111107B 1, 2 2
- EP EXERCISE Baseline Inspections 08/16/2004 08/20/2004 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 08/16/2004 08/20/2004 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 08/16/2004 08/20/2004 Performance Indicator Verification IP 71151 1, 2 4
LIC RENE
- SECOND LICENSE RENEWAL INSPECTION License Renewal Insp 09/20/2004 10/08/2004 License Renewal Inspection IP 71002 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.