August 13, 2003 From:
Peter Tam To:
internet:iftikhar.Abbasi@nmp.cn.com; John J Dosa; Steven Leonard Date:
8/13/03 9:20AM
Subject:
Nine Mile Point Relief Requests (TAC MC0191 and MC0192)
Steve:
This is regarding your application for relief dated 8/8/03 from the qualification requirements for dissimilar metal piping welds.
There are two parts to this relief request - one is to use the PDI program as an alternative to the ASME Code requirements, and one is relief from a depth sizing requirement. For plants that needed to perform such inspections this past spring outage, licensees needed relief from both parts. However, since that time, industry personnel have become qualified to the depth sizing requirement. Therefore, while review to use the PDI alternative is warranted, we are have more reserved about a request for relief from the depth sizing requirement.
Are you aware of the industrys latest capabilities to depth size flaws in dissimlar metal welds?
We propose to discuss with you in a conference call how the relief request may be modified.
This e-mail serves solely to prepare you and others for the propsed conference call. It does not convey an NRC staff position, nor does it formally request for additional information.
Peter S. Tam, Senior Project Manager Project Directorate I-1 Division of Licensing Project Management Office of Nuclear Reactor Regulation e-mail: pst@nrc.gov Tel.: 301-415-1451 CC:
Terence Chan Mail Envelope Properties (3F3A3B29.370 : 10 : 20510)
Subject:
Nine Mile Point Relief Requests (TAC MC0191 and MC0192)
Creation Date:
8/13/03 9:20AM From:
Peter Tam Created By:
PST@nrc.gov Recipients Action Date & Time iftikhar Transferred 08/13/03 09:20AM
Abbasi (internet:iftikhar.Abbasi@nmp.cn.c owf2_po.OWFN_DO Delivered 08/13/03 09:20AM TLC CC (Terence Chan)
Opened 08/13/03 10:09AM nmp.cn.com Transferred 08/13/03 09:20AM John.Dosa (John J Dosa)
Steven.Leonard (Steven Leonard)
Post Office Delivered Route iftikhar internet:nmp.cn.com owf2_po.OWFN_DO 08/13/03 09:20AM nmp.cn.com Files Size Date & Time MESSAGE 2375 08/13/03 09:20AM Options Auto Delete:
No Expiration Date:
None Notify Recipients:
Yes Priority:
Standard Reply Requested:
No Return Notification:
None Concealed
Subject:
No Security:
Standard To Be Delivered:
Immediate Status Tracking:
Delivered & Opened