June 25, 2003 Mr. Lew W. Myers Chief Operating Officer FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - BULLETIN 2002-01, REACTOR PRESSURE VESSEL HEAD DEGRADATION AND REACTOR COOLANT PRESSURE BOUNDARY INTEGRITY, 15-DAY RESPONSE (TAC NO. MB4542)
Dear Mr. Myers:
On March 18, 2002, the staff issued Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, to the industry requesting that addressees provide information related to the structural integrity of the reactor coolant pressure boundary, including the reactor pressure vessel head, and the extent to which inspections have been undertaken to satisfy applicable regulatory requirements.Bulletin 2002-01 also required licensees to provide the basis for concluding that plans for future inspections of the reactor coolant pressure boundary will satisfy applicable regulatory requirements at their respective pressurized-water reactor plants. All addressees were requested to respond to Items 1.A.
through E. within 15 days of the Bulletins issuance, or to provide a written response to the Nuclear Regulatory Commission (NRC) in accordance with the provisions of Title 10, Section 50.54(f), of the Code of Federal Regulations (10 CFR 50.54(f)) if they are unable to provide the information or they can not meet the requested completion dates.
You responded to Bulletin 2002-01 by letters dated March 25, 2002, and March 31, 2003. The staff finds that you have provided the information requested for the 15-day response. However, the staff may issue followup questions in order to confirm or verify the information that you have provided. The NRC staff is continuing to review your response to Bulletin 2002-01, specifically Items 2 and 3, following which the staffs review will be complete.
Please contact me on (301) 415-3027 if you have any questions.
Sincerely,
/RA/
Jon B. Hopkins, Sr. Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346 cc: See next page
June 25, 2003 Mr. Lew W. Myers Chief Operating Officer FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 - BULLETIN 2002-01, REACTOR PRESSURE VESSEL HEAD DEGRADATION AND REACTOR COOLANT PRESSURE BOUNDARY INTEGRITY, 15-DAY RESPONSE (TAC NO. MB4542)
Dear Mr. Myers:
On March 18, 2002, the staff issued Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, to the industry requesting that addressees provide information related to the structural integrity of the reactor coolant pressure boundary, including the reactor pressure vessel head, and the extent to which inspections have been undertaken to satisfy applicable regulatory requirements.Bulletin 2002-01 also required licensees to provide the basis for concluding that plans for future inspections of the reactor coolant pressure boundary will satisfy applicable regulatory requirements at their respective pressurized-water reactor plants. All addressees were requested to respond to Items 1.A.
through E. within 15 days of the Bulletins issuance, or to provide a written response to the Nuclear Regulatory Commission (NRC) in accordance with the provisions of Title 10, Section 50.54(f), of the Code of Federal Regulations (10 CFR 50.54(f)) if they are unable to provide the information or they can not meet the requested completion dates.
You responded to Bulletin 2002-01 by letters dated March 25, 2002, and March 31, 2003. The staff finds that you have provided the information requested for the 15-day response. However, the staff may issue followup questions in order to confirm or verify the information that you have provided. The NRC staff is continuing to review your response to Bulletin 2002-01, specifically Items 2 and 3, following which the staffs review will be complete.
Please contact me on (301) 415-3027 if you have any questions.
Sincerely,
/RA/
Jon B. Hopkins, Sr. Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-346 cc: See next page DISTRIBUTION:
PUBLIC AMendiola OGC WBateman PD3-2 R/F JHopkins ACRS ALee EMCB R/F SBloom GGrant, RIII SCoffin THarris ADAMS ACCESSION NO. ML031640072 OFFICE PDIII-2/PM PDIII-2/LA EMCB/Bulletin Lead PDIII-2/SC NAME JHopkins THarris SBloom AMendiola DATE 6/24/2003 6/24 /2003 6/24 /2003 6/24/2003 OFFICIAL RECORD COPY
Davis-Besse Nuclear Power Station, Unit 1 cc:
Mary E. OReilly FirstEnergy Corporation 76 South Main St.
Akron, OH 44308 Manager - Regulatory Affairs FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State - Route 2 Oak Harbor, OH 43449-9760 Director, Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Regional Administrator U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60523-4351 Michael A. Schoppman Framatome ANP 1911 N. Ft. Myer Drive Rosslyn, VA 22209 Resident Inspector U.S. Nuclear Regulatory Commission 5503 North State Route 2 Oak Harbor, OH 43449-9760 Randel J. Fast, Plant Manager FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station 5501 North State - Route 2 Oak Harbor, OH 43449-9760 Dennis Clum Radiological Assistance Section Supervisor Bureau of Radiation Protection Ohio Department of Health P.O. Box 118 Columbus, OH 43266-0118 Carol OClaire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-2206 Zack A. Clayton DERR Ohio Environmental Protection Agency P.O. Box 1049 Columbus, OH 43266-0149 State of Ohio Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Attorney General Department of Attorney General 30 East Broad Street Columbus, OH 43216 President, Board of County Commissioners of Ottawa County Port Clinton, OH 43252 President, Board of County Commissioners of Lucas County One Government Center, Suite 800 Toledo, OH 43604-6506 David Lochbaum, Nuclear Safety Engineer Union of Concerned Scientists 1707 H Street NW, Suite 600 Washington, DC 20006 The Honorable Dennis J. Kucinich United States House of Representatives Washington, D.C. 20515 The Honorable Dennis J. Kucinich, Member United States House of Representatives 14400 Detroit Avenue Lakewood, OH 44107