Senior Reactor Operator Examinations - Indian Point Station, Unit 3 Dtd 6/13/03
ML031640396
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 06/13/2003
From: Conte R
NRC/RGN-I/DRS/OSB
To: Dacimo F
Entergy Nuclear Operations
Shared Package
ML031640396 List:
References
Download: ML031640396 (5)


Text

June 13, 2003 Mr. Fred R. Dacimo Vice President - Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 295 Broadway, Suite 2 P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

SENIOR REACTOR OPERATOR EXAMINATIONS -

INDIAN POINT STATION, UNIT 3

Dear Mr. Dacimo :

In telephone conversations on May 28, 2003, between Mr. Alan Blamey, Examiner/Inspector, and Mr. Frank Wilson, Indian Point Operations Training Manager, arrangements were made for the administration of licensing examinations at Indian Point Station Unit 3, during the week of December 8, 2003.

As agreed during the telephone conversation, the NRC will prepare the examinations based on the guidelines in the January 2003 Draft Revision 9 of NUREG-1021, Operator Licensing Examination Standards for Power Reactors. The NRC regional office will discuss with your staff any changes that might be necessary before the examinations are administered. Your staff will be given the opportunity to review the examinations during the week of November 10, 2003.

To meet the above schedule, it will be necessary for your staff to furnish the reference materials identified in Attachment 2 of ES-201 by June 23, 2003. All materials should be complete and ready-to-use. Any delay in receiving the required reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.

In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),

Mr. Fred R. Dacimo 2

and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018, which expires on May 31, 2003. The public reporting burden for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at SLF@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.

Thank you for your cooperation in this matter. Mr. Frank Wilson has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRCs examination procedures and guidelines, please contact Mr. Alan Blamey at (610) 337-5366, or me at (610) 337-5183.

Sincerely,

/RA/

Richard J. Conte, Chief Operational Safety Branch Division of Reactor Safety Docket No.

50-286 License No.

DPR-64

Mr. Fred R. Dacimo 3

cc w/encl:

G. J. Taylor, Chief Executive Officer, Entergy Operations M. R. Kansler, President - Entergy Nuclear Operations, Inc.

J. Herron, Senior Vice President and Chief Operations Officer C. Schwarz, General Manager - Plant Operations D. Pace, Vice President, Engineering R. Edington, Vice President, Operations Support J. McCann, Manager, Nuclear Safety and Licensing J. Kelly, Director, Nuclear Safety Assurance J. Comiotes, Director, Nuclear Safety Assurance C. Faison, Manager, Licensing H. Salmon, Jr., Director of Oversight F. Wilson, Manager - Operation Training J. Fulton, Assistant General Counsel, Entergy Nuclear Operations, Inc.

P. Smith, Acting President, New York State Energy, Research, and Development Authority J. Spath, Program Director, New York State Energy Research and Development Authority P. Eddy, Electric Division, New York State Department of Public Service C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law T. Walsh, Secretary, NFSC, Entergy Nuclear Operations, Inc.

D. ONeill, Mayor, Village of Buchanan J. G. Testa, Mayor, City of Peekskill R. Albanese, Executive Chair, Four County Nuclear Safety Committee S. Lousteau, Treasury Department, Entergy Services, Inc.

Chairman, Standing Committee on Energy, NYS Assembly Chairman, Standing Committee on Environmental Conservation, NYS Assembly Chairman, Committee on Corporations, Authorities, and Commissions M. Slobodien, Director, Emergency Planning B. Brandenburg, Assistant General Counsel P. Rubin, Operations Manager Assemblywoman Sandra Galef, NYS Assembly C. Terry, Niagara Mohawk Power Corporation County Clerk, Westchester County Legislature A. Spano, Westchester County Executive R. Bondi, Putnam County Executive C. Vanderhoef, Rockland County Executive E. A. Diana, Orange County Executive T. Judson, Central NY Citizens Awareness Network M. Elie, Citizens Awareness Network D. Lochbaum, Nuclear Safety Engineer, Union of Concerned Scientists Public Citizen's Critical Mass Energy Project M. Mariotte, Nuclear Information & Resources Service F. Zalcman, Pace Law School, Energy Project L. Puglisi, Supervisor, Town of Cortlandt Congresswoman Sue W. Kelly Congresswoman Nita Lowey Senator Hilary Rodham Clinton

Mr. Fred R. Dacimo 4

Senator Charles Schumer J. Riccio, Greenpeace A. Matthiessen, Executive Director, Riverkeepers, Inc.

M. Kapolwitz, Chairman of County Environment & Health Committee A. Reynolds, Environmental Advocates M. Jacobs, Director, Longview School D. Katz, Executive Director, Citizens Awareness Network P. Gunter, Nuclear Information & Resource Service P. Leventhal, The Nuclear Control Institute K. Copeland, Pace Environmental Litigation Clinic R. Witherspoon, The Journal News W. DiProfio, PWR SRC Consultant D. C. Poole, PWR SRC Consultant W. T. Russell, PWR SRC Consultant

Mr. Fred R. Dacimo 5

Distribution w/encl:

Region I Docket Room (with concurrences)

P. Drysdale, SRI - NRC Resident Inspector H. Miller, RA J. Wiggins, DRA H. Nieh, RI EDO Coordinator R. Laufer, NRR P. Milano, PM, NRR G. Vissing, Backup PM, NRR P. Eselgroth, DRP W. Cook, DRP R. Martin, DRP A. Blamey, DRS, Chief Examiner C. Buracker, DRS (OL Facility File)

R. Conte, DRS DRS Files DOCUMENT NAME: G:\\OSB\\Blamey\\IP3Dec2003\\120DAYEXAMLTR.WPD ADAMS PKG: ML031480347 After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS/OSB RI/DRS/OSB RI/DRS/OSB NAME CBuracker ABlamey RConte DATE 06/11/03 06/10/03 06/13/03 06/ /03 06/ /03 OFFICIAL RECORD COPY