August 5, 2003 Carolina Power & Light Company ATTN:

Mr. James Scarola Vice President - Harris Plant Shearon Harris Nuclear Power Plant P. O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

SUBJECT:

PUBLIC MEETING

SUMMARY

SHEARON HARRIS NUCLEAR POWER PLANT - DOCKET NO. 50-400

Dear Mr. Scarola:

This refers to the management meeting held at your request in the Region II Office, Sam Nunn Atlanta Federal Center, 61 Forsyth Street, S.W., Atlanta, Georgia, in Suite 24T20 on July 31, 2003, from 1:00 p.m. to 3:00 p.m. (EDT). The meetings purpose was to discuss your progress in making changes to your fire protection program. Enclosed is a list of attendees and the presentation handouts.

Your staff presented an overview of recent NRC fire protection inspection findings, root causes, and corrective actions. The organization, goals, tasks and milestones associated with your new Safe Shutdown Analysis Validation Project, as well as newly identified fire protection issues, were also discussed. We believe this meeting was informative and useful in understanding your achievements and future plans related to your fire protection program. We agreed to meet again in December 2003 to update your progress in this area.

In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter and its enclosures will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Should you have any questions concerning this meeting, please contact me at (404) 562-4605.

Sincerely,

/RA/

Charles R. Ogle, Chief Engineering Branch 1 Division of Reactor Safety Docket No.: 50-400 License No.: NPF-63

Enclosures:

(See page 2)

2 CP&L

Enclosures:

1.

List of Attendees 2.

Licensee Presentation Handouts cc w/encls:

James W. Holt, Manager Performance Evaluation and Regulatory Affairs CPB 9 Carolina Power & Light Company Electronic Mail Distribution Robert J. Duncan II Director of Site Operations Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Benjamin C. Waldrep Plant General Manager--Harris Plant Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Terry C. Morton, Manager Support Services Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution John R. Caves, Supervisor Licensing/Regulatory Programs Carolina Power & Light Company Shearon Harris Nuclear Power Plant Electronic Mail Distribution Steven R. Carr Associate General Counsel - Legal Department Progress Energy Service Company, LLC Electronic Mail Distribution John H. ONeill, Jr.

Shaw, Pittman, Potts & Trowbridge 2300 N. Street, NW Washington, DC 20037-1128 Beverly Hall, Acting Director Division of Radiation Protection N. C. Department of Environmental Commerce & Natural Resources Electronic Mail Distribution (cc w/encl contd - See page 3)

3 CP&L (cc w/encl contd)

Peggy Force Assistant Attorney General State of North Carolina Electronic Mail Distribution Public Service Commission State of South Carolina P. O. Box 11649 Columbia, SC 29211 Chairman of the North Carolina Utilities Commission c/o Sam Watson, Staff Attorney Electronic Mail Distribution Robert P. Gruber Executive Director Public Staff NCUC 4326 Mail Service Center Raleigh, NC 27699-4326 Herb Council, Chair Board of County Commissioners of Wake County P. O. Box 550 Raleigh, NC 27602 Tommy Emerson, Chair Board of County Commissioners of Chatham County Electronic Mail Distribution Distribution w/encl:

C. Patel, NRR RIDSNRRDIPMLIPB PUBLIC OFFICE RII:DRS RII:DRP SIGNATURE RA NAME OGLE FREDRICKSON DATE 8/ /2003 8/5/2003 8/ /2003 8/ /2003 8/ /2003 8/ /2003 8/ /2003 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO PUBLIC DOCUMENT YES NO OFFICIAL RECORD COPY DOCUMENT NAME: C:\\ORPCheckout\\FileNET\\ML032200269.wpd ATTENDANCE LIST DATE: July 31, 2003 ORGANIZATION: Shearon Harris Nuclear Power Plant PURPOSE: To discuss progress in making changes to the Harris fire protection program Licensee A. Khanpour, Engineering Manager J. Caves, Licensing Supervisor T. Maness, Fire Protection Supervisor NRC C. Payne, Fire Protection Team Leader R. Schin, Senior Reactor Inspector G. Wiseman, Senior Reactor Inspector G. MacDonald, Senior Reactor Inspector