ML032050070

From kanterella
Jump to navigation Jump to search
IR 05000483-03-010, on June 2-6, 2003, Union Electric Co. Identification and Resolution of Problems, Mitigating Systems
ML032050070
Person / Time
Site: Callaway Ameren icon.png
Issue date: 07/24/2003
From: Gage P
Operations Branch IV
To: Randolph G
Union Electric Co
References
IR-03-010
Download: ML032050070 (15)


See also: IR 05000483/2003010

Text

July 24, 2003

Garry L. Randolph, Senior Vice

President and Chief Nuclear Officer

Union Electric Company

P.O. Box 620

Fulton, Missouri 65251

SUBJECT:

CALLAWAY PLANT - NRC PROBLEM IDENTIFICATION AND RESOLUTION

INSPECTION REPORT 05000483/2003-010

Dear Mr. Randolph:

On June 6, 2003, the NRC completed a team inspection at your Callaway Plant. The enclosed

report documents the inspection findings which were discussed with you and other members of

your staff on June 6, 2003.

This inspection examined activities conducted under your license as they relate to the

identification and resolution of problems, and compliance with the Commissions rules and

regulations and the conditions of your operating license. Within these areas, the inspection

consisted of selected examination of procedures and representative records, observations of

activities, and interviews with personnel.

On the basis of the sample selected for review, the team concluded that in general, problems

were adequately identified, evaluated, and corrected with some exceptions. One exception

included a failure to promptly identify and correct an industry known deficient condition

affecting the functionality of multiple safety-related circuit breakers. Another exception involved

the failure to promptly identify and correct a voided condition affecting both trains of the

containment spray system even though abnormal system response to surveillance testing was

observed during several occasions dating back to 1995. These failures, reflected some

isolated problems with problem identification, extent of condition reviews, root cause

determinations, and corrective actions. One green finding was identified during this inspection

associated with the safety-related circuit breaker issue discussed above and is being treated as

a noncited violation, consistent with Section VI.A of the Enforcement Policy, and is described in

the subject inspection report. Additionally, a licensee-identified violation, which was of very low

safety significance, is listed in Section 40A7 of this report. If you contest the violations or

significance of these noncited violations, you should provide a response within 30 days of the

date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with copies to the

Regional Administrator, U.S. Nuclear Regulatory Commission, Region IV, 611 Ryan Plaza

Drive, Suite 400, Arlington, Texas 76011; the Director, Office of Enforcement, U.S. Nuclear

Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the

Callaway Plant facility.

Union Electric Company

-2-

In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter, its

enclosure, and your response will be made available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Paul C. Gage, Chief

Operations Branch

Division of Reactor Safety

Docket: 50-483

License: NPF-30

Enclosure:

NRC Inspection Report

50-483/03-03

cc w/enclosure:

Professional Nuclear Consulting, Inc.

19041 Raines Drive

Derwood, Maryland 20855

John ONeill, Esq.

Shaw, Pittman, Potts & Trowbridge

2300 N. Street, N.W.

Washington, D.C. 20037

Mark A. Reidmeyer, Regional

Regulatory Affairs Supervisor

Regulatory Affairs

AmerenUE

P.O. Box 620

Fulton, Missouri 65251

Manager - Electric Department

Missouri Public Service Commission

301 W. High

P.O. Box 360

Jefferson City, Missouri 65102

Union Electric Company

-3-

Ronald A. Kucera, Deputy Director

for Public Policy

Department of Natural Resources

P.O. Box 176

Jefferson City, Missouri 65102

Rick A. Muench, President and

Chief Executive Officer

Wolf Creek Nuclear Operating Corporation

P.O. Box 411

Burlington, Kansas 66839

Dan I. Bolef, President

Kay Drey, Representative

Board of Directors Coalition

for the Environment

6267 Delmar Boulevard

University City, Missouri 63130

Manager

Quality Assurance

AmerenUE

P.O. Box 620

Fulton, Missouri 65251

Jerry Uhlmann, Director

State Emergency Management Agency

P.O. Box 116

Jefferson City, Missouri 65102-0116

Scott Clardy, Director

Section for Environmental Public Health

P.O. Box 570

Jefferson City, Missouri 65102-0570

Manager

Regulatory Affairs

AmerenUE

P.O. Box 620

Fulton, Missouri 65251

Technical Services Branch Chief

FEMA Region VII

2323 Grand Blvd., Suite 900

Kansas City, Missouri 64108-2670

Union Electric Company

-4-

David E. Shafer

Superintendent, Licensing

Regulatory Affairs

AmerenUE

P.O. Box 66149, MC 470

St. Louis, Missouri 63166-6149

Union Electric Company

-5-

Electronic distribution by RIV:

Acting Regional Administrator (TPG)

DRP Director (ATH)

Acting DRS Director (ATG)

Senior Resident Inspector (MSP)

Branch Chief, DRP/B (DNG)

Senior Project Engineer, DRP/B (RAK1)

Staff Chief, DRP/TSS (PHH)

RITS Coordinator (NBH)

Mel Fields (MBF1)

CWY Site Secretary (DVY)

ADAMS:  Yes

 No Initials: ______

 Publicly Available  Non-Publicly Available

 Sensitive

 Non-Sensitive

R:\\_CW\\2003\\CW2003-010RP-MCH.wpd

SRI:DRP/E

RI:DRS/OB

C:DRP/B

C:OB

MCHay

MHaire

DGraves

PGage

/RA/

/RA/ E

/RA/

/RA/

7/2/03

07/23/03

7/23/03

7/24/03

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

ENCLOSURE

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket:

50-483

License:

NPF-30

Report:

05000483/2003-010

Licensee:

Union Electric Company

Facility:

Callaway Plant

Location:

Junction Highway CC and Highway O

Fulton, Missouri

Dates:

June 2-6, 2003

Inspectors:

M.C. Hay, Senior Resident Inspector, Projects Branch B

M. Haire, Operations Engineer, Operations Branch

Approved By:

Paul C. Gage, Chief

Operations Branch

Division of Reactor Safety

-2-

SUMMARY OF FINDINGS

IR 05000483/2003-010; Union Electric Co; 06/02/03-06/06/03; Callaway Plant. Identification

and Resolution of Problems, Mitigating Systems.

The inspection was conducted by a senior resident inspector and an operations engineer. One

green finding of very low safety significance was identified during this inspection and was

classified as a noncited violation. The finding was evaluated using the significance

determination process.

Identification and Resolution of Problems

On the basis of the sample selected for review, the team concluded that problems were

adequately identified, evaluated, and corrected. The team identified a number of examples

pertaining to the failure to promptly identify and correct conditions adverse to quality. One long-

standing issue involving a failure to promptly identify and correct voided conditions affecting

both trains of the containment spray system suction piping following abnormal system response

during surveillance testing on multiple occasions dating back to 1995 was identified by the

team. Problem identification and resolution issues have affected Callaway historically and

corrective actions have been put in place to improve performance. The team noted that

engineering products reviewed effectively supported the corrective action process, were

technically adequate, and provided sufficient justification to support operability for degraded

conditions evaluated.

Cornerstone: Mitigating Systems

Green. The licensee failed to promptly identify, correct, or preclude recurrence of an industry

known potential significant condition adverse to quality associated with failures of Magne-Blast

4160 volt circuit breakers. The breaker failures were the result of a defective contact block

assembly used as control switches in the breaker control circuits.

The failure to promptly identify, correct, or preclude recurrence of the deficient condition from

affecting multiple safety-related components due to failures of Magne-Blast 4160 volt circuit

breakers was determined to be a violation of 10 CFR Part 50, Appendix B, Criterion XVI. This

violation is being treated as a noncited violation consistent with Section VI.A of the NRC

Enforcement Policy. This finding is greater than minor because if left uncorrected this condition

impacts the reliability and availability of all safety-related loads supplied by Magne-Blast 4160

volt circuit breakers. This finding was determined to be of very low safety significance since all

failures reviewed did not result in loss of a safety function for a single train for greater than its

Technical Specification allowed outage time.

Licensee-Identified Violations.

Violations of very low safety significance, which were identified by the licensee have been

reviewed by the inspectors. Corrective actions taken or panned by the licensee have been

entered into the licensees corrective action process.

-3-

Technical Specification 5.4.1requires that the licensee establish, implement, and

maintain written procedures recommended in Regulatory Guide 1.33, Revision 2,

Appendix A, February 1978. Appendix A recommends maintenance procedures.

The failure to follow a maintenance procedure for installing a diesel generator

fuel injector resulting in Diesel Generator B failing a surveillance test and spilling

approximately 100 gallons of fuel oil on November 11, 2002, is being considered

a violation of Technical Specification 5.4.1. This was identified in the licensees

corrective action program as Callaway Action Request 200207472. This finding

is of very low safety significance because it did not result in loss of safety

function of a single train for greater than the Technical Specification allowed

outage time.

REPORT DETAILS

4. OTHER ACTIVITIES (OA)

4OA2 Problem Identification and Resolution

a.

Effectiveness of Problem Identification

(1)

Inspection Scope

The inspectors focused on reviewing items that were characterized in the licensees

corrective action process as requiring engineering evaluation for resolution. The

purpose of selecting these items was to assess the licensees efforts in response to an

NRC identified cross cutting issue that was determined to exist during the 2002

mid-cycle plant performance review. The NRC noted that a major contributor to the

cross cutting issue was inconsistent engineering evaluations that led to multiple

examples of ineffective problem identification and resolution issues. The NRC had

previously performed a Problem Identification and Resolution team inspection in

December of 2002. The results of the inspection are contained in NRC Inspection

Report 50-483/02-03.

The team reviewed approximately 80 items to determine if problems were being properly

identified, characterized, and entered into the corrective action program for evaluation

and resolution. Specifically the inspectors selected approximately 60 Callaway action

requests that were entered into the licensees corrective action process since April 2003.

The inspectors also reviewed several licensee audits and self assessments, including

one audit of the corrective action program. The effectiveness of the audits and

assessments were evaluated by comparing the audit and assessment results against

self-revealing and NRC-identified findings.

The inspectors evaluated the Callaway action requests to determine the licensees

threshold for identifying problems and entering them into the corrective action program.

Also, the licensees efforts in establishing the scope of problems were evaluated by

reviewing pertinent control room logs, work requests, system health reports, action

plans, and select engineering design calculations. The Callaway action requests and

other documents listed in the attachment to this report were used to facilitate the review.

(2)

Findings

The team determined that the licensee was generally effective at identifying problems

and entering them into the corrective action system. This was evidenced by the

relatively few deficiencies identified by external organizations that had not been

previously identified by the licensee during the review period. Licensee audits and

assessments were of good depth and identified issues similar to those that were self-

revealing or raised during previous NRC inspections. Also, during this inspection there

were no instances identified where conditions adverse to quality were being handled

outside the corrective action program.

-2-

b.

Prioritization and Evaluation of Issues

(1)

Inspection Scope

The team reviewed approximately 60 Callaway action requests and supporting

documentation. This effort was accomplished to verify that licensees evaluation of

problems identified considered the full extent of conditions, operability of affected

systems, reportability requirements, generic implications, common causes, and previous

occurrences. In addition, the team reviewed the licensees evaluation of select industry

experience information to assess if issues applicable to the licensees facility were

appropriately addressed.

Specific documents reviewed during this inspection are listed in the attachment to this

report.

(2)

Issues

The issues reviewed by the team revealed that the proper categorization had been

assigned to identified issues. In general, problems were adequately evaluated and

corrected with some exceptions. One exception included a failure to promptly identify

and correct an industry known deficient condition affecting the functionality of multiple

safety-related circuit breakers. Another exception involved the failure to promptly

identify and correct a voided condition affecting both trains of the containment spray

system even though abnormal system response to surveillance testing was observed

during several occasions dating back to 1995. These failures, reflected some isolated

problems with problem identification, extent of condition reviews, root cause

determinations, and corrective actions.

The team reviewed Callaway Action Request 200200694 pertaining to the licensee

identifying an underlying problem associated with the effectiveness of past incident

investigations and/or evaluations to determine the extent of condition for equipment

problems. Although corrective actions to address this condition were still in progress the

team noted that a significant effort was being taken by the licensee to improve

performance in this area. Specifically, the licensee was in the process of developing

clear roles and responsibilities for each layer of management to improve the level of

oversight and guidance and increase the amount of communications between all levels

of the staff. The licensee was also in the process of developing and implementing an

equipment reliability improvement program that was projected to be fully implemented

by June of 2004.

Circuit Breaker Failures

Introduction. The licensee failed to promptly identify, correct, or preclude recurrence of

an industry known potential significant condition adverse to quality associated with

failures of Magne-Blast 4160 volt circuit breakers. The breaker failures were the result

of a defective contact block assembly used as control switches in the breaker control

circuits. The team determined this condition was a noncited violation of 10 CFR Part 50,

Appendix B, Criterion XVI, and a finding of very low safety significance.

-3-

Description. The team reviewed Callaway Action Request 200207398 pertaining to

failure of the motor driven auxiliary feedwater Pump A to start on November 8, 2002.

The root cause of the event was attributed to failure of the supply breaker to close due

to a faulty contact block. The team noted that this failure mechanism was also

attributed to breaker failures that affected component cooling water Pump B on

November 28, 2001, and safety injection Pump A on February 11, 1998. The licensee

also stated that additional failures due to this failure mechanism were documented prior

to 1998.

The team noted that contact block (CR2940 manufactured by GE) was identified as a

component whose reliability was questionable. NRC Information Notices 95-02 and 97-

08 both alerted licensees to the potential failure of GE Magne-Blast medium voltage

breakers to properly operate because of defective GE Type CR2940 contact blocks.

These information notices expected licensees to review this information for applicability

to their facilities and consider actions, as appropriate, to avoid similar problems.

The inspectors noted that these information notices addressed several acceptable

corrective actions that licensees had taken including jumpering out the susceptible

contacts, modification of the circuit, and in cases were these actions were not taken, to

verify continuity of the affected circuit immediately after each breaker closure. The

inspectors noted that continuity of the affected Magne-Blast breakers at Callaway could

be checked by ensuring a white indicating light was lit located in the switchgear rooms.

Callaways corrective actions for this particular issue included replacement of the

contact module every 12 years, and verification of function and contact resistance every

3 years. Also it was documented that equipment operators would verify the white lights

were illuminated during their rounds as required by Operations Procedure ODP-ZZ-

0016E. The inspectors reviewed this procedure and noted that these rounds were

performed once every 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. The inspectors noted no action was required to be taken

immediately following breaker cycling and that failure of the contact module could go

unidentified until an operator performed their routine rounds to the switchgear rooms.

This could result in the potential for not promptly identifying a degraded condition in a

timely manner. In review of the identified failures the team noted that on November 28,

2001, a condition existed where component cooling water pump B was secured at

10:47 am and failure of the contact module was not identified until 2:57pm. In this

example a member of a maintenance team identified that the white light was out.

The team discussed their concerns with the licensee. In response the licensee initiated

Callaway Action Request 200304247 to evaluate feasibility for modification of the circuit

to remove the contact switch from the breaker closing circuit. The licensee also initiated

a control room standing order to verify that the closing circuit light is illuminated

immediately following each 4160 volt Magne-Blast breaker closure.

Analysis. The failure to promptly identify, correct, or preclude recurrence of the

deficient condition from affecting multiple safety-related components due to failures of

Magne-Blast 4160 volt circuit breakers was determined to be a violation of 10 CFR Part 50, Appendix B, Criterion XVI. This violation is being treated as a noncited violation

consistent with Section VI.A of the NRC Enforcement Policy. This finding is greater than

minor because if left uncorrected this condition could impact the reliability and

-4-

availability of all safety-related loads supplied by Magne-Blast 4160 volt circuit breakers.

This finding was determined to be of very low safety significance since all failures

reviewed did not result in loss of a safety function for a single train for greater than its

Technical Specification Allowed Outage Time.

Enforcement. Title 10 of the Code of Federal Regulations, Part 50, appendix B,

Criterion XVI, Corrective Actions, requires that Measures be established to assure

that conditions adverse to quality, such as failures, malfunctions, deficiencies,

deviations, defective material and equipment, and nonconformances are promptly

identified and corrected. In the case of significant conditions adverse to quality, the

measures shall assure that the cause of the condition is determined and corrective

action taken to preclude repetition. Contrary to the above, the licensee failed to

promptly identify, correct, or preclude recurrence of the deficient condition from affecting

multiple safety-related components due to failures of Magne-Blast 4160 volt circuit

breakers. Because of the very low safety significance and the licensees action to place

the issue in their corrective action program (Callaway Action Request 200304247), this

violation is being treated as a noncited violation in accordance with Section VI.A.1 of the

NRC Enforcement Policy (05000483/2003010-01).

Containment Spray System Voiding

The team reviewed Callaway Action Request 200303918 pertaining to abnormal system

response that was identified during surveillance testing of containment spray Pump B on

May 22, 2003. This Callaway action request documented that following the start of the

containment spray pump, low motor current, nonexistent discharge pressure and very

little flow noise through the piping were observed for approximately 5 minutes.

Following the initial 5 minutes all indications returned to normal. Operations then re-

performed the surveillance, determined the problem was caused by a plugged sensing

line, and declared the pump operable. The team noted that questioning by the NRC

resident inspectors, who were concerned that voiding conditions could be affecting the

containment spray system, resulted in the licensee declaring the system inoperable.

The licensee subsequently determined that gas voiding of the suction piping had

occurred.

The team noted that this condition had previously been identified by the licensee on four

other occasions dating back to 1995, however they had failed to effectively determine

the root cause and implement effective corrective actions to preclude recurrence. The

team noted that the licensee was in the process of evaluating the root causes and

extent of this condition during the inspection. This issue will be dispositioned in NRC

Inspection Report 05000483/2003-004.

c.

Effectiveness of Corrective Actions

(1)

Inspection Scope

The team reviewed a variety of documentation to verify that the appropriate corrective

actions had been identified and implemented in a timely manner commensurate with the

safety significance of the issue, including corrective actions to address common-cause

or generic concerns. The team also evaluated the timeliness and adequacy of

-5-

operability evaluations. The team reviewed corrective actions planned and implemented

by the licensee and sampled technical issues to determine whether adequate decisions

related to structure, system, and component operability were made by engineering. A

listing of specific documents reviewed during this inspection is included in the

attachment to this report.

(2)

Issues

The team determined that the majority of conditions adverse to quality were effectively

resolved in a timely manner. This conclusion was supported by the relatively few

examples (described in previous section) of repetitive issues identified that were a result

of ineffective corrective actions. The team determined that engineering products

supporting the corrective action process were timely, technically adequate, and provided

sufficient justification to support operability for degraded conditions.

4OA6 Exit Meeting

The team discussed the findings with Mr. Gary Randolf, Senior Vice President,

Generation, and other members of the licensees staff on June 6, 2003. Licensee

management did not identify any materials examined during the inspection as

proprietary.

4OA7 Licensee Identified Findings

The following violation of very low safety significance (Green) was identified by the

licensee and is a violation of NRC requirements which meet the criteria of Section VI of

the NRC Enforcement Policy, NUREG-1600, for being dispositioned as a noncited

violation.

Technical Specification 5.4.1requires that the licensee establish, implement, and

maintain written procedures recommended in Regulatory Guide 1.33, Revision 2,

Appendix A, February 1978. Appendix A recommends maintenance procedures.

The failure to follow a maintenance procedure for installing a diesel generator

fuel injector resulting in Diesel Generator B failing a surveillance test and spilling

approximately 100 gallons of fuel oil on November 11, 2002, is being considered

a violation of Technical Specification 5.4.1. This was identified in the licensees

corrective action program as Callaway Action Request 200207472. This finding

is of very low safety significance because it did not result in loss of safety

function of a single train for greater than the Technical Specification Allowed

Outage Time.

ATTACHMENT

PARTIAL LIST OF PERSONS CONTACTED

Licnesee

H. Bond, Supervisor, Operating Experience

S. Bond, Superintendent, System Engineering

M. Evans, Manager, Nuclear Engineering

B. Farnam, Superintendent, Health Physics

F. Forck, Supervisor, Human Performance

J. Hiller, Engineer

G. Hughes, Supervising Engineer, Quality Assurance

J. McGraw, Superintendent, Design Engineering

S. Menger, Acting Supervisor, Quality Assurance

K. Mills, Supervising Engineer, Safety Analysis

G. Randolf, Senior Vice President, Generation

M. Reidmeyer, Supervisor, Nuclear Regulatory Affairs

D. Rickard, Nuclear Engineering

T. Robertson, Corrective Action Program Engineer

R. Roseling, Superintendent, Training

S. Sandboth, Superintendent, Operations

J. Schnack, Supervising Engineer, Corrective Action Program

C. Slizewski, Acting Manager, Quality Assurance

NRC

M. Peck, Senior Resident Inspector, Callaway

J. Hanna, Resident Inspector, Callaway

R. Wink, Supervising Engineer, System Engineering

W. Witt, Plant Manager

ITEMS OPENED AND CLOSED

Opened and Closed

50-483/0310-01

NCV

Failure to implement effective corrective actions

DOCUMENTS REVIEWED

Procedures

Administrative Procedure APA-ZZ-00107, Review of Current Industry Operating Experience,

Revision 8

Administrative Procedure APA-ZZ-00320, Processing Work Requests, Revision 25

Work Management Procedure APA-ZZ-00322, Integrated Work Management Process

Description, Revision 0

-2-

Administrative Procedure APA-ZZ-00500, Corrective Action Program, Revision 34

Administrative Procedure APA-ZZ-00520, Reporting Requirements and Responsibilities,

Revision 17

Administrative Procedure APA-ZZ-00542, Event Review, Revision 5

Corrective Action Documents

CAR200206058

CAR200206287

CAR200206301

CAR200206359

CAR200206470

CAR200206585

CAR200206763

CAR200206766

CAR200206979

CAR200207024

CAR200207280

CAR200207471

CAR200207472

CAR200207806

CAR200207844

CAR200207933

CAR200208044

CAR200208066

CAR200300053

CAR200300824

CAR200300935

CAR200300943

CAR200301276

CAR200301690

CAR200301933

CAR200301941

CAR200302325

CAR200303370

CAR200206237

CAR200206323

CAR200206413

CAR200206839

CAR200206908

CAR200206970

CAR200207340

CAR200207398

CAR200207456

CAR200207492

CAR200207518

CAR200207602

CAR200207742

CAR200207751

CAR200208017

CAR200208392

CAR200300810

CAR200300954

CAR200300984

CAR200301515

CAR200301779

CAR200302450

CAR200303110

Other Documents Reviewed

SEGR 02-10-005, ITR of the operability process

SPO3-004, QA audit, Corrective action program

SPO2-029, QA audit, Material Qualification

APO3-001, Design Control