August 27, 2003 Mr. George Vanderheyden Vice President - Calvert Cliffs Nuclear Power Plant Constellation Generation Group Calvert Cliffs Nuclear Power Plant, Inc.
1650 Calvert Cliffs Parkway Lusby, MD 20657-4702
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
CALVERT CLIFFS NUCLEAR POWER PLANT
Dear Mr. Vanderheyden:
On July 29, 2003, the NRC staff completed its mid-cycle plant performance review of Calvert Cliffs Nuclear Power Plant. The mid-cycle review for Calvert Cliffs Nuclear Power Plant involved the participation of all technical divisions in evaluating performance for the first half of the calendar year 2003 assessment cycle. The process included a review of performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance and our plans for future inspections at your facility so that you will have an opportunity to prepare for these inspections and to inform us of any planned inspections that may conflict with your plant activities.
Plant performance for the most recent quarter was within the Regulatory Response Column of the NRCs Action Matrix, based on one finding of low to moderate safety significance (White) common to both units in the Emergency Preparedness Cornerstone. The finding involved the offsite alert and notification siren system which was incapable of being actuated in a timely manner. The NRC conducted a 95001 supplemental inspection in January 2003 and determined that your actions to resolve this issue were appropriate.
The enclosed inspection plan details the inspections scheduled through September 30, 2004.
The inspection plan is provided to minimize the resource impact on your staff and to allow for scheduling conflicts and personnel availability to be resolved in advance of inspector arrival on site. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last six months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting. The NRC plans to Pilot a new Inspection Procedure (71111.DS, Safety System Design and Performance Capability) during the weeks of January 12 and 26, 2004.
This procedure combines the inspection activities previously performed by 71111.21 (Safety System Design and Performance Capability), 71111.17B (Permanent Plant Modifications), and 71111.02 (Evaluation of Changes, Tests, or Experiments).
Mr. George Vanderheyden 2
In accordance with 10 CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact James M. Trapp, Chief, Reactor Projects Branch 1, at 610-337-5186 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
A. Randolph Blough, Director Division of Reactor Projects Docket Nos.
50-317 50-318 License Nos. DPR-53 DPR-69
Enclosure:
Calvert Cliffs Inspection/Activity Plan cc w/encl:
President, Calvert County Board of Commissioners J. M. Petro, Esquire, Constellation Energy Group, Inc.
J. E. Silberg, Esquire, Shaw, Pittman, Potts and Trowbridge M. Geckle, Manager of Operations (CCNPP)
R. McLean, Manager, Nuclear Programs K. Burger, Esquire, Maryland People's Counsel P. T. Birnie, Esquire, Maryland Safe Energy Coalition L. F. Donatell, NRC Technical Training Center P. Furio, Acting Director, Nuclear Regulatory Matters (CCNPP)
Institute of Nuclear Power Operations (INPO)
State of Maryland (2)
Mr. George Vanderheyden 3
Distribution w/encl:
H. Miller, RA/J. Wiggins, DRA (1)
A. Blough, DRP W. Lanning, DRS B. Holian, DRP K. McConnell, DRP R. Crlenjak, DRS M. Giles - SRI - Calvert Cliffs J. OHara, DRP R. Laufer, NRR G. Vissing, PM, NRR R. Clark/P. Tam, PM, NRR (Backup)
D. Screnci, PAO N. Sheehan, PAO J. Trapp, DRP DRS Branch Chiefs (5)
M. Modes, DRS R. Nimitz, DRS P. Frechette, DRS N. McNamara, DRS RidsNrrDipmlipb Region I Docket Room (with concurrences)
DOCUMENT NAME: G:\\BRANCH1\\2003 ROP4 mid-c letters\\Calvert Cliffs Mid-cycle Letter 2003.wpd After declaring this document An Official Agency Record it will/will not be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP RI/DRP NAME JOHara/JT for JTrapp/JT ABlough/AB DATE 08/13/03 08/13/03 08/26/03 08/ /03 08/ /03 OFFICIAL RECORD COPY
Calvert Cliffs Inspection / Activity Plan 06/29/2003 - 10/02/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/26/2003 13:19:46 Report 22 1
71151
- EP PI VERIFICATION Baseline Inspections 07/07/2003 07/11/2003 Performance Indicator Verification IP 71151 1, 2 5
TI148BC
- SEC ICM Safety Issues 07/07/2003 07/11/2003 Inspection of Nuclear Reactor Safeguards - Interim Compensatory Measures IP 2515/148 1, 2 1
- PUB RAD SAFETY - RADWASTE Baseline Inspections 09/08/2003 09/12/2003 Radioactive Material Processing and Transportation IP 7112202 1, 2 5
- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 10/20/2003 10/24/2003 Identification and Resolution of Problems IP 71152B 1, 2 Baseline Inspections 11/03/2003 11/07/2003 Identification and Resolution of Problems IP 71152B 1, 2 5
7111401
- EP EXERCISE EVALUATION Baseline Inspections 10/20/2003 10/24/2003 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 10/20/2003 10/24/2003 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 1
71121
- OCC RAD SAFETY Baseline Inspections 12/01/2003 12/05/2003 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 12/01/2003 12/05/2003 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 12/01/2003 12/05/2003 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2 1
7112201
- PUB RAD SAFETY - RETS Baseline Inspections 12/08/2003 12/12/2003 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1, 2 2
7111111B
- L.O. REQUALIFICATION PROGRAM Baseline Inspections 12/14/2003 12/19/2003 Licensed Operator Requalification IP 7111111B 1, 2 8
71111DS
- DESIGN INSPECTION Baseline Inspections 01/12/2004 01/16/2004 Safety System Design and Performance Capability IP 71111.DS 1, 2 Baseline Inspections 01/26/2004 01/30/2004 Safety System Design and Performance Capability IP 71111.DS 1, 2 3
3/1 EXM
- OPERATOR LICENSING INITIAL EXAMS Not Applicable 02/02/2004 02/06/2004 CALVERT CLIFFS UNITS 1&2 INITIAL EXAM (3/1-5/04)
U01517 1
Not Applicable 03/01/2004 03/05/2004 CALVERT CLIFFS UNITS 1&2 INITIAL EXAM (3/1-5/04)
U01517 1
1 7111107B
- HEAT SINK Baseline Inspections 02/09/2004 02/15/2004 Heat Sink Performance IP 7111107B 1, 2 1
71121
- OCC RAD SAFETY Baseline Inspections 03/22/2004 03/26/2004 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 03/22/2004 03/26/2004 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 03/22/2004 03/26/2004 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2 1
71121
- OCC RAD SAFETY Baseline Inspections 04/12/2004 04/16/2004 Access Control to Radiologically Significant Areas IP 7112101 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Calvert Cliffs Inspection / Activity Plan 06/29/2003 - 10/02/2004 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/26/2003 13:19:46 Report 22 1
71121
- OCC RAD SAFETY Baseline Inspections 04/12/2004 04/16/2004 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 04/12/2004 04/16/2004 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2 2
7111108P
- INSERVICE INSPECTION-UNIT 1 Safety Issues 04/19/2004 04/23/2004 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02)
Baseline Inspections 04/19/2004 04/23/2004 Inservice Inspection Activities - PWR IP 7111108P 1
3 71111.05
- TRIENNIAL FIRE PROTECTION Baseline Inspections 05/10/2004 05/14/2004 Fire Protection IP 7111105T 2
Baseline Inspections 05/24/2004 05/28/2004 Fire Protection IP 7111105T 1, 2 1
71121
- OCC RAD SAFETY Baseline Inspections 06/14/2004 06/18/2004 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 06/14/2004 06/18/2004 ALARA Planning and Controls IP 7112102 1, 2 1
71114
- EP PROGRAM INSPECT & PI VERIF Baseline Inspections 07/19/2004 07/23/2004 Alert and Notification System Testing IP 7111402 1, 2 Baseline Inspections 07/19/2004 07/23/2004 Emergency Response Organization Augmentation Testing IP 7111403 1, 2 Baseline Inspections 07/19/2004 07/23/2004 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 07/19/2004 07/23/2004 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 07/19/2004 07/23/2004 Performance Indicator Verification IP 71151 1, 2 1
7112202
- PUB RAD SAFETY - RADWASTE Baseline Inspections 07/26/2004 07/30/2004 Radioactive Material Processing and Transportation IP 7112202 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.