|
---|
Category:Inspection Report
MONTHYEARIR 05000254/20230042024-02-0505 February 2024 Integrated Inspection Report 05000254/2023004 and 05000265/2023004 IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 IR 05000254/20230022023-08-0808 August 2023 Integrated Inspection Report 05000254/2023002 and 05000265/2023002 IR 05000254/20234012023-06-26026 June 2023 Cyber Security Inspection Report 05000254/2023401 and 05000265/2023401 IR 05000265/20230402023-06-22022 June 2023 Reissue Quad Cities Nuclear Power Station 95001 Supplemental Inspection Supplemental Report 05000265/2023040 and Follow Up Assessment Letter ML23167B1722023-06-16016 June 2023 95001 Supplemental Inspection Report 05000265/2023040 and Follow-Up Assessment Letter IR 05000254/20234022023-05-15015 May 2023 Security Baseline and ISFSI Inspection Reports 05000254/2023402, 05000265/2023402, 07200053/2023401 IR 05000254/20230012023-05-0808 May 2023 Integrated Report 05000254/2023001 and 05000265/2023001 ML23065A2832023-03-0707 March 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 IR 05000254/20220062023-03-0101 March 2023 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2022006 and 05000265/2022006) IR 05000254/20220042023-02-10010 February 2023 Integrated Inspection Report 05000254/2022004 and 05000265/2022004 IR 05000254/20220112023-01-0606 January 2023 Triennial Fire Protection Inspection Report 05000254/2022011 and 05000265/2022011 IR 05000254/20220102022-12-13013 December 2022 Phase 4 Post-Approval License Renewal Inspection Report 05000254/2022010 and 05000265/2022010 ML22313A1502022-11-29029 November 2022 EA-22-062 QC ERV Final Action IR 05000254/20224012022-11-22022 November 2022 Security Baseline Inspection Report 05000254/2022401 and 05000265/2022401 IR 05000254/20220132022-11-17017 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000254/2022013 and 05000265/2022013 IR 05000254/20220032022-11-0303 November 2022 Integrated Inspection Report 05000254/2022003 and 05000265/2022003 IR 05000254/20220052022-08-22022 August 2022 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2022005; 05000265/2022005) IR 05000254/20225012022-08-15015 August 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2022501 and 05000265/2022501 IR 05000254/20220022022-08-0909 August 2022 Integrated Inspection Report 05000254/2022002 and 05000265/2022002 IR 05000254/20220902022-08-0808 August 2022 NRC Inspection Report 05000254/2022090 and 05000265/2022090; Preliminary White Finding IR 05000254/20220122022-07-11011 July 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000254/2022012 and 05000265/2022012 IR 05000254/20220012022-05-11011 May 2022 Integrated Inspection Report 05000254/2022001 and 05000265/2022001 IR 05000254/20210062022-03-0202 March 2022 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2021006 and 05000265/2021006) ML22033A1672022-02-0202 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000265/2022001 IR 05000254/20210042022-02-0202 February 2022 Integrated Inspection Report 05000254/2021004 and 05000265/2021004 IR 05000254/20214022021-12-0101 December 2021 Security Baseline Inspection Report 05000254/2021402 and 05000265/2021402 IR 05000254/20210102021-11-24024 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000254/2021010 and 05000265/2021010 IR 05000254/20210032021-10-28028 October 2021 Integrated Inspection Report 05000254/2021003 and 05000265/2021003 IR 05000254/20214012021-09-0909 September 2021 Security Baseline Inspection Report 05000254/2021401 and 05000265/2021401 IR 05000254/20210052021-09-0101 September 2021 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2021005 and 05000265/2021005) ML21238A3142021-08-26026 August 2021 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000254/2021004; 05000265/2021004 IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 IR 05000254/20210022021-08-0909 August 2021 Integrated Inspection Report 05000254/2021002 and 05000265/2021002 IR 05000254/20214032021-06-28028 June 2021 Quad Nuclear Power Station - Material Control and Accounting Program Inspection Report 05000254/2021403 and 05000265/2021403 IR 05000254/20210012021-04-26026 April 2021 Integrated Inspection Report 05000254/2021001 and 05000265/2021001 IR 05000254/20200062021-03-0404 March 2021 Annual Assessment Letter for Quad Cities Nuclear Power Station Units 1 and 2 (Report 05000254/2020006 and 05000265/2020006) IR 05000254/20200042021-02-0404 February 2021 Integrated Inspection Report 05000254/2020004 and 05000265/2020004 IR 05000254/20204022021-01-11011 January 2021 Security Baseline Inspection Report 05000254/2020402 and 05000265/2020402 IR 05000254/20200102020-11-24024 November 2020 Biennial Problem Identification and Resolution Inspection Reportt 05000254/2020010 and 05000265/2020010 IR 05000254/20200112020-11-0909 November 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000254/2020011 and 05000265/2020011 IR 05000254/20200032020-11-0909 November 2020 Integrated Inspection Report 05000254/2020003; 05000265/2020003 and 07200053/2020001 IR 05000254/20205012020-09-0808 September 2020 Emergency Preparedness Inspection Report 05000254/2020501 and 05000265/2020501 IR 05000254/20200052020-09-0101 September 2020 Updated Inspection Plan for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2020005 and 05000265/2020005) IR 05000254/20200022020-08-11011 August 2020 Integrated Inspection Report 05000254/2020002 and 05000265/2020002 IR 05000254/20200012020-05-11011 May 2020 Integrated Inspection Report 05000254/2020001 and 05000265/2020001 2024-02-05
[Table view] Category:Letter
MONTHYEARIR 05000254/20230042024-02-0505 February 2024 Integrated Inspection Report 05000254/2023004 and 05000265/2023004 ML24004A0052024-01-17017 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0042 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2024-01-0303 January 2024 Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 ML23349A1622023-12-17017 December 2023 Issuance of Amendment Nos. 298 and 294 Increase Completion Time in Technical Specification 3.8.1.B.4 (Emergency Circumstances) RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-15015 December 2023 Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days ML23339A1762023-12-0505 December 2023 Notification of NRC Baseline Inspection and Request for Information (05000265/2024001) ML23319A3342023-11-20020 November 2023 Regulatory Audit in Support of License Amendment Requests to Adopt TSTF 505, Revision 2 and 10 CFR 50.69 RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 RS-23-113, Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 262023-10-20020 October 2023 Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23206A0382023-09-21021 September 2023 Proposed Alternative to the Requirements of the ASME Code IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 RS-23-089, Sixth Ten-Year Interval Inservice Testing Program2023-09-0505 September 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-086, Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-08-28028 August 2023 Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval SVP-23-038, Owner'S Activity Report Submittal Fifth 10-Year Interval 2023 Refueling Outage Activities2023-08-14014 August 2023 Owner'S Activity Report Submittal Fifth 10-Year Interval 2023 Refueling Outage Activities IR 05000254/20230022023-08-0808 August 2023 Integrated Inspection Report 05000254/2023002 and 05000265/2023002 ML23178A0742023-08-0707 August 2023 Issuance of Amendment Nos. 296 and 292 Adoption of TSTF-416 Low Pressure Coolant Injection (LPCI) Valve Alignment Verification Note Location ML23216A0362023-08-0707 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI ML23216A0562023-08-0404 August 2023 Information Meeting (Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 SVP-23-031, Regulatory Commitment Change Summary Report2023-07-14014 July 2023 Regulatory Commitment Change Summary Report ML23181A1062023-06-30030 June 2023 Postponement- Information Meeting (Open House) with a Question-And-Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23179A1932023-06-28028 June 2023 07122023 Letter-Significant Public Meeting to Discuss NRC End-of-Cycle Performance Assessment of Quad Cities Nuclear Plant for Performance for 2022 Calendar Year IR 05000254/20234012023-06-26026 June 2023 Cyber Security Inspection Report 05000254/2023401 and 05000265/2023401 IR 05000265/20230402023-06-22022 June 2023 Reissue Quad Cities Nuclear Power Station 95001 Supplemental Inspection Supplemental Report 05000265/2023040 and Follow Up Assessment Letter RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23167B1722023-06-16016 June 2023 95001 Supplemental Inspection Report 05000265/2023040 and Follow-Up Assessment Letter RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0808 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23144A3632023-05-26026 May 2023 Information Meeting (Open House) with a Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23033A4042023-05-15015 May 2023 Exemption from the Requirements of 10 CFR Part 2, Section 2.109(B) Related to Submission of Subsequent License Renewal Application Letter IR 05000254/20234022023-05-15015 May 2023 Security Baseline and ISFSI Inspection Reports 05000254/2023402, 05000265/2023402, 07200053/2023401 ML23132A2022023-05-12012 May 2023 Annual Radiological Environmental Operating Report ML23125A0612023-05-0808 May 2023 Proposed Alternative to the Requirements of the ASME Code IR 05000254/20230012023-05-0808 May 2023 Integrated Report 05000254/2023001 and 05000265/2023001 RS-22-067, 10 CFR 50.46 Annual Report2023-05-0404 May 2023 10 CFR 50.46 Annual Report ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 RS-23-068, Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell2023-04-28028 April 2023 Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell SVP-23-018, Radioactive Effluent Release Report for 20222023-04-28028 April 2023 Radioactive Effluent Release Report for 2022 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23110A0622023-04-25025 April 2023 Transmittal of Final Quad Cities Nuclear Power Plant, Unit 1 Accident Sequence Precursor Report (Licensee Event Report 254-2022-001) ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration 2024-02-05
[Table view] |
See also: IR 05000254/2003012
Text
July 22, 2003
Mr. John L. Skolds, President
Exelon Nuclear
Exelon Generation Company, LLC
Quad Cities Nuclear Power Station
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: QUAD CITIES NUCLEAR POWER STATION
NOTIFICATION OF AN NRC TRIENNIAL FIRE PROTECTION BASELINE
INSPECTION 50-254/03-12(DRS); 50-265/03-12(DRS)
Dear Mr. Skolds:
On October 6, 2003, the NRC will begin a triennial fire protection baseline inspection at the
Quad Cities Nuclear Power Station. This inspection will be performed in accordance with the
NRC baseline Inspection Procedure 71111.05.
The schedule for the inspection is as follows:
- Information gathering visit - September 17-19, 2003
- On-site inspection activity - October 6-10, 2003 and October 20-24, 2003
The purpose of the information gathering visit is: (1) to obtain information and documentation
needed to support the inspection; (2) to become familiar with the Quad Cities Nuclear Power
Station fire protection programs, fire protection features, post-fire safe shutdown capabilities
and plant layout; and (3) to arrange administrative details such as office space, availability of
knowledgeable office personnel and to ensure unescorted site access privileges.
Experience has shown that the baseline fire protection inspections are extremely resource
intensive both for the NRC inspectors and the licensee staff. In order to minimize the
inspection impact on the site and to ensure a productive inspection for both organizations, we
have enclosed a request for documents needed for the inspection. These documents have
been divided into four groups. The first group lists information necessary to aid the inspection
team in choosing specific focus areas for the inspection. It is requested that this information be
provided to the lead inspector via mail or electronically no later than September 12, 2003. The
second group lists information necessary to ensure that the inspection team is adequately
prepared for the inspection. This information should be available on-site no later than
September 17, 2003. The third group of requested documents are those items that the team
will review, or need access to, during the inspection. Please have this information available by
the first day of the on-site portion of the inspection (October 6, 2003). The fourth group lists
information necessary to aid the inspection team in tracking issues identified as a result of the
J. Skolds -2-
inspection. It is requested that this information be provided to the lead inspector as the
information is generated during the inspection. It is important that all of these documents are
up to date and complete in order to minimize the number of additional documents requested
during the preparation and/or the onsite portions of the inspection.
The lead inspector for this inspection is Ronald A. Langstaff. We understand that our
regulatory contact for this inspection is Mr. Fuhs of your organization. If there are any
questions about the inspection or the material requested, please contact the lead inspector at
(630) 829-9747 or via e-mail at ral4@nrc.gov.
In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter and
its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRCs
document system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Julio F. Lara, Chief
Electrical Engineering Branch
Division of Reactor Safety
Docket Nos. 50-254; 50-265
License Nos. DPR-29; DPR-30
Enclosure: Fire Protection Inspection Document Request
See Attached Distribution
J. Skolds -2-
inspection. It is requested that this information be provided to the lead inspector as the
information is generated during the inspection. It is important that all of these documents are
up to date and complete in order to minimize the number of additional documents requested
during the preparation and/or the onsite portions of the inspection.
The lead inspector for this inspection is Ronald A. Langstaff. We understand that our
regulatory contact for this inspection is Mr. Fuhs of your organization. If there are any
questions about the inspection or the material requested, please contact the lead inspector at
(630) 829-9747 or via e-mail at ral4@nrc.gov.
In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter and
its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRCs
document system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Julio F. Lara, Chief
Electrical Engineering Branch
Division of Reactor Safety
Docket Nos. 50-254; 50-265
License Nos. DPR-29; DPR-30
Enclosure: Fire Protection Inspection Document Request
See Attached Distribution:
DOCUMENT NAME: C:\ORPCheckout\FileNET\ML032100641.wpd
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy
OFFICE RIII RIII RIII RIII
NAME RLangstaff:tr MRing JLara
DATE 07/22/03 07/22/03 07/24/03
OFFICIAL RECORD COPY
INITIAL DOCUMENT REQUEST
FIRE PROTECTION INSPECTION DOCUMENT REQUEST
Inspection Report: 50-254/03-12; 50-265/03-12
Inspection Dates: September 17-19, 2003 (Information Gathering)
October 6-10, 2003 (On-site Inspection Activity)
October 20-24, 2003 (On-site Inspection Activity)
Inspection Procedures: IP 71111.05, Fire Protection
Inspectors: Lead Inspector: R. Langstaff
Team Members: R. Daley
R. Echoles
G. Hausman
Information Requested Prior to the Information Gathering Visit
The following information is requested by September 12, 2003. If you have any questions
regarding this information, please call the lead inspector as soon as possible. All information
may be sent electronically (to R. A. Langstaff, e-mail address ral4@nrc.gov) or provided on
compact disc.
(1) The reactor plant's Individual Plant Examination for External Events (IPEEE) for fire,
results of any post-IPEEE reviews for fire, and listings of actions taken/plant
modifications conducted in response to IPEEE information for fire. Alternatively,
probabilistic risk analyses for fire and associated information, if it exists and is more
recent than the IPEEE.
(2) A list of fire areas requiring alternative shutdown capability, i.e., those areas for which
10 CFR Part 50, Appendix R, Section III.G requirements are satisfied under
Section III.G.3.
Information Requested During the Information Gathering Visit (September 17-19, 2003)
This information is requested to be available on-site during the information gathering visit.
(1) The current version of the Fire Protection Program and Fire Hazards Analysis.
(2) Listing of plant fire protection licensing basis documents.
(3) The NRC Safety Evaluation Reports (SERs) and actual copies of the 50.59 reviews
which form the licensing basis for the reactor plant's post-fire safe shutdown
configuration.
(4) A list of Generic Letter 86-10 evaluations.
1 Enclosure
INITIAL DOCUMENT REQUEST
(5) A list of applicable codes and standards related to the design of plant fire protection
features. The list should include National Fire Protection Association (NFPA) code
versions committed to (i.e. the NFPA codes of record).
(6) A list of plant deviations from code commitments.
(7) Post-fire safe shutdown analyses, including post-fire safe shutdown systems and
separation analysis.
(8) Piping and instrumentation (flow) diagrams showing the components used to achieve
and maintain hot standby and cold shutdown for fires outside the control room and those
components used for those areas requiring alternative shutdown capability.
(9) Plant layout and equipment drawings which identify the physical plant locations of hot
standby and cold shutdown equipment for selected fire zones/areas (to be determined
during information gathering visit).
(10) Plant layout drawings which identify plant fire area delineation, areas protected by
automatic fire suppression and detection, and the locations of fire protection equipment
for selected fire zones/areas (to be determined during information gathering visit).
(11) Listing of open and closed fire protection condition reports (problem identification forms
and their resolution reports) for the past three years.
(12) Listing of fire impairments for the previous year.
(13) Pre-fire plans for selected fire zones/areas (to be determined during information
gathering visit).
(14) Plant operating procedures which would be used and describe shutdown for a
postulated fire in selected fire zones/areas (to be determined during information
gathering visit).
(15) A listing of the protection methodologies identified under 10 CFR Part 50, Appendix R,
Section III.G used to achieve compliance for selected fire zones/areas (to be
determined during information gathering visit). That is, please specify whether 3-hour
rated fire barriers (Section III.G.2.a), 20-foot separation along with detection and
suppression (Section III.G.2.b), 1-hour rated fire barriers with detection and suppression
(Section III.G.2.c), or alternative shutdown capability (Section III.G.3) is used for each
selected fire zone/area.
(16) One-line schematic drawings of the electrical distribution system for 4160 volts -
alternating current (VAC) down to 480 VAC.
(17) One-line schematic drawings of the electrical distribution system for 250 volts - direct
current (VDC) and 125 VDC systems as applicable.
(18) A listing of abbreviations/designators for plant systems.
2 Enclosure
INITIAL DOCUMENT REQUEST
(19) Organization charts of site personnel down to the level of fire protection staff personnel.
(20) A phone list for on-site licensee personnel.
In addition, during the information gathering visit, it is requested that licensee staff be available
for the following:
(1) Informal discussion on plant procedures operators would use in the event of fire and
under what conditions would the plant be shutdown using alternative shutdown
methodology.
(2) Informal discussion on the plants safe shutdown cable routing database and the plant-
wide cable routing database, as applicable.
(3) A tour of alternative shutdown and risk significant fire areas.
Information Requested to be Available on First Day of Inspection (October 6, 2003)
(1) List of the fire protection program implementing procedures (e.g. administrative controls,
surveillance testing, fire brigade).
(2) List of maintenance and surveillance testing procedures for alternative shutdown
capability and fire barriers, detectors, pumps and suppression systems.
(3) List of maintenance procedures which routinely verify fuse breaker coordination in
accordance with the post-fire safe shutdown coordination analysis.
(4) List of procedures/instructions that control the configuration of the reactor plant's fire
protection program, features, and post-fire safe shutdown methodology and system
design.
(5) List of procedures/instructions that govern the implementation of plant modifications,
maintenance, and special operations, and their impact on fire protection.
(6) Coordination calculations and/or justifications that verify fuse/breaker coordination for
selected fire zones/areas (to be determined during information gathering visit) that are
fed off of the same electrical buses as components in the protected safe shutdown train.
(7) Significant fire protection and post-fire safe shutdown related design change package
descriptions (including their associated 10 CFR 50.59 evaluations) and Generic Letter
(GL) 86-10 evaluations.
(8) Gaseous suppression system pre-operational testing, if applicable, for selected fire
zones/areas (to be determined during information gathering visit).
3 Enclosure
INITIAL DOCUMENT REQUEST
(9) Hydraulic calculations and supporting test data which demonstrate operability for water
suppression systems, if applicable, for selected fire zones/areas (to be determined
during information gathering visit).
(10) Alternating current (AC) coordination calculations for 4160 VAC down to 480 VAC
electrical systems.
(11) The three most recent fire protection Quality Assurance (QA) audits and/or fire
protection self-assessments.
(12) Corrective action documents (e.g. condition reports, including status of corrective
actions) generated as a result of the three most recent fire protection Quality Assurance
(QA) audits and/or fire protection self-assessments.
Information Requested to Be Provided Throughout the Inspection
(1) Copies of any corrective action documents generated as a result of the teams questions
or queries during this inspection.
(2) Copies of the list of questions submitted by the team members and the status/resolution
of the information requested (provide daily during the inspection to each team member).
4 Enclosure
J. Skolds -3-
cc w/encl: Site Vice President - Quad Cities Nuclear Power Station
Quad Cities Nuclear Power Station Plant Manager
Regulatory Assurance Manager - Quad Cities
Chief Operating Officer
Senior Vice President - Nuclear Services
Senior Vice President - Mid-West Regional
Operating Group
Vice President - Mid-West Operations Support
Vice President - Licensing and Regulatory Affairs
Director Licensing - Mid-West Regional
Operating Group
Manager Licensing - Dresden and Quad Cities
Senior Counsel, Nuclear, Mid-West Regional
Operating Group
Document Control Desk - Licensing
Vice President - Law and Regulatory Affairs
Mid American Energy Company
M. Aguilar, Assistant Attorney General
Illinois Department of Nuclear Safety
State Liaison Officer, State of Illinois
State Liaison Officer, State of Iowa
Chairman, Illinois Commerce Commission
D. Tubbs, Manager of Nuclear
MidAmerican Energy Company
J. Skolds -3-
cc w/encl: Site Vice President - Quad Cities Nuclear Power Station
Quad Cities Nuclear Power Station Plant Manager
Regulatory Assurance Manager - Quad Cities
Chief Operating Officer
Senior Vice President - Nuclear Services
Senior Vice President - Mid-West Regional
Operating Group
Vice President - Mid-West Operations Support
Vice President - Licensing and Regulatory Affairs
Director Licensing - Mid-West Regional
Operating Group
Manager Licensing - Dresden and Quad Cities
Senior Counsel, Nuclear, Mid-West Regional
Operating Group
Document Control Desk - Licensing
Vice President - Law and Regulatory Affairs
Mid American Energy Company
M. Aguilar, Assistant Attorney General
Illinois Department of Nuclear Safety
State Liaison Officer, State of Illinois
State Liaison Officer, State of Iowa
Chairman, Illinois Commerce Commission
D. Tubbs, Manager of Nuclear
MidAmerican Energy Company
ADAMS Distribution:
AJM
DFT
CFL
RidsNrrDipmIipb
GEG
HBC
KKB
C. Ariano (hard copy)
DRPIII
DRSIII
PLB1
JRK1
6