Letter Sequence RAI |
---|
|
|
MONTHYEARML0319605302003-07-31031 July 2003 Request for Additional Information, Jet Pump Operability Surveillance Requirements and Correction to Reference Cited in TS 4.11.C.1 Project stage: RAI ML0323104492003-08-0707 August 2003 Response to NRC Request for Additional Information in Support of Proposed Changes to Jet Pump Operability Surveillance Requirements Project stage: Response to RAI ML0403307902004-01-30030 January 2004 License Amendment, Tech Spec Pages Project stage: Other ML0332903472004-01-30030 January 2004 License Amendment, Issuance of Amendment, Jet Pump Surveillance Requirements Project stage: Approval 2003-08-07
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML21223A2422021-08-16016 August 2021 Enclosure - Pilgrim Nuclear Power Station - Request for Additional Information Regarding Pilgrim - License Amendment Request Independent Spent Fuel Storage Installation Only Emergency Plan ML21161A1072021-07-0909 July 2021 Request for Additional Information Regarding Pilgrim License Amendment Request ISFSI Only Emergency Plan ML21013A5232021-01-15015 January 2021 Request for Additional Information Regarding the Request to Change the Physical Security Plan - Alternative Measures ML20297A2382020-10-22022 October 2020 Fleet DQAP RAIs - Enclosure ML20297A2372020-10-22022 October 2020 Request for Additional Information - HDI Fleet Decommissioning Quality Assurance Program ML20142A2422020-05-26026 May 2020 Acceptance of Requested Licensing Action Physical Security Plan Revision and License Amendment Request to Incorporate Additional Independent Spent Fuel Storage Installation with Requests for Additional Information ML20280A1912020-04-17017 April 2020 Request for Additional Information- Clarifying Information for Pilgrim ISFSI Physical Security Amendment Application ML19207B3662019-07-26026 July 2019 NRR E-mail Capture - Pilgrim - RAI Direct and Indirect Transfer of Lic.; Conforming Lic. Amend.; Req. for Exemption 10 CFR 50.82(A)(8)(I)(A) for Holtec Decom. International, Llc ML19154A5242019-06-0303 June 2019 NRR E-mail Capture - RAI - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML19086A3492019-03-21021 March 2019 NRR E-mail Capture - Pilgrim Power Station - Request for Additional Information Application for Order Consenting to Direct and Indirect Transfers of Control of Licenses and Approving Conforming License Amendment (EPID: L-2018-LL0-0003) ML19036A6512019-02-0404 February 2019 NRR E-mail Capture - RAI - Pilgrim EP Exemption ML18320A1292018-11-16016 November 2018 NRR E-mail Capture - Request for Additional Information (RAI) - Pilgrim Post-Decommissioning Technical Specifications (PDTS) License Amendment Request (LAR) ML18323A1192018-11-15015 November 2018 CAL 5 Document Request #2 ML18317A2202018-11-11011 November 2018 NRR E-mail Capture - (External_Sender) Questions and Comments Regarding Pilgrim EP Exemption RAI, October 16, 2018 ML18317A2192018-11-0808 November 2018 NRR E-mail Capture - (External_Sender) RAI EP 11.06.18-Question ML18310A0212018-11-0606 November 2018 NRR E-mail Capture - RAI - Pilgrim EP Exemption ML18289A4072018-10-16016 October 2018 NRR E-mail Capture - RAIs - Pilgrim EP Exemption ML18285A8182018-10-12012 October 2018 NRR E-mail Capture - for Your Action: RAIs - Pilgrim - LAR - EP and EAL Scheme to Address Permanently Defueled Condition ML18124A1392018-05-0404 May 2018 NRR E-mail Capture - RAI - Pilgrim ERO Staffing License Amendment Request ML18094B0922018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to B. S. Ford RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for ISFSI Docket Nos.: 72-43, 72-51, 72-1044, 72-07, 72-12, and 72-59) ML18005A5422018-01-0505 January 2018 NRR E-mail Capture - Second Round of RAI for DAEC Fifth Inservice Inspection Interval Program Plan, Relief Request RR-03 - EPID: L-2017-LLR-0110 ML16347A0042016-12-0909 December 2016 NRR E-mail Capture - Pilgrim: Request for Additional Information for Relief Requests on Volumetric Exam Requirements, PNPS-ISI-001, 002 and 003 ML16013A0642016-01-13013 January 2016 NRR E-mail Capture - Request for Additional Information Entergy CNRO-2015-00023 - Revision to Entergy Quality Assurance Program Manual (Fleet Submittal CAC Nos. MF7086-MF7097) ML15341A1662015-12-0707 December 2015 NRR E-mail Capture - Entergy Fleet RR-EN-15-1, Request for Additional Information (CACs MF6341-MF6349) ML15211A6612015-07-30030 July 2015 Licensed Operator Positive Fitness-For-Duty-Test ML15051A0322015-02-25025 February 2015 Request for Additional Information Regarding the Safety Limit Minimum Critical Power Ratio License Amendment Request ML14342A0942014-12-17017 December 2014 Request for Additional Information Regarding Relief Request PRR-24, Nozzle-to-Vessel Welds and Nozzle Inner Radii Examinations ML14042A0432014-02-18018 February 2014 Request for Additional Information Regarding Safety Limits to Resolve Pressure Regulator Fail-Open Transient License Amendment Request ML13333A9102013-12-0505 December 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool ins ML13323B4702013-11-25025 November 2013 Request for Additional Information Regarding Relief Request PRR-22 ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13179A4622013-07-0505 July 2013 Entergy Nuclear Operations, Inc., Decommissioning Funding Status Report Request for Additional Information Regarding the Decommissioning Funding Status Report ML13182A4252013-07-0101 July 2013 Request for Additional Information E-mail from R.Guzman to W.Lobo PR-03 and PR-05 Fifth Ten-Year Inservice Testing (IST) Program ML13165A2762013-06-20020 June 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (NRC Order EA-12-051) ML12278A3862012-10-0404 October 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2, and 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford, Request for Additional Information, Round 2, Amendment Request to Revise QA Program Manual and Staff Qualification TSs ML1209604492012-04-0505 April 2012 ANO 1 & 2, Big Rock, FitzPatrick, GGNS, Indian Point 1, 2 & 3, Palisades, Pilgrim, RBS, Vermont Yankee, and Waterford - Request for Additional Information, Revise Quality Assurance Program Manual and Staff Qualification Technical Specificat ML1208601472012-03-26026 March 2012 Request for Additional Information - Pilgrim Nuclear Power Station Revision to Condensate Storage Tank Low Level Trip Setpoint ML12056A0512012-03-12012 March 2012 Enclosure 5 - Recommendation 9.3: Emergency Preparedness ML12056A0502012-03-12012 March 2012 Enclosure 4 - Recommendation 2.3: Flooding ML12056A0482012-03-12012 March 2012 Enclosure 2 - Recommendation 2.1: Flooding ML12056A0492012-03-12012 March 2012 Enclosure 3 - Recommendation 2.3: Seismic ML12056A0472012-03-12012 March 2012 Enclosure 1 - Recommendation 2.1: Seismic ML1132502282011-11-22022 November 2011 Request for Additional Information, Relief Request No. PRR-21 ML1132202342011-11-21021 November 2011 Request for Additional Information 60-Day Response to Bulletin 2011-01, Mitigating Strategies, ML1114402342011-05-25025 May 2011 Request for Additional Information to Support the Review of 2011 Decommissioning Funding Status Report ML1108202082011-04-11011 April 2011 Summary of Telephone Conference Call Held on March 23, 2011, Between the USNRC and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application ML1106101872011-03-0303 March 2011 Request for Additional Information to Support the Review of Pilgrim Nuclear Power Station Cyber Security Plan (Id: 2.10.034) ML1105403302011-02-15015 February 2011 Response to Request for Additional Information (Rai), Dated January 5, 2011 on the Cyber Security Plan ML1100900272011-01-10010 January 2011 Request for Additional Information Revision to TS for Setpoint and Setpoint Tolerance Increase for Safety Relief Valves and Spring Safety Valves, and Related Changes (ME3543) ML1034105062011-01-0707 January 2011 December 1, 2010, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc., Concerning the Pilgrim Nuclear Power Station License Renewal Application 2021-08-16
[Table view] |
Text
July 31, 2003 Mr. Michael Kansler President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601
SUBJECT:
PILGRIM NUCLEAR POWER STATION - REQUEST FOR ADDITIONAL INFORMATION RE: JET PUMP OPERABILITY SURVEILLANCE REQUIREMENTS AND CORRECTION TO REFERENCE CITED IN TS 4.11.C.1 (TAC NO. MB7950)
Dear Mr. Kansler:
By application dated December 10, 2002, as replaced by application dated January 30, 2003, Entergy Nuclear Operations, Inc. (ENO) submitted a license amendment request for proposed changes to the Pilgrim Nuclear Power Station Technical Specification 4.6.E, associated with jet pump operability surveillance requirements.
The U.S. Nuclear Regulatory Commission staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter and was sent to Mr. Bryan Ford, of your staff, by e-mail on June 23, 2003. During a conference call held with your staff on July 28, 2003, Mr. Ford indicated that ENO would respond to the requested information by August 8, 2003. If circumstances result in the need to revise the response date, please contact me at (301) 415-8474.
Sincerely,
/RA/
Travis L. Tate, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-293
Enclosure:
Request for Additional Information cc w/encl: See next page
July 31, 2003 Mr. Michael Kansler President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601
SUBJECT:
PILGRIM NUCLEAR POWER STATION - REQUEST FOR ADDITIONAL INFORMATION RE: JET PUMP OPERABILITY SURVEILLANCE REQUIREMENTS AND CORRECTION TO REFERENCE CITED IN TS 4.11.C.1 (TAC NO. MB7950)
Dear Mr. Kansler:
By application dated December 10, 2002, as replaced by application dated January 30, 2003, Entergy Nuclear Operations, Inc. (ENO) submitted a license amendment request for proposed changes to the Pilgrim Nuclear Power Station Technical Specification 4.6.E, associated with jet pump operability surveillance requirements.
The U.S. Nuclear Regulatory Commission staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter and was sent to Mr. Bryan Ford, of your staff, by e-mail on June 23, 2003. During a conference call held with your staff on July 28, 2003, Mr. Ford indicated that ENO would respond to the requested information by August 8, 2003. If circumstances result in the need to revise the response date, please contact me at (301) 415-8474.
Sincerely,
/RA/
Travis L. Tate, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-293
Enclosure:
Request for Additional Information cc w/encl: See next page DISTRIBUTION:
PDI-2 Reading C. Anderson, RI PUBLIC C. Raynor J. Clifford T. Tate F. Arner, RI J. Bobiak, RI F. Akstulewicz G. Thomas ADAMS Accession Number: ML031960530 OFFICE PDI-2/PM PDI-2/LA PDI-2/SC NAME TTate CRaynor JClifford DATE 7/30/03 7/29/03 7/31/03 OFFICIAL RECORD COPY
REQUEST FOR ADDITIONAL INFORMATION PILGRIM NUCLEAR POWER STATION REQUEST FOR AMENDMENT TO THE TECHNICAL SPECIFICATIONS, JET PUMP OPERABILITY SURVEILLANCE AND CORRECTION TO REFERENCE CITED IN TS 4.11.C.1 In your application dated December 10, 2002, as replaced by application dated January 30, 2003, you reference the guidance in NUREG-1434, Standard Technical Specifications (STS) for BWR/6 in your proposed change instead of the requirements in NUREG-1433, STS for BWR/4, at several sections in the submittal. In BWR/6 plants, flow control valves are used rather than the variable pump speed for recirculation flow control. Pilgrim utilizes the variable pump speed design for flow control. Please provide an explanation of why Entergy proposes the use of the jet pump operability requirements in NUREG-1434, STS for BWR/6, rather than STS for BWR/4. Please address the impact, if any, of the difference in flow control for the pumps on your proposed changes.
Enclosure
Pilgrim Nuclear Power Station cc:
Resident Inspector Mr. Steve Brennion U. S. Nuclear Regulatory Commission Supt., Regulatory & Industry Affairs Pilgrim Nuclear Power Station Entergy Nuclear Operations, Inc.
Post Office Box 867 Pilgrim Nuclear Power Station Plymouth, MA 02360 600 Rocky Hill Road, M/S 1 Plymouth, MA 02360-5508 Chairman, Board of Selectmen 11 Lincoln Street Mr. Jack Alexander Plymouth, MA 02360 Manager, Reg. Relations and Quality Assurance Chairman, Duxbury Board of Selectmen Pilgrim Nuclear Power Station Town Hall 600 Rocky Hill Road 878 Tremont Street Plymouth, MA 02360-5599 Duxbury, MA 02332 Mr. David F. Tarantino Office of the Commissioner Nuclear Information Manager Massachusetts Department of Pilgrim Nuclear Power Station Environmental Protection 600 Rocky Hill Road One Winter Street Plymouth, MA 02360-5599 Boston, MA 02108 Ms. Jane Perlov Office of the Attorney General Secretary of Public Safety One Ashburton Place Executive Office of Public Safety 20th Floor One Ashburton Place Boston, MA 02108 Boston, MA 02108 Dr. Robert M. Hallisey, Director Mr. Stephen J. McGrail, Director Radiation Control Program Attn: James Muckerheide Commonwealth of Massachusetts Massachusetts Emergency Management Executive Offices of Health and Agency Human Services 400 Worcester Road 174 Portland Street Framingham, MA 01702-5399 Boston, MA 02114 Chairman Regional Administrator, Region I Nuclear Matters Committee U. S. Nuclear Regulatory Commission Town Hall 475 Allendale Road 11 Lincoln Street King of Prussia, PA 19406 Plymouth, MA 02360 Mr. John M. Fulton Mr. William D. Meinert Assistant General Counsel Nuclear Engineer Entergy Nuclear Operations, Inc. Massachusetts Municipal Wholesale 440 Hamilton Avenue Electric Company White Plains, NY 10601 P.O. Box 426 Ludlow, MA 01056-0426
Pilgrim Nuclear Power Station (Cont.)
cc:
Mr. Gary Taylor Mr. John Kelly Chief Executive Officer Director, Nuclear Safety Assurance Entergy Operations Entergy Nuclear Operations, Inc.
1340 Echelon Parkway 440 Hamilton Avenue Jackson, MS 39213 White Plains, NY 10601 Mr. John Herron Ms. Charlene Faison Sr. VP and Chief Operating Officer Manager, Licensing Entergy Nuclear Operations, Inc. Entergy Nuclear Operations, Inc.
440 Hamilton Avenue 440 Hamilton Avenue White Plains, NY 10601 White Plains, NY 10601 Mr. Michael A. Balduzzi Director of Oversight Site Vice President Entergy Nuclear Operations, Inc.
Entergy Nuclear Operations, Inc. 440 Hamilton Avenue Pilgrim Nuclear Power Station White Plains, NY 10601 600 Rocky Hill Road Plymouth, MA 02360-5508 Senior Resident Inspector U.S. Nuclear Regulatory Commission Mr. William J. Riggs Pilgrim Nuclear Power Station Director, Nuclear Assessment 600 Rocky Hill Road Entergy Nuclear Operations, Inc. Mail Stop 66 Pilgrim Nuclear Power Station Plymouth, MA 02360-5508 600 Rocky Hill Road Plymouth, MA 02360-5508 Ms. Stacey Lousteau Treasury Department Mr. Bryan S. Ford Entergy Services, Inc.
Manager, Licensing 639 Loyola Avenue, Mail Stop L-ENT-15E Entergy Nuclear Operations, Inc. New Orleans, LA 70113 Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Mr. Dan Pace Vice President, Engineering Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Randall Edington Vice President, Operations Support Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601